Nondelegable Duties
June 04, 2024 —
David Adelstein - Florida Construction Legal UpdatesHave you heard the expression “nondelegable duty”? The issue of a nondelegable duty comes into play when a party hires an independent contractor and the independent contractor commits negligence, primarily in the personal injury context. In other words, a plaintiff wants to hold a defendant liable for the injuries caused by the defendant’s independent contractor.
A nondelegable duty is one that “may be imposed by statute, contract, or the common law. In determining whether a duty is nondelegable, the question is whether the responsibility at issue is so important to the community that an employer should not be allowed to transfer it to a third party.” Garcia v. Southern Cleaning Service, Inc., 360 So.3d 1209, 1211 (Fla. 3d DCA 2023) (internal citation omitted).
When it comes to CONTRACTUAL duties:
[S]pecifically the principle that one who undertakes by contract to do for another a given thing cannot excuse himself to the other for a faulty performance by showing that he hired someone else to perform the task and that other person was the one at fault. In other words, where the contracting party makes it her or his duty to perform a task, that party cannot escape liability for the damage caused to the other contracting party by the negligence of independent contractors hired to carry out the task.
Gordon v. Sanders, 692 So.2d 939, 941 (Fla. 3d DCA 1997).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Florida Court Puts the Claim of Landlord’s Insurer In The No-Fly Zone
March 06, 2023 —
William L. Doerler - The Subrogation StrategistIn United States Aviation Underwriters v. Turnberry Airport Holdings, LLC, No. 3D22-270, 2023 Fla. App. LEXIS 1207 (U.S. Aviation), the Court of Appeal of Florida, Third District (Appellate Court) considered whether the insurer for a commercial landlord could pursue subrogation against the landlord’s tenant. Based on the terms of the lease between the landlord and the tenant, the Appellate Court held that the landlord’s insurer could not pursue subrogation.
In U.S. Aviation, the defendant, Turnberry Airport Holdings, LLC (Turnberry Airport) leased space to an insured aircraft owner. The lease contained the following provision:
TENANT agrees that all policies of insurance obtained by it in connection with the Space or as required hereunder shall contain appropriate waiver of subrogation clauses.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Doerler, White and Williams LLPMr. Doerler may be contacted at
doerlerw@whiteandwilliams.com
MTA Implements Revised Contractors Debarment Regulations
July 06, 2020 —
Steven M. Charney, Gregory H. Chertoff & Paul Monte - Peckar & Abramson, P.C.On June 3, 2020, the Metropolitan Transit Authority (“MTA”) published and implemented revised regulations pertaining to the debarment of contractors. The revised regulations address many of the deep concerns raised by the contracting community.
Under relevant administrative procedure, the MTA publication of the revised regulations starts a 45 day notice period before the regulations can be adopted as final.
The prior regulations essentially required that debarment occur upon a purely formulaic calculation establishing that a contractor: 1) was more than 10% late, or 2) had submitted invalid claims that exceeded the adjusted contract price by a measure of 10%.
The revised regulations represent improvements over the prior regulations.
Critically, the revised regulations address the primary concern raised by the contracting community, that being the mandate of purely formulaic debarment. Instead, the revised regulations establish a process that includes greater flexibility and discretion before debarment may ensue.
Reprinted courtesy of Peckar & Abramson, P.C. attorneys
Steven M. Charney,
Gregory H. Chertoff and
Paul Monte
Mr. Charney may be contacted at scharney@pecklaw.com
Mr. Chertoff may be contacted at gchertoff@pecklaw.com
Mr. Monte may be contacted at pmonte@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Florida County Suspends Impact Fees to Spur Development
November 18, 2011 —
CDJ STAFFHernando County, just north of Tampa on Florida’s west coast, has suspended impact fees for a year, hoping to spur development. Hernando Today reports that the move drew applause from the audience at the county commissioners meeting. Many of those in attendance were builders or members of the Greater Hernando Chamber of Commerce.
Not all were convinced. Frankie Burnett, the mayor of Brooksville, told the commissioners that his city council were not convinced that this would spur development. “Development should pay its fair share, even in slow economic times.” Burnett’s letter to the board warned that “if lowering impact fees succeeded in stimulating more residential overbuilding, it would only further depress the current real estate market.”
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Fourth Circuit Clarifies What Qualifies As “Labor” Under The Miller Act
May 08, 2023 —
Jeffrey Hummel - The Construction SeytUnder the Miller Act, 40 U.S.C. §§ 3131 et seq., contractors hired to work on federal construction projects are required to furnish payment bonds in order to ensure payment to certain persons that provide labor for the project. The United States Court of Appeals for the Fourth Circuit recently issued a published decision clarifying the type of work that qualifies as “labor” under the Miller Act. Elliot Dickson v. Fidelity and Deposit Company (issued April 26, 2023).
