Florida Lien Law and Substantial Compliance vs. Strict Compliance
April 20, 2017 —
David Adelstein - Florida Construction Legal UpdatesThere are literally some (or, perhaps, many!) disputes that will make you say “hmm!” The “hmm” is a euphemism for “what is a party thinking?!?” The case of Trump Endeavor 12 LLC v. Fernich, Inc., 42 Fla. L.Weekly D830a (Fla. 3d DCA 2017) is one of these cases because a party (the owner) is banking its defense on a technical “all-or-nothing” argument pertaining to whether a lienor (a supplier) substantially complied with Florida’s Lien Law because a supplier’s Notice to Owner identified the wrong general contractor. This is a challenging argument because the owner has to prove how they were adversely affected / prejudiced by the lack of substantial compliance, which is not an easy burden.
This case concerns the Trump National Doral Miami project. The project consisted of a lodge project and a separate clubhouse project, both of which had different general contractors. On the lodge project, the general contractor hired a painter which, in turn, procured paint from a supplier (the lienor). The supplier visited the project and obtained the Notice of Commencement from the owner so that it could perfect its lien rights. The owner furnished the supplier the Notice of Commencement for the clubhouse project that had a different general contractor. Relying on this Notice of Commencement, the supplier served a Notice to Owner. The Notice to Owner was timely serviced however it identified the wrong contractor – it identified the general contractor for the clubhouse project instead of the lodge project. Although the supplier later learned there was a different general contractor on the lodge project, it did not remedy the issue by serving a Notice to Owner on the correct contractor. Indeed, the contractor for the lodge project learned of the Notice to Owner furnished by the supplier and that the supplier was furnishing paint to the painting subcontractor for purposes of that project.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
Dadelstein@gmail.com
Attorneys’ Fees and the American Arbitration Association Rule
September 09, 2024 —
Bill Wilson - Construction Law ZoneA common question from clients, when a dispute arises on a construction project, is whether they can recover their attorney’s fees from the other side if they pursue a case and win. More often than not, such fees are not recoverable. As a general rule (commonly known as the “American Rule”), each party to a dispute must bear their own attorney’s fees unless there is some statutory provision or contractual agreement between the parties allowing otherwise. Since most construction disputes involve claims for breach of contract and/or negligence, no realistic statutory provision often allows for attorney’s fees. Many construction contracts do not typically provide a prevailing party the right to collect attorney’s fees from the other side. However, even if the American Rule applies, there may be another path to recovering attorney’s fees if the parties agree to arbitrate their dispute under the American Arbitration Association (AAA) rules.
Reprinted courtesy of
Bill Wilson, Robinson & Cole LLP
Mr. Wilson may be contacted at wwilson@rc.com
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
Proposition 65: OEHHA to Consider Adding and Delisting Certain Chemicals of Concern
September 03, 2015 —
Lee Marshall & Jeffrey A. Vinnick – Haight Brown & Bonesteel LLPThe Office of Environmental Health Hazard Assessment (“OEHHA”), which is responsible for determining the chemicals that are included on its list of chemicals known to be carcinogenic or to cause reproductive harm, thereby requiring businesses to comply with the rules accorded under California’s Proposition 65, has announced the beginning of a 45-day public comment period on five chemicals:
- Nickel
- Pentachlorophenol
- Perfluorooctanoic acid (PFOA)
- Perfluorooctane sulfonate (PFOS)
- Tetrachloroethylene
Reprinted courtesy of Lee Marshall, Haight Brown & Bonesteel LLP and Jeffrey A. Vinnick, Haight Brown & Bonesteel LLP
Mr. Marshall may be contacted at lmarshall@hbblaw.com
Mr. Vinnick may be contacted at jvinnick@hbblaw.com
Read the court decision
Read the full story...
Reprinted courtesy of
Bankrupt Canada Contractor Execs Ordered to Repay $26 Million
April 25, 2022 — Scott Van Voorhis - Engineering News-Record
John Aquino, the former president of a major and now bankrupt Ontario construction contractor, plans to appeal a provincial court ruling that puts him and his associates on the hook for $26.2 million drained from the company, according to his attorney.
Reprinted courtesy of Scott Van Voorhis, Engineering News-Record
ENR may be contacted at enr@enr.com
Read the full story... Read the court decision
Read the full story...
Reprinted courtesy of
Difficult Task for Court to Analyze Delay and Disorder on Construction Project
August 23, 2021 — David Adelstein - Florida Construction Legal Updates
One of my favorites quotes from a case, and I am sure others in the construction industry feel the same way or can relate, is from the District of Columbia Court of Appeals in Blake Construction Co., Inc. v. C.J. Coakley Co., Inc., 431 A.2d 569, 575 (D.C. 1981):
We note parenthetically and at the outset that, except in the middle of a battlefield, nowhere must men coordinate the movement of other men and all materials in the midst of such chaos and with such limited certainty of present facts and future occurrences as in a huge construction project such as the building of this 100 million dollar hospital. Even the most painstaking planning frequently turns out to be mere conjecture and accommodation to changes must necessarily be of the rough, quick and ad hoc sort, analogous to ever-changing commands on the battlefield. Further, it is a difficult task for a court to be able to examine testimony and evidence in the quiet of a courtroom several years later concerning such confusion and then extract from them a determination of precisely when the disorder and constant readjustment, which is to be expected by any subcontractor on a job site, become so extreme, so debilitating and so unreasonable as to constitute a breach of contract between a contractor and a subcontractor.
