Practical Pointers for Change Orders on Commercial Construction Contracts
December 31, 2014 —
John E. Bowerbank - Newmeyer & DillionConstruction projects pose unique challenges, including keeping costs within budget, meeting project deadlines, and coordinating the work of numerous contractors and subcontractors in the wake of inevitable design revisions and changes to the plans. Anticipating potential project challenges and negotiating contract provisions before commencing work on a project is critical for all parties. Careful planning should reduce the number of contract disputes. This, in turn, can facilitate the completion of a project within budget and on schedule.
“Changes” Clauses in Construction Contracts
Most commercial construction contracts have a clause addressing changes to the contract. A “changes” clause typically requires the mutual agreement of the parties on the scope of any modifications to the contract, as well as the effect on the contract price and timeframe for the work to be performed. This results in what is generally referred to as a “change order.” Many projects have a large number of change orders, which can result in significant cost overruns and delays to the project if the contract contains a complicated change order process. Therefore, in order to minimize cost overruns and project delays, it is crucial to keep the change order process as simplified and streamlined as possible.
In the most basic terms, change orders memorialize modifications to the original contract, and typically alter the contract's price, scope of work, and/or completion dates. A typical change order is a written document prepared by the owner or its design professional, and signed by the owner, design professional, and affected contractors and subcontractors. An executed change order indicates the parties’ agreement as to what changes are taking place, including approval for additional costs and schedule impacts.
While the reasons for change orders and the parties initiating them may vary, all change orders have one feature in common. Effective change orders alter the original contract and become part of the contract. Therefore, from a legal standpoint, change orders must be approached with the same caution and forethought as the original contract.
Practice Pointers for Change Orders
In light of the foregoing, some practice pointers for change orders in commercial construction contracts are as follows:
- Carefully Negotiate and Draft Change Order Provisions in the Original Contract.
A carefully negotiated and drafted “changes” clause that accounts for “unexpected circumstances” or “hidden conditions” can protect the parties from downstream costly disputes.
- Immediately Address Changes by Following the Change Order Process, Including Obtaining Necessary Signatures.
Regardless if you are an owner, general contractor or subcontractor, you should address any proposed change order immediately. Even if a decision maker gives “verbal” approval to go ahead with changed work, the work should not proceed without following the change order process in the original contract. This includes making sure to obtain any necessary signatures for the change order, if at all possible.
- Analyze the Plans and Specifications to Determine Whether “Changes” are Within the Scope of the Original Contract, or Whether They are Extra Work.
Prior to entering an original contract, it is imperative that the parties review the plans and specifications for ambiguities regarding work included in the original contract, versus potential extra work that would require a change order. This is important because a careful review of the plans and specifications sometimes reveals that work believed to be a change order is, in fact, original work, or vice versa.
- Make Sure Requests and Approvals for Change Orders are Done by an Authorized Representative.
When a party requests or gives its approval to a change order, it is important to confirm the request or approval came from an authorized representative.
- Avoid Vague and Open-Ended Change Orders.
Indeed, the vaguer a change order, the more likely it can lead to a dispute. Vague and open-ended change orders, including change orders that provide for payment on a time and materials basis, can be difficult for an owner to budget and schedule. This can lead to disputes as to cost and/or time extensions.
- Oral Assurances for Payment Without a Signed Change Order May Not Be Recoverable.
When a party provides verbal assurances to another party for extra work without following the change order process, there is a much higher likelihood that disputes will occur. Although there is case law that may allow a contractor to recover for extra work in private contracts based on oral promises, the parties should avoid placing themselves in such a legal position. Notably, in public contracts, a contractor may not be able to recover for any extra work without a signed changed order, even with verbal assurances of payment from the owner.
About the Author:
John E. Bowerbank, Newmeyer & Dillion
Mr. Bowerbank is a partner in the Newport Beach office and practices in the areas of business, insurance, real estate, and construction litigation. You can reach John at john.bowerbank@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
Subcontractor Sued for Alleged Defective Work
June 11, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Louisiana Record reported that “[a] construction company is suing a subcontractor for alleged defective work on two construction projects” in New Orleans, Louisiana.
New Beginnings Enterprises and J. Fernando Arriola are “accused of providing defective labor and materials, failing to properly supervise construction on the properties, failing to obtain inspections required under building codes, failing to construct dwellings in accordance with plans and specifications and failing to perform agreements in a workmanlike manner,” according to the Louisiana Record.
Plaintiffs including Bartel Construction LLC seek $209,500 in damages “as additional sums for defective and incomplete work, lost profits, consequential damages and attorney’s fees.”
Read the court decisionRead the full story...Reprinted courtesy of
Broker's Motion for Summary Judgment on Negligence Claim Denied
July 30, 2018 —
Tred R. Eyerly - Insurance Law HawaiiAfter being sued for negligence for failing to secure proper coverage, the broker was unsuccessful in seeking dismissal by way of summary judgment. Liverman Metal Recycling, Inc. v. Arthur J. Gallagher & Co., 2018 U.S. Dist. LEXIS 87957 (E.D. N.C. May 25, 2018).
