Montreal Bridge Builders Sue Canada Over New Restrictions
April 13, 2017 —
Scott Van Voorhis - Engineering News-RecordThe consortium building the $3.2-billion Champlain Bridge in Montreal has sued Canada’s government for $93 million, claiming transportation officials gave it late notice of stricter load limits that could add to delay and make it liable for tens of millions of dollars in penalties, according to Canadian press reports and a stock analyst’s comments. A spokeswoman for the team’s lead firm, engineer-contractor SNC-Lavalin, confirms the March 28 filing in Quebec Superior Court but declined further comment.
Read the court decisionRead the full story...Reprinted courtesy of
Scott Van Voorhis, ENRENR may be contacted at
ENR.com@bnpmedia.com
Spearin Doctrine 100 Years Old and Still Thriving in the Design-Build Delivery World
January 09, 2019 —
John P. Ahlers - Ahlers Cressman & Sleight PLLCThe Supreme Court’s ruling in United States v. Spearin, [1] also referred to as the Spearin doctrine, is a landmark construction decision.[2] The Spearin doctrine provides that the Owner impliedly warrants the information, plans and specifications which an Owner provides to a General Contractor. If a Contractor is bound to build according to plans and specifications prepared by the Owner, the Contractor will not be responsible for the consequences of defects in the plans and specifications.
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers Cressman & Sleight PLLCMr. Ahlers may be contacted at
john.ahlers@acslawyers.com
New York Shuts Down Majority of Construction
March 30, 2020 —
Laura Bourgeois LoBue & Matthew D. Stockwell - Gravel2Gavel Construction & Real Estate Law BlogDue to pressure from construction workers, officials, and some construction workers having tested positive for COVID-19, the Empire State Development Corp. (acting on behalf of Governor Cuomo) has frozen all construction in New York today, with the exception of work on hospitals and health care facilities, transit facilities, roads and bridges, affordable housing and homeless shelters.
As a result, commercial construction and condominium projects are on hold, with the exception of work that must be completed to prevent unsafe conditions. Until now, construction has been considered “essential” in New York.
Reprinted courtesy of
Laura Bourgeois LoBue, Pillsbury and
Matthew D. Stockwell, Pillsbury
Ms. LoBue may be contacted at laura.lobue@pillsburylaw.com
Mr. Stockwell may be contacted at matthew.stockwell@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Denial of Motion to Dissolve Lis Pendens Does Not Automatically Create Basis for Certiorari Relief
November 16, 2023 —
David Adelstein - Florida Construction Legal UpdatesA recent appellate decision out of Florida’s Sixth District Court of Appeal holds that a trial court’s denial of motion to dissolve a lis pendens does NOT automatically give a basis for a petition for a writ of certiorari. Generalized allegations of “irreparable harm” to support the basis for the petition for writ of certiorari are insufficient. Rather, the party moving for the petition MUST clearly demonstrate the irreparable harm; otherwise, the petition for writ of certiorari will fail.
A lis pendens has legal significance. It is a recorded document that notifies the world that there is a pending lawsuit dealing with the real property at issue. This is important because who wants to buy a piece of property that is subject to litigation – that would be a risky transaction!
In CPPB, LLC v. Taurus Apopka City Center, LLC, 48 Fla.L.Weekly D1837a (Fla. 6th DCA 2023), a dispute arose as to a real estate transaction. The owner sold a parcel to a buyer. The owner also owned three adjacent parcels. As part of the transaction, the buyer agreed to perform certain improvements to all of the parcels including those adjacent parcels owned by the owner. The owner deposited funds in escrow for purposes of its share of the improvements. A payment dispute arose regarding the improvements and the buyer sued the seller. The seller filed a counterclaim to rescind the transaction along with a recorded lis pendens on the parcel purchased by the buyer. The buyer moved to dissolve the lis pendens which the trial court denied. This prompted the appeal – a petition for a write of certiorari based on the trial court’s denial of the motion to dissolve the lis pendens.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Texas Central Wins Authority to Take Land for High-Speed Rail System
October 03, 2022 —
Barclay Nicholson & Erica Gibbons - Sheppard Mullin Construction & Infrastructure Law BlogMove over luxury bus lines and quick flights. Central Texans should be on the lookout for bulldozers and train stops. On June 24, 2022, the Supreme Court of Texas held that Texas Central Railroad & Infrastructure, Inc. and related entities (collectively “Texas Central”) have eminent domain authority to acquire property for a proposed high-speed rail system between Dallas and Houston.
