Additional Insured Secures Defense Under Subcontractor's Policy
October 14, 2013 —
Tred Eyerly — Insurance Law HawaiiThe court determined there were sufficient allegations in the underlying complaint and third party complaints to raise a duty to defend for the additional insured. Ill. Emcasco Ins. Co. v. Waukegan Steel Sales, 2013 Ill. App. LEXIS 624 (Ill. Ct. App. Sept. 13, 2013).
Waukegan was named as an additional insured under subcontractor I-MAXX Metalworks, Inc.'s policy with Emcasco. An employee of I-MAXX, John Walls, was injured on the job site and sued Waukegan. The complaint alleged Waukegan was negligent in failing to property manage, operate and maintain the premises.
I-MAXX had a policy with Emcasco which named Waukegan as an additional insured. The coverage was limited, however, to the additional insured's vicarious liability as a result of the insured's conduct.
Emcasco refused to defend Waukegan because the allegations of direct negligence against Waukegan were excluded by the vicariously liability provision.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
Construction Litigation Roundup: “This Is Sufficient for Your Purposes …”
April 08, 2024 —
Daniel Lund III - Lexology… but just barely.
Federal courts are “notice” pleading courts. One source writes: “Notice pleading refers to pleading standards that merely notify the opposing party and court of the general issues in the case. In contrast to fact pleading standards, notice pleading standards do not require pleadings to include hyper-detailed facts in support of each claim.”
Some state courts – including Louisiana – are fact pleading courts. Ordinarily, no one practicing in Louisiana state courts would describe the fact pleading requirements for initiating a lawsuit as mandating “hyper-detailing” of the facts, but … why risk it?
In a construction mechanics lien case – the jurisprudence for which requires that courts strictly construe the related law because liens empower lien holders with rights which are “in derogation” of common property ownership rights – the defendant was successful in having the trial court dismiss a lien suit for failing to affirmatively set forth in the complaint (a “petition” in Louisiana) the date of substantial completion. The lien claimant appealed.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
2014 WCC Panel: Working Smarter with Technology
May 13, 2014 —
Beverley BevenFlorez-CDJ STAFFDon MacGregor, Project Manager and General Contractor with Bert L. Howe & Associates, will be joining Brian Kahn, Esq. of Chapman, Glucksman, Dean, Roeb & Barger, Paul R. Kiesel, Esq. of Kiesel Law, Hon. Peter Lichtmen (ret), Hon. Nancy Wieben Stock (ret), and Peter S. Curry of Curry Stenger Engineering as a panelist in the break-out session Working Smarter With Technology at the 2014 West Coast Casualty Construction Defect Seminar being held May 15th and 16th at the Disneyland Hotel in Anaheim, California.
With a strong focus on the topic of this year’s seminar, Back to Business . . . Working Smarter, Not Harder, the panel will discuss ways that technology can assist our industry in working more efficiently, saving money and providing a better product. Conversely, the panel will also acknowledge the limitations of technology and areas where the use of advanced technology may not be appropriate.
The information provided will be of benefit to the construction defect litigator but equally valuable to other types of complex litigation. Accordingly, this panel will appeal to those whose scope of work goes beyond the bounds of construction defect. A brief outline of topics that will be addressed by each panelist include remote virtual appearance and deposition attendances, document management software, how to create, manage and edit documents using remote technology, technological tools that allow for easier communications, transfer of information and flexibility, expert technology, and technology in mediation and trial.
The panel discussion will go beyond past seminar discussions in that they will discuss and demonstrate tools that are just coming into use now as well as new tools which are being released prior to the seminar.
Read the court decisionRead the full story...Reprinted courtesy of
Owner’s Obligation Giving Notice to Cure to Contractor and Analyzing Repair Protocol
November 23, 2016 —
David Adelstein – Florida Construction Legal UpdatesRecently, I read an informative article from another attorney addressing considerations of an owner when it receives a repair protocol in response to a Florida Statutes Chapter 558 notice of defect letter. This is a well-written article and raises two important issues applicable to construction defect disputes: 1) how is an owner supposed to respond to a repair protocol submitted by a contractor in accordance with Florida’s 558 notice of construction defects procedure and 2) irrespective of Florida’s 558 procedure, how is an owner supposed to treat a contractual notice to cure / notice of defect requirement that requires the owner to give the contractor a notice to cure a defect. This article raises such pertinent points that I wanted to address the issues and topics raised in this article.