In that case, the U.S. Department of Defense hired Forney Enterprises (Forney) as the prime contractor on a renovation project at the Pentagon. Forney retained Fidelity and Deposit Company of Maryland (Fidelity) to provide the required Miller Act payment bond. Forney then entered into a subcontract with Elliott Dickson (Dickson), a professional engineer, to work as a project manager on the contract. Dickson primarily supervised labor on the site, but also performed other tasks, including logistical and clerical duties, taking various field measurements, cleaning the worksite, moving tools and materials, and sometimes even watering the concrete himself. Dickson’s work required him to be onsite on a daily basis.
Read the court decisionRead the full story...Reprinted courtesy of
Jeffrey Hummel, SeyfarthMr. Hummel may be contacted at
jhummel@seyfarth.com
CGL Coverage for Liquidated Damages and the Contractual Liability Exclusion
October 09, 2023 —
Stu Richeson - The Dispute ResolverLiquidated delay damages are common in construction contracts and are generally imposed when a contractor fails to achieve substantial completion within the time required by the contract. While contracts like the AIA A201-2017 have provisions for extending the time to achieve substantial completion when delays are caused by circumstances beyond the contractor’s control, delays can result from factors other than improper management or planning and the like, for which the owner is not required to give the contractor additional time. Courts are split on whether there is ever coverage under a CGL policy for contractually agreed upon liquidated delay damages.
Liquidated delay damages are often excluded under the contractual liability exclusion of most CGL policies. The contractual liability exclusion excludes coverage for “liability for which the Insured is obligated to pay damages by reason of the assumption of liability in a contract or agreement.” Courts often find the contractual liability exclusion in a CGL policy precludes coverage for liquidated delay damages, because such damages are contractual in nature and are triggered by the failure to bring the contract to substantial completion by a fixed deadline, regardless of the cause of the delay. However, some courts will look to the cause of the delay and find that there is coverage under a CGL policy for liquidated delay damages that are the result of property damage caused by an accident or occurrence.
In Clark Const. Grp., Inc. v. Eagle Amalgamated Serv., Inc., 01-2478-DV, 2005 WL 2092998, at *1 (W.D. Tenn. Aug. 24, 2005) a general contractor entered a contract for the renovation of the convention center in Memphis. Part of the project included the demolition of a structure attached to the convention center. The demolition work was improperly performed by a subcontractor and resulted in damage to the convention center.
Read the court decisionRead the full story...Reprinted courtesy of
Stu Richeson, PhelpsMr. Richeson may be contacted at
stuart.richeson@phelps.com
Evaluating Construction Trends From 2023 and Forecasting For 2024
February 12, 2024 —
Jason Feld & Dominic Donato - Kahana FeldAs we begin 2024, it is informative to evaluate what transpired in 2023 in the construction industry, and especially the use of construction technology. 2023 ushered in a variety of newly implemented construction technologies including 3D printed entire houses, improved wearables that detect all aspects of the construction worker from location to temperature to heart rate, increased use of modular construction for entire apartments, hotels, and condominium projects, and eco-friendly and conservation minded technologies to minimize carbon footprint, water preservation and sustainable construction methods, to name a few.
2023 also identified some significant issues in the construction industry. First and foremost, the labor shortages and hiring of skilled and qualified workers continued to be an issue resulting in increased delays, construction accidents, and project mismanagement. The skyrocketing interest rates, decline in commercial/office projects, supply chain issues, material price fluctuation and increase changes in scope of projects all negatively impacted the construction industry in 2023. There is also the demand for renewable and infrastructure projects put strain on construction resources as the projects became “mega” with larger and more complex construction leading to multi-party, high dollar, and more complex claims. Finally, there is a growing trend of construction claims and litigation being financed by third party litigation funding sources for personal/bodily injury claims and construction defect claims.
Reprinted courtesy of
Jason Feld, Kahana Feld and
Dominic Donato, Kahana Feld
Mr. Feld may be contacted at jfeld@kahanafeld.com
Mr. Donato may be contacted at ddonato@kahanafeld.com
Read the court decisionRead the full story...Reprinted courtesy of
Summary Findings of the Fourth National Climate Assessment
January 02, 2019 —
Anthony B. Cavender - Gravel2GavelOn November 23, the latest National Climate Assessment, Fourth National Climate Assessment (NCA4), was released by the U.S. Global Research Program, as required by the Clean Air Act. The Assessment, comprising three volumes and 1600 pages, contains some rather bleak findings which the Report usefully summarizes. Here’s a description of these findings.
1.
Communities. The report states that “climate change creates new risks and exacerbates existing vulnerabilities in communities across the United States.” In particular, “more frequent and intense extreme weather and climate-related events” will continue to damage infrastructure , ecosystems and social systems. However, “global action” to significantly cut greenhouse gas emissions can substantially reduce these risks.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at