Federal Court Ruling Bolsters the “Your Work” Exclusion in Standard CGL Policies
October 27, 2016 —
Daniel E. Levin – Florida Construction Law NewsIn Evanston Insurance Company v. Dimucci Development Corportion of Ponce Inlet, Inc., the United states District Court for the Middle District of Florida further clarified the standard CGL policy exclusion (L) – the “Your Work” exclusion, one of the several business risk exclusions in a standard CGL policy which insurers and insureds are most likely to encounter in a typical construction defect claim. No. 6:15-cv-486-Orl-37DAB, 2016 U.S. Dist. LEXIS 123678, at *26 (M.D. Fla. Sep. 13, 2016).
The lawsuit between Evanston Insurance Company and DiMucci Development Corp. of Ponce Inlet Inc. (“DiMucci”) arose out of initial claims by the homeowners’ association at the Towers Grande high rise in Daytona Beach Shores, Florida, against DiMucci for various construction defect related issues. The lawsuit alleged that DiMucci’s work was defective on a portion of the high rise condominium project, which caused property damage to other elements of the building that DiMucci was also responsible for constructing. Specifically, pertinent here, the Association alleged water damage as a result of DiMucci’s improper waterproofing of the building.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel E. Levin, Cole, Scott & Kissane, P.A.Mr. Levin may be contacted at
daniel.levin@csklegal.com
How to Mitigate Lien Release Bond Premiums with Disappearing Lien Claimants
May 20, 2019 —
Scott MacDonald - Ahlers Cressman & Sleight PLLCIt is one of those dreaded business situations that plagues the construction industry, especially in times of economic downturn—what to do when a lower-tier entity files a lien against a property then disappears. It has happened to countless owners, general contractors, subcontractors, and even some particularly unlucky sub-tier subcontractors and suppliers. Here is how it arises: a project is moving along, then performance or payment issues arise, and a company that is over extended or unwilling to continue work stops performance, walks off the job, and files a lien against the property for whatever amounts were allegedly unpaid. Often, the allegedly unpaid sums were legitimately withheld due to a good faith dispute over payment/performance, and it is not unusual for the defaulting entity to not be entitled to any of the sums claimed in the lien. Regardless, the lien stays on the property, and pressure is applied from the “upstream” entities to the party who contracted with the defaulting entity to “deal” with the lien.
Oftentimes, a contract will require the parties to “deal” with a lien by obtaining a lien release bond (“release bond”). For those lucky enough to not have encountered this issue, a release bond is a nifty statutory device whereby a surety agrees to record a release bond for the full claimed amount of the lien, with the release bond substituting in for the liened property, effectively discharging the property from liability under the lien. In other words, the lien is released from the property and attaches to the release bond. If the lien claimant recovers on its lien, it is technically satisfied by the surety providing the release bond (or the party who agrees to indemnify and defend the release bond). In exchange for delivering the release bond, the surety demands yearly premiums be paid on the release bond amount
Read the court decisionRead the full story...Reprinted courtesy of
Scott MacDonald, Ahlers Cressman & Sleight PLLCMr. MacDonald may be contacted at
scott.macdonald@acslawyers.com
The Looming Housing Crisis and Limited Government Relief—An Examination of the CDC Eviction Moratorium Two Months In
December 14, 2020 —
Zachary Kessler - Gravel2GavelMonths after the Centers for Disease Control and Prevention (CDC) issued a nationwide eviction moratorium using its emergency pandemic powers under the Public Health Service Act, the efficacy of this unprecedented measure remains unclear. While the Order ostensibly protects tenants facing homelessness or housing insecurity due to the financial impacts of the COVID-19 pandemic through the end of 2020, legal challenges have been initiated in Ohio and Georgia, with additional lawsuits appearing likely. Further, even barring legal challenges, courts have not handled these cases in a uniform manner. With lawmakers unable to reach any stimulus or COVID-19 relief agreement before the election, the CDC Order appears likely to remain the only federal eviction moratorium through its expiration on December 31, 2020.
Since the Order’s enactment, the CDC has since released new guidance, answering some of the open questions not covered by the initial Order. This guidance, while non-binding, is largely more favorable to landlords and property management companies than the initial text of the Order, as it provides that landlords are not required to make tenants aware of the Order’s protections and may challenge the truthfulness of the tenants’ declarations in any state or municipal court. The guidance also clarified the potential criminal penalties for violating the Order and the criminal penalties for perjury for bad faith submissions of the requisite declaration by tenants.
Read the court decisionRead the full story...Reprinted courtesy of
Zachary Kessler, PillsburyMr. Kessler may be contacted at
zachary.kessler@pillsburylaw.com
Conspirators Bilked Homeowners in Nevada Construction Defect Claims
March 28, 2012 —
CDJ STAFFCourthouse News has a summary of the current lawsuit over a Nevada conspiracy to defraud homeowners by taking control of homeowner boards and then providing inadequate repairs. Homeowners in eight Las Vegas area communities are involved in the suit, which claims that the conspirators purchased units in the communities and then transferred fractional interests to others to allow them to run for HOA board elections. The suit claims that David Amesbury and his firm helped manipulate the elections.