[1] Specifically, the Court held that the corporation qualifies as an “interurban electric railway company” under the Texas Transportation Code. This ruling grants Texas Central the broad condemnation authority to procure land for the project.
Texas Central has Statutory Authority to Take Land
The plaintiff in the matter, a farm owner with property south of Dallas along the proposed path of the bullet train, challenged the companies power to condemn land. The landowner’s declaratory judgment action challenged Texas Central’s eminent-domain authority. Under Texas law, condemnation power must be conferred by the legislature, either expressly or by necessary implication.
[2]
Here, Texas Central was created for the purpose of constructing, acquiring, maintaining, or operating lines of electric railway between Texas municipalities. The Court found that Texas Central is engaged in activities to further that purpose. Therefore, the Court concluded, that although legislators did not contemplate high-speed railways at the time of drafting the Transportation Code, Texas Central nonetheless qualified as “interurban electric railway companies” under the statute.
Reprinted courtesy of
Barclay Nicholson, Sheppard Mullin and
Erica Gibbons, Sheppard Mullin
Mr. Nicholson may be contacted at bnicholson@sheppardmullin.com
Ms. Gibbons may be contacted at egibbons@sheppardmullin.com
Read the court decisionRead the full story...Reprinted courtesy of
DC Circuit Upholds EPA’s Latest RCRA Recycling Rule
September 23, 2019 —
Anthony B. Cavender - Gravel2GavelOn July 2, 2019, the U.S. Court of Appeals for the District of Columbia Circuit decided the case of California Communities Against Toxics, et al. v. EPA. In this decision, the court rejected the latest petition to strike or vacate EPA’s 2018 revisions to the Resource Conservation and Recovery Act (RCRA) hazardous waste recycling rules. In 1985, EPA promulgated a new regulatory definition of “solid waste,” which is the linchpin of the agency’s very stringent hazardous waste management rules. (See the rules located at 40 CFR Sections 260-268.) Unless a material is a “solid waste” as defined by the rules, it cannot also be a hazardous waste.
The 1985 rules grappled with the challenges posed by recycling practices, and attempted to distinguish between legitimate recycling which is not subject to hazardous waste regulation, and other more suspect forms of recycling. The rules are complex and replete with nuance. In doing so, EPA was adhering to RCRA’s statutory mandate that it develop appropriate rules to govern the treatment, storage and disposal of hazardous waste, while also promoting “properly conducted recycling and reuse.” The DC Circuit reviewed the 1985 rules in the seminal case of American Mining Congress v EPA, 824 F.2d 1177 (1987), (AMC) and stressed that only those materials that were truly discarded could be regulated as solid waste; for instance, those materials that were destined for immediate recycling or recovery in an ongoing production process were not discarded and hence were not solid waste. Over the years, the court has struggled to clarify the basic holding of AMC in numerous cases while EPA has frequently revised and amended the RCRA rules, and in particular the definition of solid waste, in an attempt to balance the policies mandated by the statute.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Harmon Tower Demolition on Hold Due to Insurer
November 27, 2013 —
CDJ STAFFPermission for CityCenter to demolish Harmon Tower over claims of dangerous construction defects have been withdrawn by the judge in the case after the building’s insurer said it needed more time to investigate. After they were granted permission to demolish the building on August 23, CityCenter filed a claim of total loss with their insurer FM Global on August 27.
Now FM Global is saying that they need to further inspect the building. Meanwhile, a demolition contractor has already gained approval to start removing the exterior glass. And things stand, it looks as if that won’t be happening on the planned date of December 2.
CityCenter contends that FM Global has already done their inspections, describing FM Global’s prior actions as “the most extensive investigation of anyone,” according to Mark Ferrario, an attorney for CityCenter.
Also, the initial plan to implode the building has been rejected. Should demolition proceed, the building will be dismantled floor by floor.
Read the court decisionRead the full story...Reprinted courtesy of
Homebuilding Continues to Recover in San Antonio Area
December 04, 2013 —
CDJ STAFFThere was a slowing in the third quarter, but home builders expect that 2013 will see more than 9,000 home starts in the San Antonio area. And even though the third quarter was slow, it was still about 3% above the same quarter in 2012.
And the new homes are more expensive. Jack Inselmann, a senior vice president at MetroStudy noted that “in 2011, 40 percent of housing activity was under $175,000. And here we are two years later and 31 percent is under $175,000.” He worries that people looking for homes will go to the resale market, instead of buying a new home.
Read the court decisionRead the full story...Reprinted courtesy of