Flood Coverage Denied Based on Failure to Submit Proof of Loss
November 26, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe court granted summary judgment to the insurer because the insureds submitted only documentation of damage by flood, not proof of loss forms required by the policy. Alexander v. Allstate Ins. Co., 2014 U.S. Dist. LEXIS 143284 (E.D. La. Oct. 8, 2014).
Hurricane Isaac caused flood damaged to the insureds' home. A claim was filed for flood damage under their Standard Flood Insurance Policy issued by Allstate. An independent adjuster estimated that building repairs would be $50,025. Allstate also prepared a contents loss estimate of $22,655 based on a personal property list submitted by the insureds. Proof of loss forms for these amounts were sent to the insureds and returned to Allstate. Consequently, these claims were paid.
The insureds submitted a new proof of loss for additional lost contents, and another payment was made. Additional building damages were found. Again, the proof of loss was resubmitted and an additional payment was made by Allstate.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Design Professionals Owe a Duty of Care to Homeowners
July 09, 2014 —
Stephen A. Sunseri - Gatzke Dillon & Ballance LLPToday, the California Supreme Court, in Beacon Residential Community Association v. Skidmore, Owings & Merrill LLP (Jul. 3, 2014, S208173) __Cal.4th__ [2014 WL 2988058], held that architects owe a duty of care to future homeowners of residential buildings, particularly if they act as principal architects on a project, and are not subordinate to any other design professional. Until now, design professionals were rarely held liable, if at all, for third-party claims for design deficiencies.
In Beacon, architectural and engineering firms provided sole design services for The Beacon residential condominium project, a 595 unit project located in San Francisco. The condominiums were initially leased after construction, but were eventually sold to individual owners. The design firms claimed their role was limited to only providing design recommendations to the project's owner, who ultimately controlled and directed which design elements to construct. Not long after completion of the project, the homeowners' association sued the design firms (among others) for construction defects and damages related to alleged water infiltration, inadequate fire separations, structural cracks, and other purported safety hazards. The claims included allegations under SB 800 (the "Right to Repair Act," Civil Code §895, et seq.) and common law negligence theories.
The design firms demurred to the complaint, which the trial court sustained. On appeal, however, the Court of Appeal reversed the trial court's ruling, concluding that the design firms owed a duty of care to third parties. The Supreme Court affirmed.
Historically, liability for deficient goods and services hinged on whether there is a contractual relationship between a buyer and seller. However, the Supreme Court recognized that in certain circumstances a contractual relationship is not required. In its ruling, the Supreme Court relied on fifty year old precedent, Biankanja v. Irving (1958) 49 Cal.2d 647. In Biankanja, the California Supreme Court outlined several factors to determine whether a duty of care is owed to non-contracting third parties. Although Biankanja analyzes many factors, emphasis was placed placed on whether a purported harm was foreseeable by a defendant's conduct and how close of a connection there is between that conduct and an injury.
Here, the Court recognized that even though the design firms did not actually build the project, they did conduct weekly inspections, monitored contractor compliance, altered design elements when issues arose, and advised the owners of any nonconforming work. In applying the Biankanja factors to these circumstances, the Supreme Court determined the homeowners were intended beneficiaries of the design work and the design firms' primary role in the project bore a close connection to the alleged injuries. As a result, the Supreme Court held that the allegations in the complaint were sufficient and, if proven, establishes the defendants owed a duty of care to the homeowners' association.
Interestingly, the Supreme Court sidestepped the issue of whether SB 800 was intended to exclusively capture design defects in its scope, even though the Court indicated it may. Nevertheless, the Supreme Court's ruling is significant. The case will affect how design professionals allocate risk on future residential projects, perhaps by raising design prices or insuring around the liability exposure. The likely outcome, however, is that design professionals are now targets in construction defect lawsuits.
Read the court decisionRead the full story...Reprinted courtesy of
Stephen A. Sunseri, Gatzke Dillon & Ballance LLPMr. Sunseri may be contacted at
ssunseri@gdandb.com
How is Negotiating a Construction Contract Like Buying a Car?
March 01, 2017 —
Christopher G. Hill – Construction Law MusingsI know, you’re probably looking for a punchline, and likely thinking something along the lines of “only a construction attorney would be sitting in his office and come up with such an analogy,” but I really do think it’s a good one.
When you are buying a car, you look for priorities. Is the color what you want? Is the motor a hybrid or a v-6? Does it have Android Auto? What is the fuel mileage? All of these things may be more or less important to you. If you can get your priorities for a price that is attractive, you will likely let some other less important items, e. g. trunk space or rear seat leg room, slide and purchase the car anyway. Furthermore, you may use these minor items as negotiating points to either get one of the priorities or a lower price. Of course the dealership will want to get its priorities, likely a sale and a profit, when negotiating and will have certain items that it won’t move on just as you have terms that you won’t move on.
