Practical Pointers for Change Orders on Commercial Construction Contracts
December 31, 2014 —
John E. Bowerbank - Newmeyer & DillionConstruction projects pose unique challenges, including keeping costs within budget, meeting project deadlines, and coordinating the work of numerous contractors and subcontractors in the wake of inevitable design revisions and changes to the plans. Anticipating potential project challenges and negotiating contract provisions before commencing work on a project is critical for all parties. Careful planning should reduce the number of contract disputes. This, in turn, can facilitate the completion of a project within budget and on schedule.
“Changes” Clauses in Construction Contracts
Most commercial construction contracts have a clause addressing changes to the contract. A “changes” clause typically requires the mutual agreement of the parties on the scope of any modifications to the contract, as well as the effect on the contract price and timeframe for the work to be performed. This results in what is generally referred to as a “change order.” Many projects have a large number of change orders, which can result in significant cost overruns and delays to the project if the contract contains a complicated change order process. Therefore, in order to minimize cost overruns and project delays, it is crucial to keep the change order process as simplified and streamlined as possible.
In the most basic terms, change orders memorialize modifications to the original contract, and typically alter the contract's price, scope of work, and/or completion dates. A typical change order is a written document prepared by the owner or its design professional, and signed by the owner, design professional, and affected contractors and subcontractors. An executed change order indicates the parties’ agreement as to what changes are taking place, including approval for additional costs and schedule impacts.
While the reasons for change orders and the parties initiating them may vary, all change orders have one feature in common. Effective change orders alter the original contract and become part of the contract. Therefore, from a legal standpoint, change orders must be approached with the same caution and forethought as the original contract.
Practice Pointers for Change Orders
In light of the foregoing, some practice pointers for change orders in commercial construction contracts are as follows:
- Carefully Negotiate and Draft Change Order Provisions in the Original Contract.
A carefully negotiated and drafted “changes” clause that accounts for “unexpected circumstances” or “hidden conditions” can protect the parties from downstream costly disputes.
- Immediately Address Changes by Following the Change Order Process, Including Obtaining Necessary Signatures.
Regardless if you are an owner, general contractor or subcontractor, you should address any proposed change order immediately. Even if a decision maker gives “verbal” approval to go ahead with changed work, the work should not proceed without following the change order process in the original contract. This includes making sure to obtain any necessary signatures for the change order, if at all possible.
- Analyze the Plans and Specifications to Determine Whether “Changes” are Within the Scope of the Original Contract, or Whether They are Extra Work.
Prior to entering an original contract, it is imperative that the parties review the plans and specifications for ambiguities regarding work included in the original contract, versus potential extra work that would require a change order. This is important because a careful review of the plans and specifications sometimes reveals that work believed to be a change order is, in fact, original work, or vice versa.
- Make Sure Requests and Approvals for Change Orders are Done by an Authorized Representative.
When a party requests or gives its approval to a change order, it is important to confirm the request or approval came from an authorized representative.
- Avoid Vague and Open-Ended Change Orders.
Indeed, the vaguer a change order, the more likely it can lead to a dispute. Vague and open-ended change orders, including change orders that provide for payment on a time and materials basis, can be difficult for an owner to budget and schedule. This can lead to disputes as to cost and/or time extensions.
- Oral Assurances for Payment Without a Signed Change Order May Not Be Recoverable.
When a party provides verbal assurances to another party for extra work without following the change order process, there is a much higher likelihood that disputes will occur. Although there is case law that may allow a contractor to recover for extra work in private contracts based on oral promises, the parties should avoid placing themselves in such a legal position. Notably, in public contracts, a contractor may not be able to recover for any extra work without a signed changed order, even with verbal assurances of payment from the owner.
