Pennsylvania Court Finds that Two Possible Causes Can Prove a Product Malfunction Theory of Liability
September 29, 2021 —
Gus Sara - The Subrogation StrategistIn Allstate Ins. Co. v. LG Elecs. USA, Inc., No. 19-3529, 2021 U.S. Dist. LEXIS 127014, the United States District Court for the Eastern District of Pennsylvania considered whether plaintiff’s expert engineer’s opinion that there were two possible causes of a fire—both related to alleged product defects within a refrigerator manufactured by the defendant—was sufficient to support the malfunction theory of products liability. The court found that because both potential causes imposed liability on the product manufacturer and the expert ruled out misuse of the product, as well as all external causes of the fire, it was not necessary for the engineer to identify a specific cause under the malfunction theory. The court also found that the expert’s investigation and opinions met the criteria set forth in Daubert v. Merrell Dow Pharms., Inc., 509 U.S. 579 (1993) and the Federal Rules of Evidence and, thus, were admissible.
LG Electronics arose from a fire at the home of Thomas and Lisa Ellis. The public sector fire investigator identified the area of fire origin as the top of a refrigerator manufactured by LG Electronics USA, Inc. (LG). The Ellises filed a claim with their homeowner’s insurance carrier, Allstate Insurance Company (Insurer). Insurer retained a fire investigator and an electrical engineer to investigate the origin and cause of the fire. The fire investigator agreed with the public sector investigator that the fire originated at the top of the refrigerator. The engineer conducted a forensic inspection of the scene and ruled out all potential external ignition sources. He then examined the internal components of the refrigerator. He found arcing activity on a wire at the front top of the refrigerator. He opined that there were two possible causes of the fire: either the heater circuit insulation failed over time due to mechanical damage, or the heat from the internal light fixture ignited combustible components of the refrigerator. Since the engineer ruled out improper use of the refrigerator, he opined that the damage was caused by a manufacturing defect.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
ASCE Statement on Hurricane Milton and Environmental Threats
October 15, 2024 —
Feniosky Peña-Mora, P.E., President - American Society of Civil EngineersWASHINGTON, DC. – On the heels of the tragic damage caused by Hurricane Helene throughout the Southeast, Floridians were struck by another major hurricane, Milton, less than two weeks later. Our hearts go out to those impacted again by this storm through property damage, lack of water access, power outages, or worse, loss of life, all before getting a chance to recover from Helene. Civil engineers are dedicated to protecting the public with projects that can lessen the impacts of these storms, and we are eager to help communities rebuild as quickly as possible following events like Milton and Helene.
Although we do not yet know the full scope of destruction caused by Hurricane Milton, severe weather, including compound flooding events, are increasing regularly and pose a great risk to our safety and economic vitality. While so many eyes are fixated on hurricanes impacting the Southeast, wildfires are burning across several western states, including the Elk Fire in Wyoming, the largest wildfire the Bighorn National Forest has experienced in more than a century, now spanning over 75,000 acres as the region is experiencing unusually hot and dry weather and strong winds that are helping this fire to spread rapidly. The climate impacts we are accustomed to – wildfires in the West and hurricanes in the Southeast – are getting stronger, and now environmental challenges are occurring in areas we wouldn't suspect, such as Hurricane Helene striking mountain communities in Western North Carolina that have been labeled as "climate safe-havens," and Texas dealing with annual winter storms.
ASCE is a leader in codes and standards development and has created an
easy-to-understand toolkit for legislators and the public to learn the benefits of these up-to-date standards and determine when and how to adopt them, making our built environment more resilient to natural catastrophes. ASCE's flagship standard,
ASCE/SEI 7-22, recently underwent the most significant update to its
flooding chapter to ensure structures following this standard are prepared for 500-year flood events.
Read the court decisionRead the full story...Reprinted courtesy of
Top 10 Take-Aways from the 2024 Fall Forum Meeting in Pittsburgh
December 03, 2024 —
Marissa L. Downs - The Dispute ResolverOver 500 construction law attorneys and consultants convened last week at the confluence of three rivers in what became the first-ever meeting in Pittsburgh, Pennsylvania of the ABA Forum on Construction Law. The Steel City was a fitting backdrop for a meeting focused on issues of design in construction. Thanks to the hard work of many, most notably the newly minted Forum Chair Keith Bergeron and Meeting Coordinators Kendall Woods and Michael Clark, the meeting's attendees brought home new connections and a host of new lessons learned. Read on for my top 10 take-aways from the 2024 Fall Meeting in Pittsburgh and feel free to share yours in the comments below.
10. An architect's standard of care does not require perfection. A common refrain across many of the meeting's plenary sessions was that any design that is produced by human hands will never be perfect. In recognition of our own fallibility, the legal standard to which design professionals will be held to account does not require that their designs be error-free. A design professional must generally exercise the degree of care and skill ordinarily exercised by professionals performing similar services under similar circumstances. Establishing what that means in each locality will vary and will most likely need to be supported by the expert opinion of another practicing design professional.