Plaintiffs were two companies, Empire and Liverman, that processed scrap metal. They were in the process of merging under a management plan by which Empire would acquire Liverman. As part of the plan, Empire's employees were moved on to Liverman's payroll processing system. Concurrently, Liverman renewed its workmen's compensation policy. Defendant Arthur J. Gallagher & Company, an insurance broker, handled the renewal with the insurer, Bridgefield Insurance Company.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
24th Annual West Coast Casualty Construction Defect Seminar A Success
June 05, 2017 —
Margaret Graham - CDJ STAFFThe 24th Annual West Coast Casualty Construction Defect seminar was once again, a huge success . On May 18-19, 2017 attendees from the legal, insurance, builder, contractor, subcontractor and numerous other industries came from across the United States and several foreign countries to the 24th Annual West Coast Casualty Construction Defect Seminar.
Caryn Siebert, Vice President and Chief Claims Officer of The Knight Insurance Group was awarded The Jerrold S. Oliver Award of Excellence. This award recognizes a person who has contributed to the betterment of the construction defect community. For more information on the Oliver Award of Excellence, please visit: http://www.westcoastcasualty.com/seminar/ollie-award-voting/
Bert L. Howe & Associates, Inc.’s golf challenge raised $2,225.00 for the National Coalition for Homeless Veterans and $1,900 for Final Salute.
The grand total for all charitable contributions raised this year at the seminar was $45,300.00.
For more information on the National Coalition for Homeless Vets, please visit: http://nchv.org/
To learn more about how Final Salute provides homeless women Veterans with safe and suitable housing, please visit: http://www.finalsaluteinc.org/
Read the court decisionRead the full story...Reprinted courtesy of
Houston Office Secures Favorable Verdict in Trespass and Nuisance Case Involving Subcontractor’s Accidental Installation of Storm Sewer Pipe on Plaintiff’s Property
June 12, 2023 —
Lewis Brisbois NewsroomHouston, Texas (May 26, 2023) - Houston Partners Joelle Nelson and Matt Begley secured a defense verdict on behalf of a gasoline services company following a four-day trial in the 284th District Court of Montgomery County, Texas.
In this case, Lewis Brisbois represented a client who hired a contractor to install a storm sewer line to mitigate flood risks to the client’s property. The contractor, however, deviated from the engineering plans and installed the storm sewer line on a neighboring property owned by the plaintiff. The storm sewer line then remained on the plaintiff’s property for five years while the parties attempted to negotiate potential solutions to the situation. The plaintiff refused multiple reasonable settlement attempts and ultimately sued the client and the contractor for continuous trespass and private nuisance. The contractor’s carrier denied coverage, making the client the target defendant. The matter proceeded to trial.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
Why Being Climate ‘Positive’ Is the Buzzy New Goal of Green Building
December 10, 2024 —
Olivia Rudgard - BloombergThe three buildings, dotted around Norway, couldn’t look more different: a soaring timber-and-concrete obelisk in Porsgrunn; a squat, two-story Montessori school on the edge of a forest in Drøbak; and a concrete and glass wedge-shaped office in Trondheim, just a few hundred miles from the edge of the
Arctic Circle. But they share a distinctive feature. Each has a roof perfectly tilted to squeeze out every possible drop of solar energy.
They are called
Powerhouses, and the initiative behind them claims they are all “energy positive”: The upfront energy “cost” of each building, and that of later demolition and disposal, is expected to be made back over the building’s lifetime. Powerhouses sometimes draw from the grid, especially in winter, but in the long Nordic summer days they give back many times over, overspilling excess solar energy into surrounding homes and businesses.
Read the court decisionRead the full story...Reprinted courtesy of
Olivia Rudgard, Bloomberg
Construction Materials Company CEO Sees Upturn in Building, Leading to Jobs
November 05, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Washington Post reported that Mesa Industries Inc. (a construction equipment and materials company), are "prepping for significant growth," which suggests that the construction industry is poised for growth. Terry Segerberg, CEO of Mesa Industries Inc., "is seeing enough nonresidential orders to suggest a sustained jobs recovery is underway in the industry — and in firms like hers that supply it."
A Bureau of Labor Statistics report predicted that 1.6 million construction jobs will be added through 2022, according to the Washington Post.
Read the court decisionRead the full story...Reprinted courtesy of
Select the Best Contract Model to Mitigate Risk and Achieve Energy Project Success
October 17, 2022 —
Gregory S. Seador - Construction ExecutivePower and energy projects are inherently complex and risky. Therefore, management and proper allocation of risk among project participants are essential to success.
Careful drafting of the engineering, procurement and construction (EPC) contract is a critical first step in managing risk. The standard contract format used for power and energy construction projects is the EPC contract. In its traditional form, the EPC contract makes the EPC contractor responsible for the entire project, including engineering (design of the power plant), procurement (purchase, installation and performance of all equipment) and construction (construction of the plant).
EPC contracts can, however, employ different contract models and pricing structures, each of which carries differing levels of risk for project participants. Selecting the appropriate contract model and pricing structure to meet the unique needs of the project is important.
Reprinted courtesy of
Gregory S. Seador, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Seader may be contacted at
seador@slslaw.com