Mediation Confidentiality Bars Malpractice Claim but for How Long?
April 01, 2015 —
Jennifer K. Saunders – Haight Brown & Bonesteel LLPThe California Court of Appeal yesterday upheld application of the mediation confidentiality statutes to bar a malpractice action which was based on the attorneys’ actions during mediation. John Amis vs. Greenberg Traurig LLP, et al. (3/18/15) Court of Appeal, Second Appellate District, No. B248447. Inferences about the attorneys’ conduct during mediation were also determined to be unusable in an attempt to circumvent the privilege.
Plaintiff, John Amis, filed an action against his former attorneys, Greenberg Traurig, alleging they were negligent by “causing” him to execute a settlement agreement during a two-day mediation which converted a corporate obligation into a personal obligation. The causes of action included breach of fiduciary duty, malpractice and breach of a conflict waiver, in support of which Amis alleged that the attorneys failed to advise him of the risk involved in entering into the settlement agreement, “drafted, structured and caused it to be executed” during mediation and breached a conflict waiver by failing to negotiate a settlement that provided him with financial security. During plaintiff’s deposition he admitted that all of the advice he had received in connection with the settlement agreement occurred during mediation and that all the damages incurred were from his execution of that agreement during mediation. Greenberg Traurig filed a motion for summary judgment based upon plaintiff’s deposition admissions and argued that since the mediation confidentiality statutes barred each side from presenting testimony as to what occurred during mediation, the plaintiff could not establish the elements of his claims and they could not defend against those allegations. The trial court agreed with the defense, granting summary judgment.
Read the court decisionRead the full story...Reprinted courtesy of
Jennifer K. Saunders, Haight Brown & Bonesteel LLPMs. Saunders may be contacted at
jsaunders@hbblaw.com
Eleventh Circuit Upholds Coverage for Environmental Damage from Sewage, Concluding It is Not a “Pollutant”
May 24, 2018 —
Lorelie S. Masters & Alexander D. Russo - Hunton Insurance Recovery BlogOn April 20, 2018, the Eleventh Circuit affirmed an Alabama district court decision finding that an “absolute pollution exclusion” did not bar coverage for environmental property damage and injuries from a sewage leak. Evanston Ins. Co. v. J&J Cable Constr., LLC, No. 17-11188, 2018 WL 1887459, (11th Cir. Apr. 20, 2018).
J&J Cable was hired to install underground electrical conduit in a subdivision when it struck and broke the sewer pipe to two homes. As a result, sewage backed up into the homes causing property damage and personal injuries. The commercial general liability policy at issue contained an “absolute pollution exclusion,” which sought to bar coverage for “bodily injury” and “property damage” arising out of the actual, alleged, or threatened discharge, dispersal, seepage, migration, release or escape of “any solid, liquid, gaseous or thermal irritant or contaminant, including smoke, vapor, soot, fumes, acids, alkalis, chemicals and waste.” The insurer relied on an earlier Alabama federal district court decision, which precluded coverage for liability from lead paint exposure, concluding that lead was a pollutant under a similar exclusion. The Eleventh Circuit disagreed, recognizing that insurance is a state law issue and opting instead to rely on binding state court precedent. The Eleventh Circuit, therefore, found that the decision in U.S. Fid. & Guar. Co. v. Armstrong, 479 So. 2d 1164 (Ala. 1985), by the state’s highest court, the Alabama Supreme Court, governed. That case made a distinction between industrial waste and residential sewage. Accordingly, the Eleventh Circuit found that the “absolute pollution exclusion” did not preclude coverage for liability for injuries caused by sewage.
Reprinted courtesy of
Lorelie S. Masters , Hunton Andrews Kurth and
Alexander D. Russo , Hunton Andrews Kurth
Ms. Masters may be contacted at lmasters@HuntonAK.com
Mr. Russo may be contacted at arusso@huntonak.com
Read the court decisionRead the full story...Reprinted courtesy of
New York Team’s Win Limits Scope of Property Owners’ Duties to Workers for Hazards Inherent in Their Work
May 20, 2024 —
Lewis Brisbois NewsroomNew York, N.Y. (May 9, 2024) - New York Partners Jennifer Oxman and Andrew Harms recently secured dismissal of a personal injury plaintiff’s complaint on summary judgment in Queens County, with a state judge accepting their argument that a porter who allegedly tripped and fell on loose wood in a stairwell had no cause of action against the property owner because it was his job to clean the stairs in the first instance. The porter was not an employee of the property owner, but rather an employee of a property management company. Therefore, the workers compensation bar did not apply to the employee’s claims.