Once homeowner boards were controlled by the conspirators, Nancy Quon, the construction defect attorney whose recent death appears to be by suicide, handled the litigation against homebuilders. She would settle out of court, engaging Silver Lining Construction to “do very minor and superficial repairs” to the homes. The remainder of the money was split by the conspirators. The suit also notes that the construction defect claims were “frivolous,” and?in addition to the negative publicity?caused the homes to lose at least 5% of their value.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Sierra Pacific v. Bradbury Goes Unchallenged: Colorado’s Six-Year Statute of Repose Begins When a Subcontractor’s Scope of Work Ends
November 03, 2016 —
Luke Mecklenburg – Snell & Wilmer Real Estate Litigation BlogIt’s official: the October 20, 2016 deadline to petition for certiorari to the Colorado Court of Appeals on its decision in Sierra Pacific Industries, Inc. v. Bradbury has passed, so it appears that decision will stand.
In Sierra Pacific, the Court of Appeals held as a matter of first impression that the statute of repose for a general contractor to sue a subcontractor begins to run when a subcontractor’s scope of work is substantially complete, regardless of the status of the overall project. Sierra Pac. Indus., Inc. v. Bradbury, 2016 COA 132, ¶ 28, ___ P.3d ___. The Court of Appeals interpreted the statute of repose in C.R.S. section 13-80-104, which requires that “all actions against any architect, contractor, builder or builder vendor, engineer, or inspector performing or furnishing the design, planning, supervision, inspection, construction, or observation of any improvement to real property” must be brought within six years of substantial completion of that improvement. C.R.S. § 13-80-104(1)(a). Recognizing that “an improvement may be [to] a discrete component of an entire project” under Shaw Construction, LLC v. United Builder Services, Inc., 296 P.3d 145 (Colo. App. 2012), the Court of Appeals determined that “a subcontractor has substantially completed its role in the improvement at issue when it finishes working on the improvement.” Sierra Pac., 2016 COA at ¶¶ 20, 28. In doing so, it rejected Sierra Pacific’s argument that the statute could be tolled under the repair doctrine “while others worked to repair [the subcontractor’s] ‘improper installation work and flawed repair work.’” Id. at ¶ 29. Because six years had undisputedly passed since the subcontractor completed its scope of work when Sierra Pacific filed suit against it, the Court of Appeals affirmed the trial court’s order granting the subcontractor’s motion for summary judgment under Section 13-80-104(1)(a).
Read the court decisionRead the full story...Reprinted courtesy of
Luke Mecklenburg, Snell & Wilmer Real Estate Litigation BlogMr. Mecklenburg may be contacted at
lmecklenburg@swlaw.com
Nonparty Discovery in California Arbitration: How to Get What You Want
January 08, 2019 —
Leilani L. Jones - Payne & FearsOpting for arbitration requires attorneys to balance efficiency and procedural protections. The implications of arbitration are something clients certainly have to carefully consider both when drafting arbitration provisions, and after initiating a demand. While arbitration can in many respects streamline the civil discovery process, one of the largest roadblocks for cases in California arbitrations is “streamlining” discovery from nonparties. This article explores the challenges presented by third party discovery in arbitration, and proposes strategies for obtaining such discovery efficiently and expeditiously.
Read the court decisionRead the full story...Reprinted courtesy of
Leilani L. Jones, Payne & FearsMs. Jones may be contacted at
llj@paynefears.com
Federal Government Partial Shutdown – Picking Up the Pieces
February 27, 2019 —
Jacob W. Scott - Now that the partial shutdown has ended (though with the specter of another just around the corner), contractors are asking, “What now?” and “What did that cost me?” Although every case is fact-specific, following are some guidelines for moving forward after the shutdown.
Following up on our previous guidance, contractors should make sure that any court, board, or agency filings made during the shutdown were received and properly docketed. If there is any question whether a filing was received, file it again as soon as possible with proof of the earlier attempt to file. The busiest tribunals, such as the federal courts, the Court of Federal Claims, the Boards of Contract Appeals, and the Government Accountability Office, remained open, or at least open to accept filings, and all indications are that filings made during the shutdown were received and acknowledged. But for some of the other tribunals or agencies, such as the Small Business Administration (“SBA”) Office of Hearings and Appeals and the SBA Office of Government Contracting and Business Development, prudence dictates double-checking that all filings were received. In many cases, non-statutory deadlines have been or will be adjusted by the court, board, or agency.
Read the court decisionRead the full story...Reprinted courtesy of
Jacob W. Scott, Smith CurrieMr. Scott may be contacted at
jwscott@smithcurrie.com
Denver Airport Terminates P3 Contract For Main Terminal Renovation
November 12, 2019 —
Mark Shaw - Engineering News-RecordIn a move that stunned transportation planners around the country, Denver International Airport terminated the contractor team working on a $650-million terminal renovation. The move also ended the airport’s $1.8-billion public-private partnership with Great Hall Partners, a consortium led by Ferrovial Airports, with partners Saunders/JLC Infrastructure.
Mark Shaw, Engineering News-Record
Mr. Shaw may be contacted at shawm@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of