Bad Faith Claim for Inadequate Investigation Does Not Survive Summary Judgment
May 20, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe insured's claim for bad faith investigation regarding their hail damage claim did not survive the insurer's motion for summary judgment. Amarillo Hospitality Tenant, LLC v. Mass. Bay Ins. Co., 2015 U.S. Dist. LEXIS 56228 (N. D. Tex. April 29, 2015).
A hailstorm caused damage to the Courtyard Marriot. The day after the storm, the insured inspected the roof of the hotel and observed damage to a sign and some aluminum vent tubes. No damage to the roof itself was observed. Subsequently, leaks were found on the tenth floor of the hotel. A public adjuster concluded that the roof had sustained damage during the hailstorm.
The insured filed a claim with Massachusetts Bay Insurance Company. The insurer paid for the cost of repairing the damaged sign. To determine whether the damage to the roof was caused by the hailstorm, the insurer hired Donna Engineering, who conducted two inspections of the roof. Both inspections concluded that the hailstorm did not cause damage to the roof. Consequently, the claim was denied.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
ALERT: COVID-19 / Coronavirus-Related Ransomware and Phishing Attacks
April 13, 2020 —
Christopher E. Ballod & Sean B. Hoar - Digital Insights Lewis Brisbois' Data Privacy & Cybersecurity BlogAs with other events that attract societal attention – whether it be an international sporting event like the Olympics or a natural disaster like the Australian bush fires - criminals often utilize the events to exploit consumers’ fears and, in turn, compromise the cybersecurity of businesses nationwide. With the advent of the Coronavirus, criminals have begun to take advantage of what consumers expect to receive via email to conduct phishing attacks. Criminals are also expected to take advantage of millions of vulnerable remote connections from employee home networks to their corporate networks.
According to Proofpoint Inc., a cybersecurity firm, the use of sophisticated Coronavirus-related “phishing” strategies has been on the rise since January, with new malicious email campaigns surfacing each day. These emails, which appear to come from legitimate organizations, contain content such as advice on combatting the Coronavirus, phony invoices for purchases of face masks and medical supplies, advertisements for products that allegedly treat the illness, and phony alerts from the World Health Organization (WHO) or Centers for Disease Control and Prevention (CDC). When the email recipients open these messages, they unknowingly release malware, which allows the attacker to gain access to their personal information and to compromise the security of their employers’ networks.
The recent emergence of Coronavirus-related “phishing” schemes demonstrates that businesses must remain vigilant. Employees and their employers are particularly vulnerable now, in light of the novel nature of the Coronavirus, the paucity of information concerning the illness, and the rapid and significant manner in which it is spreading. Individuals are thirsty for information and advice, and are eager to take any action necessary to protect themselves and their families.
Reprinted courtesy of
Christopher E. Ballod, Lewis Brisbois and
Sean B. Hoar, Lewis Brisbois
Mr. Ballod may be contacted at Christopher.Ballod@lewisbrisbois.com
Mr. Hoar may be contacted at Sean.Hoar@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Toolbox Talk Series Recap - Undocumented Change Work
October 15, 2024 —
Douglas J. Mackin - The Dispute ResolverIn the August 29, 2024 edition of Division 1's Toolbox Talk Series,
Don Rea presented on the causes of undocumented change order work and what actions parties to a construction project can take to protect themselves, which compliments and reinforces some of the key points from the
May 30, 2024 Toolbox Talk on maximizing profits while experiencing changes during project performance.
Article 7 of AIA A201 General Conditions covers (i) change orders, (ii) constructive change directives, and (iii) “minor changes.” Work that falls outside the scope of the construction contract will often fit into one of these three categories. Rea’s presentation focused on the fact that, regardless of which category applies, proper documentation of the change work is vital.
Read the court decisionRead the full story...Reprinted courtesy of
Douglas J. Mackin, Cozen O’ConnorMr. Mackin may be contacted at
dmackin@cozen.com
Client Alert: Court Settles Conflict between CCP and Rules of Court Regarding Demurrer Deadline Following Amended Complaint
August 20, 2014 —
R. Bryan Martin and Kristian B. Moriarty - Haight Brown & Bonesteel LLPIn Carlton v. Dr. Pepper Snapple Group, Inc. (No. E056566, filed 8/14/2014), The Court of Appeal, Fourth Appellate District, held a demurrer was timely filed in compliance with California Code of Civil Procedure (“CCP”) section 471.5, despite being filed after the 10-day filing period prescribed in California Rule of Court 3.1320(j).
