Nevada Budget Remains at Impasse over Construction Defect Law
June 01, 2011 —
CDJ STAFFNegotiations for the Nevada state budget have stalled over proposals to amend the state’s construction defect laws. Assembly Republicans had offered changes to the law to make it friendlier to contractors; however, after a state Supreme Court ruling that the state could not move a local government entity’s funds into state coffers, pressure has increased on the governor to lift the expiration dates of taxes approved in 2009.
The Reno Gazette-Journal quotes John Madole, a construction industry lobbyist, “We agree with them that you have to address the issue of the attorney fees, and for all practical purposes, they are automatically awarded when anybody brings any kind of suit.”
Speaker of the Assembly, John Oceguera, a Democrat, has proposed a bill that “makes it absolutely crystal clear that the only time you get attorney's fees is if you're the prevailing party.”
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Supreme Court of New Jersey Reviews Statutes of Limitation and the Discovery Rule in Construction Defect Cases
July 18, 2018 —
David Suggs – Bert L. Howe & Associates, Inc.Robert Neff Jr. of Wilson Elser analyzed the recent case, Palisades at Fort Lee Condo. Ass’n v. 100 Old Palisade, LLC, 2017 N.J. Lexis 845, 169 A.3d 473 (Supreme Court of New Jersey, September 14, 2017), and states that this ruling “gives defendants the ability to defend against the assertion that the statute of limitations was tolled until the most recent owner (and plaintiff) discovered the cause of action.”
Neff concludes that a statute of limitations test needs to be conducted at the beginning of each case: “In Palisades, the motions to dismiss based on the statute of limitations were filed at the conclusion of all discovery. While an initial analysis might yield the conclusion that certain discovery will be needed to ascertain the appropriate accrual date (or dates, in the case of multiple defendants), counsel will then know what discovery to seek during the discovery period.”
Read the court decisionRead the full story...Reprinted courtesy of
Collapse of Breezeway Attached to Building Covered
February 24, 2020 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court found that a breezeway that collapsed during a party was covered by the commercial property policy. DENC, LLC v. Philadelphia Indem. Ins. Co., 2019 U.S. Dist. LEXIS 179083 (M.D. N.C. Oct. 15, 2019).
DENC owned an apartment complex that was insured by Philadelphia under an all-risk policy. During an early morning party, a large number of students gathered on the second-floor breezeway for a party. The students started jumping in the breezeway when a certain song started playing. The floor abruptly collapsed underneath the students.
Philadelphia sent an adjuster to inspect the breezeway a couple days later. He wrote to Philadelphia that "the sole and proximate cause of the loss is water damage occurring over an extended period of time causing the second floor breezeway to sage and the light weight concrete to crack." Shortly thereafter, the building was condemned. A structural engineer found multiple ways in which water had seeped into the breezeway's wood framing and photographed the resulting biological growth and wood decay. He concluded that the building had sustained significant long-term water intrusion which resulted in the wood framing inability to support the loads. The water intrusion was caused by the failure to properly install a water management system on the walls, a properly integrated waterproof system for the walkway slab and framing configuration, and improper venting of dryers.
DENC retained an engineer who testified that the breezeway was sagging because the concrete had broken.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Slow Down?
December 03, 2024 —
Daniel Lund III - LexologyAbsolutely not, said the Louisiana Fifth Circuit Court of Appeal to a masonry subcontractor being sued for allegedly improperly refusing to honor a subcontract bid.
A general contractor preparing its overall bid for a public project in Jefferson Parish relied in the process on the defendant masonry subcontractor’s bid. After a public bid process and receiving the award of the project, the general contractor was informed by the subcontractor that it believed that the unit price form that had been supplied to the sub “contained inaccuracies.” Notwithstanding offers by the GC to endeavor to address the purported “inaccuracies” during the project, most likely by a change order, the subcontractor refused to execute its subcontract. The general contractor then awarded the masonry work to another subcontractor for $368,222 more than the original sub’s bid.