About the Author:
John E. Bowerbank, Newmeyer & Dillion
Mr. Bowerbank is a partner in the Newport Beach office and practices in the areas of business, insurance, real estate, and construction litigation. You can reach John at john.bowerbank@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
Sometimes you Need to Consider the Coblentz Agreement
January 19, 2017 —
David Adelstein – Florida Construction Legal UpdatesSince insurance, particularly liability insurance, is such an important component when it comes a construction project, understanding certain nuances such as a
Coblentz Agreement (a what kind of agreement agreement?!?—keep reading) becomes helpful.
If there is a construction defect claim / lawsuit, the implicated parties (e.g., contractor, design professional, subcontractor, sub-consultants) are going to tender the claim / lawsuit to their respective liability insurer. This is what they should be doing – notifying the insurer so that the insurer can defend them from the claim / lawsuit and indemnify them from covered damages associated with the claim / lawsuit.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Nomos LLP Partners Recognized in Super Lawyers and Rising Stars Lists
August 16, 2021 —
Garret Murai - California Construction Law BlogNomos LLP partners Garret Murai and Jennifer Tang have been recognized in Thompson Reuter’s 2021 Northern California Super Lawyers and 2021 Northern California Rising Start lists in the area of Construction Litigation. This is the eighth consecutive year for Garret on the Super Lawyers list and the fifth consecutive year for Jennifer on the Rising Star list.
The Super Lawyers list recognizes no more than 5 percent of attorneys in each state. The Rising Stars list recognizes no more than 2.5 percent of attorneys in each state. To be eligible for inclusion in Rising Stars, a candidate must be either 40 years old or younger, or in practice for 10 years or less.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Limitation on Coverage for Payment of Damages Creates Ambiguity
April 03, 2013 —
Tred EyerlyUnable to discern the meaning of a provision stating that payment of damages would be made "through a trial but not any appeal", the court found an ambiguity.Parker v. Am. Family Ins. Co., 2013 U.S. Dist. LEXIS 9085 (D. Ore. Jan. 23, 2013).
The homeowners sued the general contractor for defective construction of their home. In November 2008, the homeowners reached a settlement through mediation with the general contractor. The general contractor's claims under its policies with American Family and Mid-Continent were assigned to the homeowners.
The homeowners then sued both insurers for breach of insurance contract and/or equitable contribution. American Family moved for summary judgment, claiming the homeowners did not prove their damages claim against the general contractor "through a trial but not any appeal."
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
New Research Shows Engineering Firms' Impact on Economy, Continued Optimism on Business Climate
October 28, 2024 —
The ACEC Research InstituteWASHINGTON – The ACEC Research Institute – the leading source of original research for the business of engineering – released the results of two important studies on the current and future state of the engineering industry, and its role in the overall U.S. economy.
The reports, the
2024 Economic Assessment of the Engineering & Design Services Industry and the
Engineering Business Sentiment Report for 2024 Q4, both point to continued optimism for the industry and its firms, though somewhat softened compared to previous quarters.
"This research shows the outsized impact the engineering industry has on the American economy," said ACEC Research Institute Chair Mike Carragher. "As the engineering industry's contributions grow year over year, the Institute's research helps firm executives position their businesses for a successful future."
All told, the industry added $656 billion to the U.S. GDP in 2023, supported well over five million jobs directly or indirectly, and contributed $92 billion to federal tax coffers, with an additional $44 billion in state and local taxes.
Overall, the report found that the engineering and design services industry has continued to build on its year-over-year post-COVID gains, growing 5.5% in 2023 to $436 billion, with much of that growth driven by infrastructure projects. Non-residential and non-building construction, flush with government funding through the IIJA and Inflation Reduction Act, remained on an upward trajectory.
Read the court decisionRead the full story...Reprinted courtesy of
New Orleans Is Auctioning Off Vacant Lots Online
March 12, 2015 —
Patrick Clark – BloombergNew Orleans is selling almost 1,800 properties on the Web to fatten its tax coffers and build on the momentum it's enjoying in the local real estate market.
The question is, who's going to show up for the online auction, and what are they going to do with the lots they buy?