This case appears to settle the conflict that existed between the CCP and the Rules of Court as to the timing of demurrers following amendments to Complaints. Prior to this case, the validity of Rule of Court 3.1320(j)(2) was unclear as it arguably conflicted with CCP Section 471.5, which requires defendants to “answer” an amended complaint within 30 days after service. At the same time, it was not clear that CCP Section 471.5 applied to amendments after a demurrer had been sustained, and it was even more unclear whether the statutory 30-day period to “answer” an amended complaint foreclosed the shorter 10-day period prescribed under Rule of Court 3.1320(j)(2) for a demurrer or motion to strike.
On July 15, 2011, Plaintiff filed a Complaint against Dr. Pepper Snapple Group, Inc. (“Dr. Pepper”) and others. On October 24, 2011, Plaintiff filed a First Amended Complaint (“FAC”). Dr. Pepper demurred to the FAC on various grounds. On January 5, 2012, the trial court sustained the demurrer in part, and overruled it in part. The Court granted Plaintiff 30 days to amend the FAC.
Reprinted courtesy of
R. Bryan Martin, Haight Brown & Bonesteel LLP and
Kristian B. Moriarty, Haight Brown & Bonesteel LLP
Mr. Martin may be contacted at bmartin@hbblaw.com, Mr. Moriarty may be contacted at kmoriarty@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Practical Pointers for Change Orders on Commercial Construction Contracts
December 31, 2014 —
John E. Bowerbank - Newmeyer & DillionConstruction projects pose unique challenges, including keeping costs within budget, meeting project deadlines, and coordinating the work of numerous contractors and subcontractors in the wake of inevitable design revisions and changes to the plans. Anticipating potential project challenges and negotiating contract provisions before commencing work on a project is critical for all parties. Careful planning should reduce the number of contract disputes. This, in turn, can facilitate the completion of a project within budget and on schedule.
“Changes” Clauses in Construction Contracts
Most commercial construction contracts have a clause addressing changes to the contract. A “changes” clause typically requires the mutual agreement of the parties on the scope of any modifications to the contract, as well as the effect on the contract price and timeframe for the work to be performed. This results in what is generally referred to as a “change order.” Many projects have a large number of change orders, which can result in significant cost overruns and delays to the project if the contract contains a complicated change order process. Therefore, in order to minimize cost overruns and project delays, it is crucial to keep the change order process as simplified and streamlined as possible.
In the most basic terms, change orders memorialize modifications to the original contract, and typically alter the contract's price, scope of work, and/or completion dates. A typical change order is a written document prepared by the owner or its design professional, and signed by the owner, design professional, and affected contractors and subcontractors. An executed change order indicates the parties’ agreement as to what changes are taking place, including approval for additional costs and schedule impacts.
While the reasons for change orders and the parties initiating them may vary, all change orders have one feature in common. Effective change orders alter the original contract and become part of the contract. Therefore, from a legal standpoint, change orders must be approached with the same caution and forethought as the original contract.
Practice Pointers for Change Orders
In light of the foregoing, some practice pointers for change orders in commercial construction contracts are as follows:
- Carefully Negotiate and Draft Change Order Provisions in the Original Contract.
A carefully negotiated and drafted “changes” clause that accounts for “unexpected circumstances” or “hidden conditions” can protect the parties from downstream costly disputes.
- Immediately Address Changes by Following the Change Order Process, Including Obtaining Necessary Signatures.
Regardless if you are an owner, general contractor or subcontractor, you should address any proposed change order immediately. Even if a decision maker gives “verbal” approval to go ahead with changed work, the work should not proceed without following the change order process in the original contract. This includes making sure to obtain any necessary signatures for the change order, if at all possible.
- Analyze the Plans and Specifications to Determine Whether “Changes” are Within the Scope of the Original Contract, or Whether They are Extra Work.
Prior to entering an original contract, it is imperative that the parties review the plans and specifications for ambiguities regarding work included in the original contract, versus potential extra work that would require a change order. This is important because a careful review of the plans and specifications sometimes reveals that work believed to be a change order is, in fact, original work, or vice versa.
- Make Sure Requests and Approvals for Change Orders are Done by an Authorized Representative.
When a party requests or gives its approval to a change order, it is important to confirm the request or approval came from an authorized representative.
- Avoid Vague and Open-Ended Change Orders.
Indeed, the vaguer a change order, the more likely it can lead to a dispute. Vague and open-ended change orders, including change orders that provide for payment on a time and materials basis, can be difficult for an owner to budget and schedule. This can lead to disputes as to cost and/or time extensions.
- Oral Assurances for Payment Without a Signed Change Order May Not Be Recoverable.
When a party provides verbal assurances to another party for extra work without following the change order process, there is a much higher likelihood that disputes will occur. Although there is case law that may allow a contractor to recover for extra work in private contracts based on oral promises, the parties should avoid placing themselves in such a legal position. Notably, in public contracts, a contractor may not be able to recover for any extra work without a signed changed order, even with verbal assurances of payment from the owner.
