Samantha M. Martino – Saxe Doernberger & Vita, P.C.On October 4, the Second Circuit held that Harleysville Insurance Company had no duty to defend or indemnify a project owner or general contractor as additional insureds under a sub-subcontractor’s commercial general liability (CGL) policy due to lack of direct contractual privity. 1
The underlying claim arose when an employee of The Kimmell Company, Inc. (Kimmell) was injured while repairing an HVAC system at a building owned by the University of Rochester Medical Center (UR). The injured employee sought damages for his injuries and fi led suit against (1) UR; (2) LeChase Construction Corp. (LeChase), the general contractor for the project; and (3) J.T. Mauro Co. Inc. (Mauro), a subcontractor hired by LeChase.
Mauro hired Kimmell as a sub-subcontractor to perform HVAC services at the project. The Mauro-Kimmel contract required Kimmel to add Mauro, UR, and LeChase as additional insureds under Kimmell’s CGL policy.
Read the court decisionRead the full story...Reprinted courtesy of
Samantha M. Martino, Saxe Doernberger & Vita, P.C.Ms. Martino may be contacted at
smm@sdvlaw.com
Insured Cannot Sue to Challenge Binding Appraisal Decision
December 16, 2023 —
Tred R. Eyerly - Insurance Law HawaiiThe court dismissed the insured condominium association's challenge to an appraisal award. The Courtyards at Prairie Fields Condominium Association v. West Band Mut. Ins. Co., 2023 U.S. Dist. LEXIS 169458 (N. D. Ill. Sept. 22, 2023).
In July 2020, the insured filed a claim with West Bend for damage to the property's roof and other building components as a result of wind and hail. West Bend inspected and estimated the replacement cost for the damage was $60,989.54. This amount was paid to the insured minus the $10,000 deductible. The insured believed the damage was so severe that the roofs need to be replaced, which the insured estimated would cost $1,389,600. The insured demanded an appraisal.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Claim for Vandalism Loss Survives Motion to Dismiss
October 02, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe court ruled that the insured's claim for vandalism of his house by a renter and for bad faith survived the insurer's motion to dismiss. Wehrenberg v. Metro. Prop. & Cas. Ins. Co., 2015 U.S. Dist. LEXIS 103758 (W.D. Pa. Aug. 7, 2015).
The insured's home was insured by a homeowner's policy issued by Metropolitan. The insured rented his home to Alphonso Hyman in October 2011. In lieu of rent, Hyman was to pay the mortgage company the equivalent of his rent each month.
In early 2012, Hyman stopped making the monthly rent/mortgage payments. The insured went to the home and found the locks had been changed. Looking in the windows, he saw the interior had been gutted. When the insured reached Hyman, Hyman said he was a contractor and was fixing the structural problems and would put the house back together. He also promised to make up late payments to the mortgage company. The insured did not report what he found to Metropolitan.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
The Peak of Hurricane Season Is Here: How to Manage Risks Before They Manage You
September 21, 2020 —
Vincent E. Morgan - Construction ExecutiveThe Atlantic hurricane season runs from June 1 to Nov. 30, but it peaks sharply during August, September and October. The latest forecasts predict this will be one of the most active seasons in history, in terms of frequency and severity, though it is always important to remember that even a single hurricane or tropical storm making landfall can still be a devastating event.
Hurricanes pose unique risks to the construction industry ranging from project and labor force disruptions to concerns about the availability and price of construction materials. This is even more true this year, which requires merging hurricane preparedness and response plans with the realities of COVID-19. Because hurricanes cannot be avoided, preparing for them is the only way to manage these risks. Ensuring the personal safety and wellbeing of affected individuals is the first priority. After that, here are some key issues, and suggestions for handling them, that may help guide construction companies through the storm.
SITE PROTECTION
Construction contracts often place responsibility for site protection on contractors. Where those duties exist, failing to properly carry them out can lead to enormous losses that then turn into liability claims. This could be anything from removing materials that can become projectiles, covering exposed ventilation shafts, and sealing electrical conduits to ensuring that key equipment such as generators and pumps can remain functional in a storm. One way to approach it is to imagine sustained 100-mph winds and relentless water, and then make sure preparedness efforts are likely to survive that kind of test. This is not the time for guessing. It is far better to go through a rigorous analytical process now than in a courtroom years later.
