Steps to Curb Construction Defect Actions for Homebuilders
June 15, 2017 —
Jason Daniel Feld – Kahana & Feld, LLPThe homebuilding and construction industries in California are at a record high in 2017 according to the National Homebuilders Association. While there is finally prosperity and growth for builders, developers and contractors after suffering from the recession of 2008, there is also a growth in construction defect claims. As with every industry and especially with construction, there are several risk prevention methods that can help curb this litigation.
Time Frames for Pursuing Construction Defect Claims
It is important to know and understand the time frames for which construction defect claims can be pursued by homeowners. There is a hard cut-off for construction defect litigation in California known as the Statute of Repose of 10 years. California Code of Civil Procedure (“CCP”) §337.15 provides a statute of repose that bars actions to recover damages for construction defects more than 10 years after substantial completion of the work of improvement. This provision is limited to property damage claims and does not extend to personal injuries (See, Geertz v. Ausonio, 4 Cal.App.4th 1363 (1992) and willful misconduct or fraudulent concealment claims. (See, Acosta v. Glenfed Development Corp., 128 Cal.App. 4th 1278 (2005).
There are also interim statutes of limitations for “patent” and “latent” defects discovered at the home also from the date of substantial completion. CCP §337.1(e) provides for a four year window to bring suit for deficiencies that are apparent by reasonable inspection (patent deficiencies). CCP §337.15(b) provides for deficiencies that are not apparent by reasonable inspection or hidden defects that require invasive testing to become apparent (latent deficiencies). A latent defect can become patent after it “manifests itself” (i.e. becomes observant – for example a roof leak) for which the four year window from the date of discovery would become the applicable statute of limitations.
The discovery rule effectively acts to toll the statute of limitation period on construction defect claims until they become reasonably apparent. (See, Regents of the University of CA v.Harford Accident & Indemnity, Co., 21 Cal.3d 624, 630 (1978). This is similar to a breach of contract claim, also a four year statute of limitation. Finally, the California Right to Repair Statute (SB800) – Civil Code §§895, et seq. specifically Civil Code §896 sets forth the “Functionality Standards” or a list of actionable defect items, including items affecting the component’s “useful life” and a catch-all provision for all items not expressed listed as defects in the statute. (Civil Code §897). The majority of the defects alleged have a 10 year statute of limitations. However, there are shortened statute of limitations for the following items:
Functionality Standards | Statute of Limitations |
Noise Transmission |
1 year from original occupancy of adjacent unit |
Irrigation |
1 year from close of escrow |
Landscaping Systems & Wood Posts (untreated) |
2 years from close of escrow |
Electrical systems, pluming/sewer systems, steel fences (untreated), flatwork cracks |
4 years from close of escrow |
Paint/Stains |
5 years from close of escrow |
All other functionality standards (Civil Code §941(a)) |
10 years after substantial completion(date of recordation of valid NOC) |
Preventative Measures to Curb Construction Defect Litigation
Once the builder knows the time frames for construction defect claims, the following are some preventive measures to limit construction defect claims. As a reminder, homeowners are less likely to bring construction defect action if they feel that the builders are taking care of them.
1. Communicate With Homeowners Prior to Claims
It is imperative to communicate with the homeowners throughout the ten years statute of repose period. For example, most builders provide a limited warranty to the homeowners at the time of purchase. Homeowners are generally confused as to the length of the warranty and what the warranty covers. A practical tip to help curb construction defect claims is for the builder to send postcards or letters to the homeowners at the six month, one year and nine-year marks to advise the homeowner of: (1) the existence of the warranty and what is covered at each time frame; (2) the maintenance obligations of the homeowner at the various time frames; and (3) the fact that the home is approaching the ten-year mark. Most builders would rather deal directly with the homeowners through customer service than defend a construction defect litigation action where the costs to defend the claim will vastly exceed the cost to address the individual homeowner issues. The more the builder communicates with the homeowner in advance, the less likely it is that the homeowner engages in litigation against the builder.
2. Timely Response to Homeowner Claims
During the purchase process, provide the homeowners instructions on how to send in a customer service or warranty requests. Provide multiple methods for notification to the builder by the homeowner when issues arise in their home (fax, email, website forms, etc.). The builder should provide a timely response – within 48 hours of the notice if possible. The homeowner wants to receive some notification from the builder that they received their request and, at the very least, will investigate the claim. Even if it is determined to be a maintenance item or homeowner caused damage, the homeowner should receive: (1) an acknowledgement of the claim; (2) an investigation report of the issue; and (3) an action plan or conclusion statement – this can be a declination of repairs with an explanation as to the cause not being the result of original construction. Sometimes even sending a customer service representative to the home to listen to the homeowner claims and explaining that there are not repairs required is sufficient to satisfy the homeowner. The goal is to make sure the homeowner’s claims are acknowledged and that the builder is standing behind its product. In my experience, the fact that the builder failed to respond in a timely fashion to the homeowner is a significant motivating factor as to why the homeowner elected to enter formal litigation against the builder.