Much like when you walk onto the car lot, and particularly as a subcontractor looking at a contract from a general contractor, or a GC looking at the contract from the owner of a project, a construction contract presented to you is the starting point. When looking at the contract, be sure to have some non-negotiable items in mind when taking a critical eye to the terms of that contract. Some of these terms may be more or less negotiable depending on your experience with the other party to the construction contract. For instance, striking a pay if paid clause may be less important with a paying party with whom you have a 10 year history without payment problems. On the other hand, if it is your first contract with the other party, a stricter list may be required. So, much like a dealer that you know will stand behind its cars, you may be more willing to take more “risk” in entering a construction contract with a trusted/known owner or GC.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Toronto Contractor Bondfield Wins Court Protection as Project Woes Mount
May 27, 2019 —
Scott Van Voorhis - Engineering News-RecordA Toronto area contractor at the center of a series of delays to major projects in Ontario, including a $139-million hospital expansion, has won court protection from its creditors. The Ontario Superior Court earlier this month granted Bondfield Construction Co.’s application for protection, court records show.
Read the court decisionRead the full story...Reprinted courtesy of
Scott Van Voorhis, ENR
Predicting the Future of Texas’s Grid Is a Texas-Sized Challenge
June 27, 2022 —
Nathaniel Bullard - BloombergA little more than a year after a paralyzing winter freeze, the Texas power market just experienced the stress of extreme heat. Last week, power prices in Houston briefly jumped above $5,000 per megawatt-hour as high temperatures coincided with a number of generators being offline for maintenance.
Yet a few days earlier, power prices in west Texas had been negative $883 dollars per megawatt-hour, because at the time wind generation was abundant and demand was low.
“Dynamic” is one way to describe the price swings within the Electric Reliability Council of Texas (Ercot), the grid that provides the majority of the state’s power. “Jarring” or “terrifying” might be other words for it, particularly for those buying power in the spot market.
Read the court decisionRead the full story...Reprinted courtesy of
Nathaniel Bullard, Bloomberg
Case-Shiller Redo Shows Less Severe U.S. Home-Price Slump
September 03, 2014 —
Lorraine Woellert – BloombergThe collapse in U.S. home prices that stoked the worst recession since the Great Depression wasn’t quite as severe as initially estimated, according to data from S&P/Case-Shiller.
Property values nationally fell 26 percent from the February 2007 peak to the December 2011 trough, not 34 percent as previously reported, revised data showed last week. The index will now be issued monthly rather than quarterly.
The change is the result of CoreLogic Inc. (CLGX)’s $6 million purchase of the S&P/Case-Shiller index from technology company Fiserv Inc. in March 2013. Case-Shiller has spent more than a year retrofitting its model with CoreLogic’s bigger, higher-quality data set, leading to a change in how the index looks.
Read the court decisionRead the full story...Reprinted courtesy of
Lorraine Woellert, BloombergMs. Woellert may be contacted at
lwoellert@bloomberg.net
Resolve to Say “No” This Year
January 26, 2016 —
Christopher G. Hill – Construction Law MusingsWe hear all of the time how to “get to ‘yes'” and how doing so can lead to more business and of course more business leads to more profits. Purely logical, right? Without construction owners with work for general contractors to perform and general contractors hiring subcontractors to perform that work, construction grinds to a halt and clients and friends of mine in the construction industry don’t make money. For this to happen, “yes” has to happen more often than not. So, why the title of this post?
Chalk it up to spending much if not all of my time as a construction attorney either anticipating or dealing with the Murphy’s Law ruled nature of the construction world or to the “Monday morning quarterback” nature of my profession, but I see numerous instances where not taking the job or signing the bad contract would have led to a better outcome than performing the work. What do I mean by this? I mean that as a construction company (particularly one that is lower down the “payment chain” and therefore less in control of the flow of money), you need to carefully evaluate not only the contract presented, but whether you get a good feeling about the party with whom you are contracting.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
A Win for Policyholders: Court Finds Flood Exclusion Inapplicable to Plumbing Leaks Caused by Hurricane Rainfall
October 21, 2024 —
Kelly A. Johnson & Damian S. Barquin - Saxe Doernberger & Vita, P.C. A recent decision by a federal court helps clear the path to coverage for property owners this hurricane season. The Court deemed one property policy’s flood exclusion inapplicable to bar coverage for water damage from backed-up drainage and overflow caused by excessive rainfall. The case, styled G.E.M.S. Partners LLC v. AmGUARD Ins. Co., — F.Supp. 3d —, No. CV 22-1664, 2024 WL 3568932 (D.N.J. July 29, 2024)), involved a familiar dispute between the insured and insurer following damage to covered property after a named storm’s heavy rainfall.
Here, G.E.M.S. Partners LLC (“Insured”) obtained a commercial property policy from AmGUARD Insurance Company (“AmGUARD”) to cover three neighboring buildings in Union, New Jersey. In September 2021, intense rainfall from Hurricane Ida overwhelmed the local infrastructure and sewer system, leading to water leakage from plumbing fixtures at the insured property. To secure coverage under its AmGUARD policy, the Insured wisely relied on its “Water Back-Up and Sump Overflow Endorsement” (“Back-Up/Overflow Endorsement”). Under this endorsement, AmGUARD promised to “pay for ... damage ... caused by ... water ... which backs up through or overflows or is otherwise discharged from a sewer.”1 Indeed, a plumber that inspected the buildings following Hurricane Ida described the root cause of the water damage as a “back up” of “sewer ... water.”2
Reprinted courtesy of
Kelly A. Johnson, Saxe Doernberger & Vita, P.C. and
Damian S. Barquin, Saxe Doernberger & Vita, P.C.