Do you agree with this sentiment? The reality is that retrospectively analyzing delay on a complicated construction project with numerous moving parts on a day-by-day, hour-by-hour, basis is no easy feat. It is not easy for the parties and certainly not easy for courts to unravel. With every party claiming delay based on a retrospective analysis there will be another party with either a different delay analysis or providing credible cross examination as to flaws with the delay analysis. The same bodes true with loss of productivity / inefficiency claims and the particular case-specific facts are important, preferably with evidence such as photos, videos, notifications, daily reports, manpower reports, etc., supporting the facts. But the facts are complicated, and the delay analysis is complicated, and it is a difficult task for a trier of fact to unravel these facts. Read the court decision
Read the full story...
Reprinted courtesy of David Adelstein, Kirwin Norris, P.A.
Mr. Adelstein may be contacted at dma@kirwinnorris.com
I’m Sorry Ms. Jackson, I [Sovereign Immunity] am For Real
June 08, 2020 — Greggory Jacobs - Florida Construction Law News Blog
The Supreme Court of Florida issued its opinion in Florida Highway Patrol v. Jackson, 2020 Fla. LEXIS 108 (Fla. Jan 23, 2020), which answered the following certified question of great public importance:
Does rule 9.130 [(A)(3)(C)(XI)] permit an appeal of a non-final order denying immunity if the record shows that the defendant is entitled to immunity as a matter of law but the trial court did not explicitly preclude it as a defense?
The Court’s answer to this question was “no.” But this opinion stands for much more than just a negative answer to a certified question. Indeed, this opinion has significant implications upon procedural and substantive areas of construction law, which may affect agents of the state of Florida, including Construction Engineering and Inspection professionals and consultants (“CEI”).
Procedurally, the Court recognizes that Fla. R. App. P. 9.130 insufficiently protects the public and governmental interests as “it leaves too great a risk that erroneous denials of operational sovereign immunity will go unreviewed until it is too late.” Id. at * 19. By extension of this risk, the Jackson Court announced that “courts should determine entitlement to sovereign immunity as early as the record permits.” Id. at * 18. In fact, on that basis, courts can address a motion for summary judgment asserting entitlement to sovereign immunity even if there are outstanding disputes as to, say, the existence of a duty of care. Id. at 17-18. Accordingly, and in an effort to remedy the risk of erroneous denials going unreviewed until it is too late, the Court amended Fla. R. App. P. 9.130 to expand appellate review of nonfinal orders denying sovereign immunity. Jackson, 2020 Fla. LEXIS 108 at * 19; In re Amendments to Fla. Rule of Appellate Procedure 9.130, No. SC19-1734 (Fla. Jan. 23, 2020). The new form of Fla. R. App. P. 9.130 cements the policy mentioned above because it allows an appeal of a nonfinal order denying a motion for summary judgment due to entitlement to sovereign immunity. Meanwhile, under the old rule, the order was only appealable if the trial court order determined – as a matter of law – that a party was not entitled to sovereign immunity. As such, the new rule focuses on what was argued in the motion as opposed to what was written in the order. Read the court decision
Read the full story...
Reprinted courtesy of Greggory Jacobs, Cole, Scott & Kissane, P.A.
Mr. Jacobs may be contacted at greggory.jacobs@csklegal.com
Buffalo-Area Roof Collapses Threaten Lives, Businesses After Historic Snowfall
December 05, 2022 — Thomas Leffler - AccuWeather
After a historical snowfall event in the Buffalo area this past week, residents weren’t just taking to the driveways and sidewalks to clear snow. In the Buffalo suburb of Orchard Park, New York (home to the NFL’s Buffalo Bills), the 80 inches of snow that accumulated was also cleared off local roofs in order to prevent a major danger to homes.
Snow as deep and heavy as the recent lake-effect snowstorm can cause roofs to collapse, threatening the lives of people who live inside. An unfortunate scenario befell Buffalo in November 2014, when a 6-foot snow event known as “Snowvember” led to emergency calls for numerous collapsed roofs around the region.
One Orchard Park business, Graffiti Grafix & Signs, had its roof collapse in 2014 and had about a third of the roof come down once again this past week, according to The Buffalo News. Orchard Park Police Chief Patrick Fitzgerald noted in an email that three commercial properties in Orchard Park, including Graffiti Grafix & Signs, suffered damage from roof collapse.
Read the court decision
Read the full story...
Reprinted courtesy of AccuWeather
Montana Federal Court Upholds Application of Anti-Concurrent Causation Clause
November 08, 2021 — Tred R. Eyerly - Insurance Law Hawaii
Interpreting Montana law, the federal district court found that the policy's anti-concurrent causation clause prevented coverage for the insured's damaged home. Ward v. Safeco Ins. Co. of Am., 2021 U.S. Dist. LEXIS 149051 (D. Mont. Aug. 9, 2021).
Plaintiff was advised by her tenants that water was bubbling up from the ground. It was determined that water was leaking from a main pipe serving the property. Subsequently, this old pipe was abandoned, left in the ground, and replaced with a new pipe in a new path with new excavation. Nevertheless, the insured reported the incident to her agent under her Landlord Protection Policy issued by Safeco, but reported there was no damage to the property.
Two months later, it was discovered a pipe burst again. The insured called her agent, who maintained the loss would not be covered, but agreed to submit a claim to Safeco. Safeco hired an inspector. A report stated that a portion of cracks found in the concrete perimeter of the home were not new and that the shape of the structure on which the house sat could explain their presence. The report noted that new cracks in the foundation could have been caused by a lack of care to make sure that the foundation was sufficient supported by consolidated soil during the excavation of the new water line. Based upon this report, Safeco denied coverage based upon the earth movement and water damage exclusions. Read the court decision
Read the full story...
Reprinted courtesy of Tred R. Eyerly, Damon Key Leong Kupchak Hastert
Mr. Eyerly may be contacted at te@hawaiilawyer.com