3. Be Proactive When Litigation Ensues Despite the fact that the homeowner has engaged an attorney and joined a construction defect action, the builder is not precluded from continuing to communicate with its homeowners. Several builders send letters to the non-plaintiff homeowners reminding them to contact the builder should they have issues at their homes rather than join the ongoing construction defect action. Under the law, clients can always talk to clients even if they are represented by counsel. While the attorneys for the builders cannot speak to the represented construction defect homeowners, the builder can communicate directly with its homeowners offering to honor its warranty and customer service procedures in lieu of the homeowner proceeding with the litigation. Both of these builder attempts to communicate with homeowners post-litigation have a dual effect – some homeowners elect to contact the builder to effectupate repairs and drop the litigation; while others elect to continue with the litigation. So proceed cautiously in this regard.
It is noted, there are many motivating factors for homeowners to bring a lawsuit against homebuilders that have nothing to do with the construction practices or customer service and are merely economically driven. However, these small steps in addition to providing solid construction practices should help curb construction defect litigation by homeowners.
Jason Daniel Feld is a founding partner of Kahana & Feld LLP, an AV Preeminent boutique litigation firm in Orange County specializing in construction defect, insurance defense, employment and general business litigation matters. The firm was founded with the goal of providing high-quality legal services at fair and reasonable rates. The firm believes that what defines attorneys is not their billing rates, but their record of success, which speaks for itself. For more information, please visit: www.kahanafeld.com.
Read the court decisionRead the full story...Reprinted courtesy of
Contract, Breach of Contract, and Material Breach of Contract
July 05, 2023 —
Wendy Rosenstein - Ahlers Cressman & Sleight PLLCAt its most basic level, a contract is an agreement to make a trade. Parties to a contract agree to perform a specific action on the condition that the other side also performs a specific action. For instance, you and a Girl Scout could create a contract in which the Girl Scout agrees to deliver one box of cookies and you agree to pay her $6.00. In this case, both you and the Girl Scout have obligations under the contract.
If the Girl Scout failed to send you the cookies, what do you do? You send her a note, in writing, telling her that you expect the cookies (or assurance that you will get the cookies) within a certain amount of time—this is notice and the opportunity to cure. Most contracts have a “notice and opportunity to cure” provision, which essentially says that one side must give the other side an opportunity to fix breaches before canceling the contract. Once a party receives a notice to cure, they must either rectify the problem or offer adequate assurances that they will fix the problem. Generally, the party has only a short period of time to address the breach.
Read the court decisionRead the full story...Reprinted courtesy of
Wendy Rosenstein, Ahlers Cressman & Sleight PLLC
Stormy Skies Ahead? Important News Regarding a Hard Construction Insurance Market
August 13, 2019 —
Jason M. Adams - Gibbs GidenWord out of the construction insurance brokerage community is that the construction insurance industry has entered a hard market, seemingly overnight. Property (i.e. builder’s risk), liability and wrap-up markets are all reacting unfavorably, resulting in higher premiums and decreased availability of coverage options.
The prospect of a hard market has been looming for some time given massive weather driven property losses and historically low rates (among other factors). It appears the time is upon us.
Key takeaways for construction professionals are:
- Expect insurance premiums to go up, potentially significantly, at renewal time and/or when seeking a new project specific program (e.g., an OCIP, CCIP, etc.).
- Expect that the available coverage will get worse. Carriers may be unable to offer once standard coverage enhancements and/or may add new exclusions.
- If quotes have been offered consider locking them in now, before the underwriters are forced to increase the rates/restrict coverage, or pull the quotes entirely.
- With respect to wrap-ups and other project specific programs, consider requesting extensions now if the project is expected to go beyond the current policy term.
- As always, the risk management team (lawyer, broker, risk manager) should work together to carefully review contracts and coverage. This will become even more important if the carriers start to introduce new exclusions as a result of the hard market.
Hard markets come and go. The tough times are when true construction insurance professionals separate themselves from the pack and become the key to weathering the storm.
Jason M. Adams, Esq. is Senior Counsel at Gibbs Giden representing construction professionals (owners/developers, contractors, architects, etc.) in the areas of Construction Law, Insurance Law and Risk Management, Common Interest Community Law (HOA) and Business/Civil Litigation. Adams is also a licensed property and casualty insurance broker and certified Construction Risk & Insurance Specialist (CRIS). Gibbs Giden is nationally and locally recognized by U. S. News and Best Lawyers as among the “Best Law Firms” in both Construction Law and Construction Litigation. Chambers USA Directory of Leading Lawyers has consistently recognized Gibbs Giden as among California’s elite construction law firms. Mr. Adams can be reached at jadams@gibbsgiden.com. Read the court decisionRead the full story...Reprinted courtesy of
Evaluating Construction Trends From 2023 and Forecasting For 2024
February 12, 2024 —
Jason Feld & Dominic Donato - Kahana FeldAs we begin 2024, it is informative to evaluate what transpired in 2023 in the construction industry, and especially the use of construction technology. 2023 ushered in a variety of newly implemented construction technologies including 3D printed entire houses, improved wearables that detect all aspects of the construction worker from location to temperature to heart rate, increased use of modular construction for entire apartments, hotels, and condominium projects, and eco-friendly and conservation minded technologies to minimize carbon footprint, water preservation and sustainable construction methods, to name a few.