Reprinted courtesy of
Vincent E. Morgan, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
California Supreme Court Upholds Insurance Commissioner’s Authority to Regulate Replacement Cost Estimates
January 26, 2017 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPn Assn. of Cal. Insurance Companies v. Jones ( No. S226529, filed 1/23/17), the California Supreme Court reversed trial and appellate court decisions to hold that California’s Insurance Commissioner Dave Jones had the authority to promulgate California Code of Regulations, title 10, section 2695.183, which sets out specific requirements for estimating replacement cost as part of any application for or renewal of homeowners insurance.
The regulation was promulgated in 2010 in response to complaints from homeowners who lost their homes in the Southern California wildfires of 2003, 2007, and 2008, and who discovered that they did not have enough insurance to cover the full cost of repairing or rebuilding their homes because the insurers’ estimates of replacement value were too low when they purchased the insurance.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Wyncrest Commons: Commonly Used Progress Payments in Construction Contracts Do Not Render Them Installment Contracts
December 11, 2023 —
Benjamin J. Hochberg - Peckar & Abramson, P.C.In BIL-JIM Construction Company, Inc. v. Wyncrest Commons, LP, 2023 WL 7276637 (Unpublished, decided November 3, 2023), the New Jersey Appellate Division was asked to consider two issues regarding the interpretation and application of a construction contract that utilized the standard form American Institute of Architects owner/contractor agreement (AIA Document A101-2007) (the “AIA Contract”). Specifically, it was asked to consider: 1) whether a modified AIA Contract was an “installment contract,” whereby each progress payment was subject to its own statute of limitations; and 2) whether and when work had been approved in the context of New Jersey’s Municipal Land Use Law. While the decision is presently unpublished, it provides guidance as to how form contracts utilizing the same or similar terms will be treated by New Jersey’s courts and is a reminder that the potential for future claims must be considered during contract negotiations.
Discussion
The primary issue in Wyncrest was whether an AIA Contract was an “installment contract,” and the remaining issues turned on the resolution of this question. Wyncrest, the owner for the project at issue, did not dispute that its contractor, BIL-JIM Construction Company, Inc., had not been fully paid for work that it had performed in connection with a construction project located in Ocean County, New Jersey. Instead, Wyncrest argued that because its AIA Contract with BIL-JIM required that invoices be presented and paid monthly, it constituted an “installment contract.” As such, older payments would be treated as individual transactions and were time barred by the applicable statute of limitations. The trial court agreed with Wyncrest’s characterization of the AIA Contract as an “installment contract,” and found that BIL-JIM’s invoices were each subject to their own statute of limitations. However, the trial court disagreed with Wyncrest’s argument that BIL-JIM’s claim for retainage—which was submitted at the end of its work at the project—was time barred.
Read the court decisionRead the full story...Reprinted courtesy of
Benjamin J. Hochberg, Peckar & Abramson, P.C.Mr. Hochberg may be contacted at
bhochberg@pecklaw.com
Eighth Circuit Affirms Finding of Bad Faith, Award of Costs and Prejudgment Interest
October 25, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe Eighth Circuit affirmed the district court's finding of bad faith and award to the insured of taxable costs and prejudgment interest. Selective Ins. Co. v. Sela, 2021 U.S. App. LEXIS 26062 (8th Cir. Aug. 30, 2021).
The insured suffered two hail storms that damaged his home. In 2010, the first storm caused over half a million dollars in loss. Before submitting a claim to his original insurer or beginning any repairs, the insured secured a new policy with Selective. The policy did not exclude pre-existing damage, it did preclude coverage if the insured "willfully and with intent to defraud, concealed or misrepresented any material fact or circumstance relating to the insurance."
Before issuing the policy, Selective appraised the property and assigned a $1.6 million value to the home. The insured then filed a claim with his original insurer and received $510,787.23 for actual cash value of his loss. Neither the terms of this settlement nor this new policy with Selective required the insured to repair all of the 2010 damage.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Jason Poore Receives 2018 Joseph H. Foster Young Lawyer Award
July 21, 2018 —
Jason Poore - White and Williams LLPJason Poore, an associate in the General Litigation Group, recently received the 2018 Joseph H. Foster Young Lawyer Award during the Philadelphia Association of Defense Counsel’s annual meeting. The Joseph H. Foster Young Lawyer Award honors “a young lawyer who best exemplifies the qualities of professionalism and dedication as defense counsel in the practice of law and in the promotion of the highest ideals of justice in the community."
Jason continues to make significant contributions to the local bar and community. In addition to serving on the Executive Committee of the Philadelphia Bar Association Young Lawyers Division, he is the creator and Chair of the PBA's Youth Courts Committee.
Read the court decisionRead the full story...Reprinted courtesy of
Jason Poore, White and Williams LLPMr. Poore may be contacted at
poorej@whiteandwilliams.com