Is the Removal and Replacement of Nonconforming Work Economically Wasteful?
September 19, 2022 —
David Adelstein - Florida Construction Legal UpdatesThere are times a contractor installs the wrong material or system contrary to the plans and specifications. A nonconformity. The owner wants the already-installed material or system to be replaced in conformity with the plans and specifications. However, what was installed is functionally equivalent to what the plans and specifications required and would be cost prohibitive, i.e., economically wasteful. If the contractor elects to remove and replace the nonconforming work, it may seek a change order because it is economically wasteful. Or, the contractor may refuse (typically, not the best approach) in furtherance of taking on the fight based on the economic wastefulness associated with the removal and replacement. A recent case, David Boland, Inc. v. U.S., 2022 WL 3440349 (Fed.Cl. 2022), talks about this exaction situation and the economic waste doctrine. This is an important doctrine for contractors to understand when faced with a similar predicament.
Here, a contractor was hired by the government to construct a wastewater collection system that was to be owned and operated by a private company. The contractor’s work was going to be incorporated into a larger sewer system that the private company already operated. The contractor was required to install sewer manholes reinforced with steel in accordance with an ASTM standard. The manholes could be rejected if they did not conform to the ASTM standard. Compliance with this ASTM standard was also required by the private company’s construction protocol for the infrastructure, which was incorporated into the contractor’s contract with the government. The contractor was required to strictly comply with the contract.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Are Construction Defect Claims Covered Under CGL Policies?
January 27, 2014 —
Beverley BevenFlorez-CDJ STAFFCourts have ruled differently as to whether a construction defect is or is not an “occurrence,” according to the publication Business Insurance. Four states—Colorado, Arkansas, Hawaii and South Carolina—have sought to remove ambiguity by passing statutes that define construction defect claims as occurrences.
Colorado, the first state to create such a statue, passed H. B. 10-1394 in May 2010. The state legislature passed the statute “because of the complex and lengthy endorsements and exclusions facing construction professionals, according to the bill” reported Business Insurance.
The article stated that “incongruous court decisions over whether construction defect claims are covered under CGL policies continue to drive uncertainty in coverage and increase litigation costs.”
Read the court decisionRead the full story...Reprinted courtesy of
New Hampshire Asbestos Abatement Firm Pleads Guilty in Federal Fraud Case
February 02, 2017 —
Justin Rice - Engineering News-RecordFor the second time in three months, a New England-based asbestos removal company pleaded guilty in federal court to wage and benefit violations.
Read the court decisionRead the full story...Reprinted courtesy of
Justin Rice, ENRMr. Rice may be contacted at
ricej@enr.com
Allegations That COVID-19 Was Physically Present and Altered Property are Sufficient to Sustain COVID-19 Business Interruption Suit
May 24, 2021 —
Michael S. Levine & Joseph T. Niczky - Hunton Insurance Recovery BlogOn Wednesday, a federal judge in Texas denied Factory Mutual’s Rule 12(c) motion for judgment on the pleadings, finding that the plaintiffs adequately alleged that the presence of COVID-19 on their property caused covered physical loss or damage in the case of Cinemark Holdings, Inc. v. Factory Mutual Insurance Co., No. 4:21-CV-00011 (E.D. Tex. May 5, 2021). This is the third COVID-19-related business interruption decision from Judge Amos Mazzant since March, but the first in favor of a policyholder. Taken together, the three decisions have two key takeaways and provide a roadmap for policyholders in all jurisdictions.
First, the Cinemark decision recognizes that the alleged presence of COVID-19 viral particles that physically altered the policyholder’s property is sufficient under federal pleading standards and controlling state law. In its motion, FM relied on Judge Mazzant’s recent decision in Selery Fulfillment, Inc. v. Colony Insurance Co., No. 4:20-CV-853, 2021 WL 963742 (E.D. Tex. Mar. 15, 2021), which dismissed a lawsuit alleging that the policyholder’s losses were caused by government orders that closed its business, rather than from the actual presence of the virus on its property. The Court held that government orders alone do not constitute physical loss or damage, and declined to rule on whether the physical presence of the virus does. Judge Mazzant reached the same conclusion weeks later in Aggie Investments, L.L.C. v. Continental Casualty Co., No. 4:21-CV-0013, 2021 WL 1550479 (E.D. Tex. Apr. 20, 2021).
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Joseph T. Niczky, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Niczky may be contacted at jniczky@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Distinguishing Hawaii Law, New Jersey Finds Anti-Assignment Clause Ineffective
March 22, 2017 —
Tred R. Eyerly – Insurance Law HawaiiThe New Jersey Supreme Court found that an anti-assignment provision could not be applied to bar a post-loss claim assignment. Givaudan Fragrances Corp. v. Aetna Cas. & Sur. Co., 2017 N.J. LEXIS 121 (N.J. Feb. 1, 2017). In reaching its decision, the court distinguished a decision from the Hawaii Supreme Court enforcing consent-to-assignment clauses and failing to recognize any post-loss exception to such clauses. See Del Monte Fresh Produce (Hawaii), Inc. v. Fireman's Fund Ins. Co., 183 P.3d 734 (Haw. 2007).