In a four-page decision, Justice Chereé A. Buggs of Queens County Supreme Court found that plaintiff’s duties as a porter included cleaning the stairwell and that he saw and cleaned loose pieces of wood on occasions prior to his accident. Justice Buggs held that while the wood debris likely came from an “outside source”, i.e. a contractor performing work at a neighboring building, the source of the debris was not relevant. Rather, what mattered was the fact that the hazard upon which plaintiff tripped was “inherent in or related to” plaintiff’s work responsibilities. By contrast, Justice Buggs held that the contractor who allegedly was the source of the wood was not entitled to summary judgment under the same legal theory because it arguably caused and created the hazard upon which plaintiff tripped.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
Critical Materials for the Energy Transition: Of “Rare Earths” and Even Rarer Minerals
September 12, 2022 —
Robert A. James, Ashleigh Myers, Shellka Arora-Cox & Amanda G. Halter - Gravel2Gavel Construction & Real Estate Law BlogAs the world pursues ambitious net-zero carbon emission goals, demand is soaring for the critical materials required for the technologies leading the energy transition. Lithium may be the most well-known of these inputs due to its usage in batteries for vehicles and consumer electronics, but roughly 50 other minerals are central to energy transition technologies. During the coming years, producers, manufacturers and end-users will be increasingly exposed to the roles played by “rare earth” elements (roughly, atomic numbers 57 to 71), platinum group metals, and other materials.
The reasons for this heightened interest are simple—even if the underlying environmental, political and technological forces at play are complex:
- Lower-carbon technologies use different materials than carbon-intensive technologies.
The mineral requirements of power and mobility systems driven by renewable, nuclear, hydrogen and fusion energy are profoundly different from those forming the backbone of fossil fuel systems. Minerals such as lithium, nickel, copper, cobalt, and rare earth elements are vital for electric vehicles (EVs), batteries, fuel cells, electricity grids, wind turbines, smart devices, and many other essential and proliferating civilian and military technologies. For example, an offshore wind plant needs 13 times more mineral resources than a gas power plant of a similar size.
Reprinted courtesy of
Robert A. James, Pillsbury,
Ashleigh Myers, Pillsbury,
Shellka Arora-Cox, Pillsbury and
Amanda G. Halter, Pillsbury
Mr. James may be contacted at rob.james@pillsburylaw.com
Ms. Myers may be contacted at ashleigh.myers@pillsburylaw.com
Ms. Arora-Cox may be contacted at shellka.aroracox@pillsburylaw.com
Ms. Halter may be contacted at amanda.halter@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
How Small Mistakes Can Have Serious Consequences Under California's Contractor Licensing Laws.
February 15, 2018 —
Eric Reed - Myers, Widders, Gibson, Jones & Feingold, LLPIn construction, some risks have nothing to do with how well a contractor executes a project. Licensing problems is one of these risks. Even a brief lapse caused by an unintentional administrative error can give the CSLB grounds to discipline a contractor, or enable a customer to seek disgorgement and other remedies provided by Business and Professions Code section 7031. This article discusses five tips for mitigating the liabilities associated with licensing problems.
Tip 1: Take workers' compensation insurance very seriously. Workers’ compensation insurance problems can trigger license suspension in California. Business and Professions Code section 7125.4 calls for automatic suspension if a contractor cannot provide proof of workers’ compensation insurance for any period of time. This is particularly serious for residential remodelers who claim exemption for workers’ compensation but are later discovered – usually during litigation with a homeowner – to have “off the books” workers helping them. Courts can declare the contractor retroactively unlicensed under these circumstances and order it to disgorge,
i.e., to pay back, every penny paid by the customer for the entire project (even for materials). (Bus. & Prof. Code, § 7031, subd. (b);
Wright v. Issak (2007) 149 Cal.App.4th 1116.) The contractor will also find itself unable to collect any amounts owed to it by the customer. (Bus. & Prof. Code, § 7031, subd. (a).)