Read the court decisionRead the full story...Reprinted courtesy of
Marissa L. Downs, Laurie & Brennan, LLPMs. Downs may be contacted at
mdowns@lauriebrennan.com
Following Pennsylvania Trend, Federal Court Finds No Coverage For Construction Defect
December 08, 2016 —
Tred R. Eyerly – Insurance Law HawaiiBound by Pennsylvania law, the federal district court found there was no coverage for defects in the installation of a roof. State Farm Fire & Cas. Co. v. Kim's Asia Constr., 2016 U.S. Dist. LEXIS 138915 (E.D. Pa. Oct. 5, 2016).
Kim's Asia Construction contracted to remove and dispose of Powerline Imports, Inc.'s roof, and then install a new roof. After completion of the project, Powerline sued, alleging that Kim's Asia's negligent construction of the roof caused the roof to leak, even in minor rain storms. Kim's Asia made additional repairs, but the leaks continued. Powerline had to hire a new contractor to remove and dispose of the roof and install another roof. Powerline then sued Kim's Asia.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Mississippi Supreme Court Addresses Earth Movement Exclusion
December 09, 2019 —
Anthony Hatzilabrou - Traub LiebermanRecently, the Mississippi Supreme Court held that structural damages to the foundation of an insured’s home came within the earth movement exclusion in a homeowner’s policy, notwithstanding a provision in the policy which provided coverage for water damage resulting “from accidental discharge or overflow of water … from within … [p]lumbing, heating, air condition or household appliance.”
In Mississippi Farm Bureau Cas. Ins. Co. v. Smith, 264 So. 3d 737 (Miss. 2019), the appellee, Smith, filed a lawsuit against her homeowner's insurance company, Mississippi Farm Bureau Casualty Insurance Company (“Farm Bureau”) for its refusal to pay for repairs to the foundation of Smith’s home. Smith alleged that the refusal to pay for repairs amounted to breach of contract and asserted claims for bad faith and tortious breach of contract. In response, Farm Bureau filed a motion for summary judgment on the basis of the policy’s earth-movement exclusion, which provided that Farm Bureau “did not insure for loss caused directly or indirectly by…Earth Movement…[which] means…[a]ny other earth movement including earth sinking, rising or shifting... caused by or resulting from human or animal forces.” Smith filed a cross-motion for partial summary judgment on the basis that the earth-movement exclusion did not preclude coverage because her insurance policy also contained a clause expressly covering water damage.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony Hatzilabrou, Traub LiebermanMr. Hatzilabrou may be contacted at
thatzilabrou@tlsslaw.com
Firm Announces Remediation of Defective Drywall
October 16, 2013 —
CDJ STAFFThe residents of Villa Lago at Renaissance Commons will be relieved of their problems with defective Chinese drywall, according to an announcement from their legal counsel, Whitfield Bryson & Mason. Gary E. Mason, a founding member of the firm, announced to homeowners that remediation would begin on November 1. “The project will start with about 30 units on the top floor and will continue floor by floor for the next 12 months.” Residents will be moved out of their units for about three months while all drywall is removed and replaced.
Read the court decisionRead the full story...Reprinted courtesy of
Yes, Indeedy. Competitive Bidding Not Required for School District Lease-Leasebacks
October 01, 2014 —
Garret Murai – California Construction Law BlogRemember when you discovered that the tooth fairy wasn’t real?
It was kind of a bummer on one hand learning that it wasn’t a fairy that magically appeared to swap your tooth for cold hard cash, but rather your mom or, visual horrors, dad.
At the same time, it was, to your nearly-halfway-to-a-decade-on-this-planet-wizened-six-year-old mind, confirmation of what you had a sneaking suspicion was the case in any event.
And, so it is with the next case.
Lease-Leasebacks
In California, most public school construction projects are built using the traditional design-bid-build project delivery method in which a design professional designs the project, the project is put out for competitive bid and the selected contractor builds the project.
But not all school construction projects are built this way.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Kronick Moskovitz Tiedemann & GirardMr. Murai may be contacted at
gmurai@kmtg.com
Preparing For the Worst with Smart Books & Records
November 07, 2012 —
CDJ STAFFContractors are often too caught up in keeping the wheel of business churning to recognize deficiencies in how their records are managed. Working hard and working often tend to leave little time for consideration of your documents. But all too often I see the unthinkable, a contractor gets into trouble and has to call on its surety for help. At that point, you might finally get your first dose of reality about your records – and it can cost you.
Read the court decisionRead the full story...Reprinted courtesy of
Douglas Reiser of Reiser Legal LLC.Mr. Reiser can be contacted at
info@reiserlegal.com