558 Procedure–Owner’s Receipt of Contractor’s Repair Protocol
When a contractor submits a repair protocol to an owner in response to a notice of construction defects letter per Florida Statutes Chapter 558, the owner should seriously consider that protocol. The owner does this by discussing with counsel and any retained expert. The owner needs to know whether the protocol is a reasonable, cost-effective protocol to repair the asserted defects or, alternatively, whether the protocol is merely a band-aid approach and/or otherwise insufficiently addresses the claimed defects. Every scenario is different.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Katz, Barron, Squitero, Faust, Friedberg, English & Allen, P.A.Mr. Adelstein may be contacted at
dma@katzbarron.com
Residential Contractors, Be Sure to Have these Clauses in Your Contracts
December 23, 2023 —
Christopher G. Hill - Construction Law MusingsI have often “mused” on the need to have a good solid construction contract at the beginning of a project. While this is always true, it is particularly true in residential contracting where a homeowner may or may not know the construction process or have experience with large scale construction. Often you, as a construction general contractor, are providing the first large scale construction that the homeowner has experienced. For this reason, through meetings and the construction contract, setting expectations early and often is key.
As a side note to this need to set expectations, the Virginia Department of Professional and Occupational Regulation (DPOR) and the Virginia General Assembly require certain clauses to be in every residential construction contract. DPOR strictly enforces these contractual items and failure to put them in your contracts can lead to fines, penalties and possibly even revocation of a contractor’s license.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Brad Pitt’s Foundation Sues New Orleans Architect for Construction Defects
September 25, 2018 —
David Suggs – Bert L. Howe & Associates, Inc.Brad Pitt’s foundation has sued its architect of New Orleans projects alleging “defective design work led to leaks and other flaws in homes built for residents of an area that was among the hardest hit by Hurricane Katrina,” reported Insurance Journal.
The Make It Right Foundation claims damages of more than $15 million caused by architect John C. Williams. According to Insurance Journal, “The foundation paid Williams’ firm millions of dollars to produce architectural drawings for more than 100 homes under the program, which was supposed to provide Lower 9th Ward residents with sustainable and affordable new homes.”
This lawsuit against the architect is apparently in response to a class-action lawsuit by New Orleans attorney Ron Austin against Pitt’s Make It Right Foundation. Austin’s lawsuit “accused the charity of building substandard homes that are deteriorating at a rapid pace,” Insurance Journal reported.
The 39 homes involved in a previous suit regarding the manufacturer of TimberSIL are excluded from the lawsuit against Williams.
Read the court decisionRead the full story...Reprinted courtesy of
Primer Debuts on Life-Cycle Assessments of Embodied Carbon in Buildings
August 20, 2018 —
Engineering News-RecordA recently released primer for the use of a life-cycle assessment approach to analyze the environmental impacts of buildings is considered a small but necessary step toward the ambitious goal of getting to net-zero embodied carbon and operational greenhouse gas emissions in the construction, operation and decommissioning of buildings. The LCA guide comes after the release of the first-of-its-kind benchmarking database of embodied carbon in existing buildings. And another first—a tool to calculate embodied carbon in construction—is on the horizon.
Read the court decisionRead the full story...Reprinted courtesy of
Engineering News-RecordENR may be contacted at
ENR.com@bnpmedia.com
Colorado House Bill 17-1279 – A Misguided Attempt at Construction Defect Reform
March 29, 2017 —
David McClain - Colorado Construction LitigationOn March 17th, House Bill 17-1279, concerning the requirement that a unit owners’ association obtain approval through a vote of unit owners before filing a construction defect action, was introduced and assigned to the House State, Veterans, and Military Affairs Committee. The bill is currently scheduled for its first committee hearing on March 29th, at 1:30 in the afternoon. While, on its face, this appears to be a step in the right direction towards instituting “informed consent” before an HOA can file a construction defect action, the bill actually restricts the ability of developer to include more stringent requirements in the declaration of covenants, conditions, and restrictions for an association, thereby lowing the threshold of “consent” required to institute an action.
House Bill 17-1279 would amend C.R.S. § 38-33.3-303.5 to require an association’s executive board to mail or deliver written notice of the anticipated commencement of a construction defect action to each unit owner and to call a meeting of the unit owners to consider whether to bring such an action. Any construction professional against which a claim may attend the unit owners’ meeting and have an opportunity to address the unit owners and may include an offer to remedy any defect in accordance with C.R.S. § 13-20-803.5(3). The conclusion of the meeting would initiate a 120-day voting period, during which period the running of any applicable statutes of limitation or repose would be tolled. Pursuant to this bill, an executive board may only institute a construction defect action only if authorized by a simple majority of the unit owners, not including: 1) any unit owned by any construction professional, or affiliate of a construction professional, involved in the design, construction, or repair of any portion of the project; 2) any unit owned by a banking institution; 3) any unit owned in which no defects are alleged to exist, and/or 4) any unit owned by an individual deemed “nonresponsive.”
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com