Tip 2: Watch out for licensing confusion after a merger or acquisition. The economic downturn of 2008 and 2009 resulted in consolidation throughout the building industry. The newly merged or acquired entities often allowed redundant licenses to expire, assuming they could complete all pending projects under the umbrella of the acquiring company's license. Many learned this was a mistake the hard way. Armed with the California Supreme Court's opinion in
MW Erectors, Inc. v. Niederhauser Ornamental & Metal Works Co., Inc. (2005) 36 Cal.4th 412, customers began refusing to pay invoices and demanding disgorgement under Business and Professions Code section 7031 because the original contractor did not maintain licensure “at all times.” Many of these customers succeeded.
Tip 3: If a license suspension has occurred or is imminent, prepare to prove substantial compliance. Section 7031(a) and (b) give a disgruntled or indebted customer every incentive to capitalize on a contractor's licensing problems. Subdivision (e) is where a contractor must turn to protect its interests if this happens. It allows the contractor to prove “substantial compliance” with licensing requirements and avoid (a)’s and (b)’s sharp edges if it can show the following:
(1) The contractor “had been duly licensed as a contractor in this state prior to the performance of the act or contract”;
(2) It “acted reasonably and in good faith to maintain proper licensure”; and
(3) It “acted promptly and in good faith to remedy the failure to comply with the licensure requirements upon learning of the failure.”
The Court of Appeal confirmed in
Judicial Council of California v. Jacobs Facilities, Inc. (2015) 239 Cal.App.4th 882 that a contractor, upon request, is entitled to a hearing on these three factors before it is subjected to disgorgement under Section 7031(b). The legislature amended Section 7031 shortly after the Court of Appeal published this case. The Assembly’s floor analysis went so far as to directly quote the opinion’s observation that penalizing a construction firm for “technical transgressions only indirectly serves the Contractors Law’s larger purpose of preventing the delivery of services by unqualified contractors.” (Assem. Com. on Bus. and Prof., Off. of Assem. Floor Analyses, analysis of Sen. Holden's No. 1793 (2015-2016 Reg. Sess.) as amended August 2, 2016, p. 2.) This echoed an industry consensus that clarifying the law was needed to ensure that properly licensed and law-abiding construction firms were not “placed at fatal monetary risk by malicious lawsuits motivated by personal gain rather than consumer protection.” (Assem. Com. on Judiciary, com. on Assem. Bill No. 1793 (2015-2016 Reg. Sess.), pp. 6-7.)
Unfortunately, existing law does not give many examples of what it means to act “reasonably and in good faith to maintain proper licensure” or to act “promptly and in good faith” to fix license problems. A practical approach is for a contractor to work backwards by assuming it will need to prove substantial compliance at some point in the future. Designated individuals within the organization should have clear responsibility over obtaining and renewing the proper licenses and should keep good records. If necessary, these designees can testify about the contractor's internal policies and their efforts to fix licensing problems when they arose. For example, if the suspension resulted from not providing the CSLB proof of workers’ compensation insurance, the designee can testify about the cause (a broker miscommunication, transmission error,
etc.) and produce documents showing how he or she worked promptly to procure a certificate of insurance to send CSLB. Saved letters, emails, and notes from telephone calls will provide designees and their successors with an important resource months or years down the line if a dispute arises and the contractor is required to reconstruct the chronology of a licensing glitch and prove its due diligence.