2023 also identified some significant issues in the construction industry. First and foremost, the labor shortages and hiring of skilled and qualified workers continued to be an issue resulting in increased delays, construction accidents, and project mismanagement. The skyrocketing interest rates, decline in commercial/office projects, supply chain issues, material price fluctuation and increase changes in scope of projects all negatively impacted the construction industry in 2023. There is also the demand for renewable and infrastructure projects put strain on construction resources as the projects became “mega” with larger and more complex construction leading to multi-party, high dollar, and more complex claims. Finally, there is a growing trend of construction claims and litigation being financed by third party litigation funding sources for personal/bodily injury claims and construction defect claims.
Reprinted courtesy of
Jason Feld, Kahana Feld and
Dominic Donato, Kahana Feld
Mr. Feld may be contacted at jfeld@kahanafeld.com
Mr. Donato may be contacted at ddonato@kahanafeld.com
Read the court decisionRead the full story...Reprinted courtesy of
In UK, 16th Century Abbey Modernizes Heating System by Going Back to Roman Times
March 18, 2019 —
Peter Reina - Engineering News-RecordAncient Romans in western England bathed in naturally warm spring water of the spa town of Aquae Sulis, now named Bath. Nearly 2,000 years later, the city’s 16th century abbey is now preparing to draw warmth from the still functioning Great Roman Drain to replace the former monastery’s dilapidated Victorian-era heating system.
Read the court decisionRead the full story...Reprinted courtesy of
Peter Reina, ENRMr. Reina may be contacted at
reina@btinternet.com
Relief Bill's Highway Funds Could Help Construction Projects
January 04, 2021 —
Tom Ichniowski - Engineering News-RecordAmong the many provisions in the coronavirus relief bill, one key item is $10 billion to help state highway agencies make up for losses in state fuel taxes and other revenue due to the pandemic-caused falloff in traffic this year. Construction is one of a list of several eligible uses for the money—one of only a few construction funding provisions in the relief measure.
Reprinted courtesy of
Tom Ichniowski, Engineering News-Record
Mr. Ichniowski may be contacted at ichniowskit@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Appraisal Panel Can Determine Causation of Loss under Ohio Law
February 19, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court granted the insured's motion to compel an appraisal that would include a determination of causation of the loss. Eagle Highland Owners Association v. State Farm Fire and Casualty Co., 2023 U.S. Dist. LEXIS 220937 (S.D. Ohio Dec. 12, 2023).
Plaintiff argued its property suffered wind and hail damage from a storm on June 18, 2021. A claim was submitted to State Farm. State Farm's investigation determined the loss to be $0.00. Plaintiff's investigator determined the loss to be $586,647.08 in repair costs.
State Farm opposed appraisal because, in its view, the damage arose from a loss in 2019, not from the June 18, 2021 storm. Plaintiff submitted a loss claim in 2019 for damage that State Farm alleged was exactly the same as the damage alleged in the loss claim for the June 18, 2021 storm. Therefore, State Farm did not view the matter as a dispute over an amount of loss, but rather over whether a loss even occurred on June 18, 2021.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Employees Versus Independent Contractors
February 23, 2017 —
Chadd Reynolds – Autry, Hanrahan, Hall & Cook, LLPAre the workers you employ on the job site considered employees or independent contractors? This is an important distinction that contractors and subcontractors must understand for many purposes, including federal taxes. The classification of your workers can affect their federal income, social security, and Medicare taxes, and the type of benefits they can receive.
When determining whether workers should be classified as employees or independent contractors, courts generally look at three key factors: behavioral control, financial control, and the relationship of the parties.
Behavior Control
Behavior control concerns the business’s right to direct or control how the worker does its work. A worker is likely to be considered an employee when the business maintains behavior control. Such control can be exercised by giving instructions. This would include instructions on how, when, or where to do the work, what tools or equipment to use, who to hire to help with the work, or where to purchase the supplies to be used. Behavioral control can also occur through training. If the business provides training to tell the worker to do the work in a certain manner then the worker is more likely to be an employee.
Read the court decisionRead the full story...Reprinted courtesy of
Chadd Reynolds, Autry, Hanrahan, Hall & Cook, LLPMr. Reynolds may be contacted at
reynolds@ahclaw.com