Plaintiff Givaudan Fragrances Corporation (Fragrances) was sued for environmental contamination at a manufacturing site. A related corporate entity had operated the facility from the 1960s to 1990. Fragrances sought coverage under policies issued to its predecessor. The predecessor attempted to assign to Fragrances post-loss rights under the policies. The insurers resisted, claiming the predecessor was the named insured, not Fragrances, and that the insurers did not consent to an assignment of the predecessor's policies.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Sureties do not Issue Bonds Risk-Free to the Bond-Principal
August 30, 2017 —
David Adelstein - Florida Construction Legal UpdatesIf your construction company is bonded, then you have signed a General Agreement of Indemnity with your surety / bonding company. Stated another way, if a surety issued an obligee on behalf of your construction company, as the bond-principal, a payment or performance bond, then you have signed a General Agreement of Indemnity with your surety.
The General Agreement of Indemnity is NOT to be taken lightly. Without the General Agreement of Indemnity, the surety is NOT issuing the bonds you need to work on a certain project. A bond is not insurance and sureties do not issue the bonds under a risk-free premise. Oh no! If a surety has to pay-out claims under a bond, the surety will be looking to recoup that loss from the indemnitors that executed the General Agreement of Indemnity.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
Dadelstein@gmail.com
Arbitration: For Whom the Statute of Limitations Does Not Toll in Pennsylvania
June 03, 2019 —
Gus Sara - The Subrogation StrategistIn Morse v. Fisher Asset Management, LLC, 2019 Pa. Super. 78, the Superior Court of Pennsylvania considered whether the plaintiff’s action was stayed when the trial court dismissed the plaintiff’s complaint after sustaining the defendants’ preliminary objections seeking enforcement of an arbitration clause in the contract at issue. The Superior Court—distinguishing between a defendant who files a motion to compel arbitration and a defendant who files preliminary objections based on an arbitration clause—held that, in the latter scenario, if the defendant’s preliminary objections are sustained, the statute of limitations is not tolled. This case establishes that, in Pennsylvania, plaintiffs seeking to defeat a challenge to a lawsuit based on a purported agreement to arbitrate need to pay close attention to the type of motion the defendant files to defeat the plaintiff’s lawsuit.
In Morse, the plaintiff entered into a contract with Fisher Asset Management (Fisher) in 2008 for investment-advisor services. The contract included a provision stating that any dispute, claim or controversy arising out of the agreement between the parties shall be determined by arbitration. In June 2009, the plaintiff filed a complaint against Fisher and two of its employees in the Court of Common Pleas of Allegheny County, alleging breach of fiduciary duty, breach of contract, negligence, and other claims. The defendants filed preliminary objections to the complaint seeking dismissal on grounds that the contract between the plaintiff and Fisher required that the dispute be determined by arbitration. The court sustained the preliminary objections and dismissed the complaint. The plaintiff did not appeal the court’s ruling.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
Jury Trials: A COVID Update
July 18, 2022 —
Joshua Lane - Ahlers Cressman & Sleight PLLCJURY TRIALS. Budd v. Kaiser Gypsum Co., Inc., — Wn. App. 2d –, 505 P.3d 120 (Wash. Ct. App. 2022). (1) Courts must ensure that juries are randomly selected to provide a fair and impartial jury. (2) While the Sixth and Fourteenth Amendments prohibit the systematic exclusion of distinctive groups from jury pools, Washington Courts’ COVID-19 policy to excuse people who were ages 60 and older and did not wish to report for duty was not a “systematic” exclusion.
Raymond Budd developed mesothelioma after working with a drywall product called “joint compound” from 1962 to 1972. He sued Kaiser Gypsum Company, Inc. and others for damages, contending that the company’s joint compound caused his illness. A jury returned a verdict in Budd’s favor and awarded him nearly $13.5 million. Kaiser appeals, claiming (1) insufficient randomness in the jury-selection process, (2) erroneous transcription of expert testimony, (3) lack of proximate causation, (4) lack of medical causation, (5) an improper jury instruction on defective design, (6) improper exclusion of sexual battery and marital discord evidence, (7) improper admission of post-exposure evidence, (8) improper exclusion of regulatory provisions, and (9) a failure to link its product to Budd’s disease. The Court of Appeals, Division 1, affirmed the verdict in favor of Budd.
Read the court decisionRead the full story...Reprinted courtesy of
Joshua Lane, Ahlers Cressman & Sleight PLLCMr. Lane may be contacted at
joshua.lane@acslawyers.com