On Friday, the city posted a list of 1,786 properties—90 percent of them vacant lots—that it plans to sell in the auction. Bidding on the properties, of which the city took control after the owners failed to pay property taxes, will start at $3,000 in most cases, plus the cost of trying to track down the most recent owner.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick Clark, BloombergMr. Clark may be contacted at
jclark185@bloomberg.net
Contractors: Revisit your Force Majeure Provisions to Account for Hurricanes
September 14, 2017 —
David Adelstein - Florida Construction Legal UpdatesWe now know and can appreciate the threat of hurricanes. Not that we did not appreciate the reality of hurricanes–of course we did–but Hurricane Harvey and Hurricane Irma created the type of actual devastation we fear because they hit close to home. The fear came to life, creating panic, anxiety, and uncertainty. It is hard to plan for a force majeure event such as a hurricane because of the capriciousness of Mother Nature. But, we need to do so from this point forward. No exception! And, I mean no exception!!
A force majeure event is an uncontrollable event that cannot be anticipated with any degree of definitiveness. The force majeure event will excusably delay or hinder performance obligations under a contract. One type of force majeure event is a hurricane—an uncontrollable and unforeseen act of Mother Nature.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
Dadelstein@gmail.com
Illinois Supreme Court Holds that Constructions Defects May Constitute “Property Damage” Caused By An “Occurrence” Under Standard CGL Policy, Overruling Prior Appellate Court Precedent
January 08, 2024 —
Jason Taylor - Traub Lieberman Insurance Law BlogOn November 30, 2023, the Illinois Supreme Court issued an opinion that overturned precedent in Illinois regarding whether faulty workmanship that only caused damage to the insured’s own work constituted “property damage” caused by an “occurrence” under Illinois law. In Acuity v. M/I Homes of Chicago, LLC, 2023 IL 129087, the Illinois Supreme Court considered whether Acuity, a mutual insurance company, had a duty to defend its additional insured, M/I Homes of Chicago, LLC (M/I Homes), under a subcontractor’s commercial general liability (CGL) policy in connection with an underlying lawsuit brought by a townhome owners’ association for breach of contract and breach of an implied warranty of habitability. The Cook County Circuit Court granted summary judgment in favor of Acuity finding no duty to defend because the underlying complaint did not allege “property damage” caused by an “occurrence” under the initial grant of coverage of the insurance policy. The appellate court reversed and remanded, finding that Acuity owed M/I Homes a duty to defend. The Illinois Supreme Court affirmed, in part, holding construction defects to the general contractor’s own work may constitute “property damage” caused by an “occurrence” under the standard CGL Policy. This is significant as it overrules prior Illinois precedent finding that repair or replacement of the insured’s defective work does not satisfy the initial grant of coverage of a CGL Policy.
By way of background, the underlying litigation stems from alleged construction defects in a residential townhome development in the village of Hanover Park, Illinois. The townhome owners’ association, through its board of directors (the Association) subsequently filed an action on behalf of the townhome owners for breach of contract and breach of the implied warranty of habitability against M/I Homes as the general contractor and successor developer/seller of the townhomes. The Association alleged that M/I Homes’ subcontractors caused construction defects by using defective materials, conducting faulty workmanship, and failing to comply with applicable building codes. As a result, “[t]he [d]efects caused physical injury to the [t]ownhomes (i.e. altered the exterior’s appearance, shape, color or other material dimension) after construction of the [t]ownhome[ ] was completed from repeated exposure to substantially the same general conditions.” The defects included “leakage and/or uncontrolled water and/or moisture in locations in the buildings where it was not intended or expected.” The Association alleged that the “[d]efects have caused substantial damage to the [t]ownhomes and damage to other property.”
Read the court decisionRead the full story...Reprinted courtesy of
Jason Taylor, Traub LiebermanMr. Taylor may be contacted at
jtaylor@tlsslaw.com