About the Author:
John E. Bowerbank, Newmeyer & Dillion
Mr. Bowerbank is a partner in the Newport Beach office and practices in the areas of business, insurance, real estate, and construction litigation. You can reach John at john.bowerbank@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
ASCE's Architectural Engineering Institute Announces Winners of 2021 AEI Professional Project Award
April 19, 2021 —
American Society of Civil EngineersRESTON, Va. – The
American Society of Civil Engineers' (ASCE) Architectural Engineering Institute (AEI) is pleased to announce the 100 Mount Street project by Skidmore, Owings & Merrill and Billie Jean King Main Library, also by Skidmore, Owings & Merrill as Best Overall Projects winners for AEI's Professional Project Awards. The 100 Mount Street project won the award Best Overall Project Over $100 Million, while the Billie Jean King Main Library won the award for Best Overall Project Under $100 Million. Traditionally, AEI announces project winners during its in-person annual Awards Banquet; however, ASCE held the banquet virtually this year to follow CDC guidelines which suggest avoiding large gatherings.
The AEI Professional Project Award recognizes outstanding achievements in design and construction by honoring the art and science of an integrated approach to architectural engineering. The program focuses on high performance buildings including structural, mechanical, electrical and lighting systems as well as construction management and architectural engineering integration. Projects are evaluated on originality and innovative character, integration and collaboration, sustainability, energy efficiency and economics, effective use of technology and constructability and site logistics.
ABOUT THE AMERICAN SOCIETY OF CIVIL ENGINEERS
Founded in 1852, the American Society of Civil Engineers represents more than 150,000 civil engineers worldwide and is America's oldest national engineering society. ASCE works to raise awareness of the need to maintain and modernize the nation's infrastructure using sustainable and resilient practices, advocates for increasing and optimizing investment in infrastructure, and improve engineering knowledge and competency. For more information, visit www.asce.org and follow us on Twitter, @ASCETweets and @ASCEGovRel.
About ASCE's Architectural Engineering Institute
Established in 1998, AEI is the premier organization for architectural engineering, promoting an integrated, multi-disciplinary approach to planning, design, construction and operation of buildings, by encouraging innovation, collaboration and excellence in practice, education and research of architectural engineering. For more information, visit www.asce.org/aei.
Read the court decisionRead the full story...Reprinted courtesy of
American Society of Civil Engineers
You’re Only as Good as Those with Whom You Contract
April 17, 2019 —
Christopher G. Hill - Construction Law MusingsI have been beating the drum of the need to have a solid construction contract as the basis for your construction project and contractor/subcontractor/supplier relationships. I have also emphasized that communication early and often is one of the best ways to assure a smooth project. However, the sad truth is that even with the best contract drafted with the assistance of an experienced construction attorney, if the other party to the contract simply decides not to perform, whether that is through unjustified non-payment or simple refusal to complete a scope of work without reason, it will be an expensive proposition to force compliance or be compensated for the monetary damage caused by such actions.
It is this often unmentioned truth relating to any contract, including those that construction professionals in Virginia deal with on a daily basis, that makes having a good knowledge of those with whom you plan to contract is key to a successful (read profitable) construction project. Of course be sure that any contractor or subcontractor you contract with has the basics of propoer insurance, the right experience and of course a contractor’s license with the proper specialty or specialties. These basics will get you most of the way to assuring that those that contract with you at least are responsible in business. Another key component, if you can find this information out, is the financial wherwithall of the other party. For a General Contractor, this means both sides of the equation: Owner and Subcontractors. For a Subcontractor, the key is the Contractor, but any other information you can get on the Owner is helpful (though this can be difficult) particularly in the face of a “pay if paid” clause.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
“Source of Duty,” Tort, and Contract, Oh My!
September 06, 2023 —
Christopher G. Hill - Construction Law MusingsHere at Construction Law Musings, I have discussed the general rule in Virginia that
tort and contract do not mix. I have also discussed a
few narrow exceptions. A Virginia Supreme Court case from October of 2019 lays out both sides of this issue in one glorious opinion.
In
Tingler v. Graystone Homes, Inc., a summary of the facts and lawsuit(s) are as follows: Water leaks developed after the home was built. Graystone’s post-construction efforts to repair the leaks and remediate mold were unsuccessful. The Tinglers and their children abandoned the home after developing mold-related medical problems. The Tinglers and their children sued Graystone in tort for personal injury, property damage, and economic loss. In other litigation that will not be discussed in this post, but that is described in the opinion linked above, Belle Meade sued Graystone in contract for property damage and economic losses. George and Crystal Tingler filed a separate complaint alleging the same contract claims.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at