The GC filed suit – for recovery of $368,222 – against the defendant subcontractor during the course of the public project. The defendant sub objected, arguing to the court that the lawsuit was “premature.” At the heart of the prematurity argument: the sub urging that the general contractor filed suit before its right to recover damages had accrued.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Homebuilding in Las Vegas Slows but Doesn’t Fall
October 15, 2013 —
CDJ STAFFThere was an 18 percent drop in the sale of new homes in September, as compared to the prior month, but that was still 6 percent higher than the home sales of the previous September. So far, August was the briskest month for homes sales in Las Vegas for 2013. Through September, builders have sold 5,653 homes, which is a fifty-three percent increase over the first nine months of 2012. Dennis Smith, the president of Home Builders Research said “that is a very strong annual change that clearly suggests new housing has revered from the recessionary doldrums of the past four years.”
Read the court decisionRead the full story...Reprinted courtesy of
A Year Later, Homeowners Still Repairing Damage from Sandy
October 01, 2013 —
CDJ STAFFThe New York and New Jersey coastal communities are still in the thick of rebuilding and repairing after hurricane Sandy struck almost a year ago. Newsday reports that in the eight months following the October 2012 storm, more than 23,000 building permits were issued in Long Island communities, an 11 percent rise over the previous year. The town of Long Beach, New York has waived fees and hired more staff in order to encourage people to rebuild, in order to rebuild the town’s tax base.
Homeowners aren’t going it alone, New York expects to fund more than $1 billion of rebuilding for homeowners who are unable to afford repairing their homes. At this point, the state is still processing more than five thousand requests for grants. The money is still in the state’s coffers. Other homeowners are still filing insurance claims.
While towns are busy issuing building permits, contractors are busy too. Bill Sims of Sims Steel said that his business has changed from commercial construction to raising homes higher to put them above future floods. “There’s probably been more homes raised this last year than in the previous 20 years,” he told Newsday. Another contractor, Pat Gordon said that he is “only taking what we can handle.” He described Long Beach as “a traffic jam of construction trucks that has never been seen before.”
Read the court decisionRead the full story...Reprinted courtesy of
OSHA Issues COVID-19 Guidance for Construction Industry
July 13, 2020 —
Garret Murai - California Construction Law BlogThis past month, after remaining relatively quiet following the coronavirus outbreak, OSHA began issuing industry-specific guidance on how to deal with the coronavirus in the workplace.
Until this month, the only construction industry specific guidance issued by OSHA was an OSHA Alert entitled COVID-19 Guidance for the Construction Workforce, a one page document providing little more guidance than that workers should stay home if sick, wear masks and frequently wash hands to prevent spreading and catching the coronavirus, and to sanitize tools and work areas.
Early this month, OSHA issued more comprehensive guidance for the construction industry. The guidance, as noted in the preface by OSHA is simply guidance, “is not a standard or regulation” and “creates no legal obligations. The guidance supplements general guidance applicable to all workplaces issued earlier by OSHA.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Ruling Dealing with Constructive Changes, Constructive Suspension, and the Implied Covenant of Good Faith and Fair Dealing
January 22, 2024 —
David Adelstein - Florida Construction Legal UpdatesA dispute pending in the Armed Services Board of Contract Appeals (ASBCA) dealt with interesting legal issues on a motion to dismiss. See Appeals of McCarthy Hitt-Next NGA West JV, ASBCA No. 63571, 2023 WL 9179193 (ASBCA 2023). The dispute involves a contractor passing through subcontractor claims due to impacts caused by the COVID-19 pandemic and the government’s response to the pandemic. More particularly, the claim centers on the premise that the government “failed to work with [the contractor] in good faith to develop a collaborative and cooperative approach to manage and mitigate the impacts and delays arising from the COVID-19 pandemic.” See Appeals of McCarthy Hitt.
The contractor (again, submitting pass through claims from subcontractors) claimed: (a) constructive changes to the contract entitling it to an equitable adjustment under the Changes clause of Federal Acquisition Regulation (F.A.R.) 52.243-4; (b) construction suspensions of the contractor’s work entitling it to an equitable adjustment under the Suspensions of Work clause of F.A.R. 52-242-14; and (c) the government breached the implied covenant of good faith and fair dealing. Each of these legal issues and theories will be discussed below because they are need-to-know legal issues. Keep these legal issues in mind, and the ASBCA’s ruling on the motion to dismiss as its analysis may demonstrate fruitful in other applications.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com