Tip 4: Don't sign new contracts unless all necessary licenses are active and any problems are resolved. A recently-formed contractor should not begin soliciting and signing contracts until all required licenses are confirmed as “active.” The first requirement of substantial compliance – being “duly licensed as a contractor in this state prior to the performance of the act or contract” – cannot be met by a contractor that first obtains its license mid-project. (Bus. & Prof. Code, § 7031, subd. (e)(1);
Alatriste v. Cesar’s Exterior Designs (2010) 183 Cal.App.4th 656.) A licensed contractor should also consider refraining from signing new contracts if there is any reason to believe its license might be suspended in the near future – especially if the suspension will be retroactive. Having a suspension on record at the time of contracting may complicate the question of whether the contractor was “duly licensed . . . prior to performance” for the purposes of substantial compliance.
Tip 5: Any judgment against a contractor can cause license suspension if not handled promptly and correctly. The Business and Professions Code authorizes the CSLB to suspend the license of a contractor that does not pay a construction related court judgment within 90 days. The term “construction related” is interpreted to include nearly all types of disputes involving a contractor. (16 Cal. Code Reg. 868;
Pacific Caisson & Shoring, Inc. v. Bernards Bros. Inc. (2015) 236 Cal.App.4th 1246, 1254-1255.) This means a contractor should treat a judgment against it for unpaid office rent, for example, as one carrying the same consequences as one arising from a construction defect or subcontractor claim. The contractor should also not assume that filing an appeal, or agreeing with the other side to stay enforcement, automatically excuses the 90-day deadline in the eyes of the CSLB. It does not. A contractor must notify the CSLB in writing before this period expires, then post bond for the amount of judgment, if it wishes to delay payment for any reason. (Bus. & Prof. Code, § 7071.17, subd. (d).) A suspension may result if it does not. This applies even to small claims judgments.
Recent case law and the 2016 amendments to Business and Professions Code section 7031 provide some solace to those caught in the dragnet of California's licensing laws. But avoiding these problems altogether is preferable. Consider licensing the foundation of a successful business and deserving of the same attention as the structures a contractor builds.
Eric R. Reed is a business and insurance litigator in the Ventura office of Myers, Widders, Gibson, Jones & Feingold, LLP.
Read the court decisionRead the full story...Reprinted courtesy of
Eric Reed, Myers, Widders, Gibson, Jones & Feingold, LLPMr. Reed may be contacted at
ereed@mwgjlaw.com
Florida trigger
May 18, 2011 —
CDCoverage.comIn Johnson-Graham-Malone, Inc. v. Austwood Enterprises, Inc., No. 16-2009-CA-005750-XXXX-MA (Fla. 4th Cir. Ct. Duval County, April 29, 2011), insured JGM was the general contractor for an apartment project completed in 1998. In 2007, the project owner sued JGM seeking damages for defective construction resulting in moisture penetration property damage. JGM tendered its defense to Amerisure. Amerisure denied a defense. JGM defended and settled the underlying suit and then filed suit against Amerisure seeking recovery of defense and settlement costs. The trial court granted JGM’s motion for partial summary judgment. The court first addressed Amerisure’s duty to defend. Applying Florida law, the court held that, although the underlying complaint alleged that the property damage was not discovered until after expiration of the Amerisure policies
Read the full story…
Reprinted courtesy of CDCoverage.com
Read the court decisionRead the full story...Reprinted courtesy of
There's No Place Like Home
March 02, 2020 —
Brian Brenner - Engineering News-RecordTwo things that generally do not go well together, bridges and tornadoes, collided with unfortunate results on July 21, 2003. On that date, a tornado struck the Kinzua viaduct in northwestern Pennsylvania. The old bridge structure already had deteriorated foundation supports, which were then under repair. The tornado lifted parts of the bridge off its foundation, and more than half of the structure collapsed.
Brian Brenner, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Construction News Roundup
September 19, 2022 —
Christopher G. Hill - Construction Law MusingsMuch happened in the last week or so in Virginia construction, both legally and otherwise. I thought a quick roundup was in order.
On the green front we has a great article in ENR relating to the liability risk of green building and the great interest in the
AGCVA Green Building Breakfast.
Also, the Virginia courts decided several interesting cases:
The first is Travelers Property Cas. Co. of America a/s/o Covenant Woods v. Premier Project Mgmt. Group LLC v. Haskell Co. a case that reminds everyone that waivers of third party rights under the contract will be enforced in Virginia.