Federal Court Denies Summary Judgment in Leaky Condo Conversion
August 04, 2011 —
CDJ STAFFIn the US District Court for Illinois, Judge William Hibber has rejected the request for summary judgment sought by the developers of a condominium building in the case of Nautilus Ins. Co. v. 1735 W. Diversey, LLC (the insureds). The insureds renovated a building at 1735 W. Diversey, Chicago, converting it into condominiums. After the project was completed and all units sold, and a condominium association form, one of the owners found that unit suffered leaks during rainstorms. The condo board hired a firm, CRI, to investigate the cause of the leakage. CRI found “water infiltration through the exterior brick masonry walls, build-up of efflorescence on the interior surfaces of the masonry, and periodic spalling of portions of the brick masonry.”
The redevelopment firm had purchased coverage from Nautilus. “Shortly after the Board filed its first complaint, the Insureds tendered the mater to Nautilus and requested that it indemnify and defend them from the Board's underlying claims. Nautilus, however, rejected the Insureds’ tender and denied coverage under both insurance policies.” Nautilus stated that the water leakage did not constitute an occurrence under the policies. The court cited these policies in which an occurrence is defined as “an accident, including continuous or repeated exposure to substantially the same general harmful conditions.” The Illinois courts have determined that construction defects are not accidents.
The court concluded that the insured did not bring forth claims within the coverage of the policies and denied the motion for summary judgment.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Negligence Against a Construction Manager Agent
March 22, 2018 —
David Adelstein – Florida Construction Legal UpdatesCan a construction manager-agent / owner’s representative hired directly by the owner be liable to the general contractor in negligence? An argument likely posited by many general contractors on projects gone awry where there is a separate construction manager. Well, here is an interesting case out of Louisiana that supports a negligence claim against a construction manager-agent.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
New Strategy for Deterring Intracorporate Litigation?: Delaware Supreme Court Supports Fee-Shifting Bylaws
May 13, 2014 —
Marc Casarino and Lori Smith – White and Williams LLPA fee-shifting bylaw of a Delaware non-stock corporation is not facially invalid according to the Delaware Supreme Court’s May 8, 2014 opinion in ATP Tour, Inc. v. Deutscher Tennis Bund.
In this case, ATP Tour, Inc., a non-stock membership corporation (“ATP”) governed by a seven member board, had adopted a bylaw provision which provided that current and former members of ATP would be responsible for the litigation costs arising out of any litigation initiated by any such member against ATP or any of the other members in which the initiating party did not obtain a judgment on the merits that substantially achieved in substance and amount the full remedy sought. The bylaw provision had been adopted, in accordance with ATP’s charter, by the Board unilaterally without any consent from the members. The members had agreed at the time they joined ATP to be bound by the bylaws, as amended from time to time. Two members of ATP initiated a suit against ATP relating to certain actions taken with respect the ATP’s tournament schedule and format alleging both federal antitrust claims and Delaware fiduciary duty claims but did not prevail on any of their claims. ATP then moved to recover its legal fees relating to such actions.
Reprinted courtesy of
Marc Casarino, White and Williams LLP and
Lori Smith, White and Williams LLP
Mr. Casarino may be contacted at casarinom@whiteandwilliams.com; Ms. Smith may be contacted at smithl@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Project Completion Determines Mechanics Lien Recording Deadline
April 08, 2024 —
William L. Porter - Porter Law GroupThe California mechanics lien is one of the most powerful collection remedies available to contractors, subcontractors and suppliers who are unpaid for work performed and materials supplied in relation to a California private works construction project. The mechanics lien allows the claimant to actually sell the property where the work was carried out in order to obtain payment, entirely of course, against the wishes of the property owner. There are a number of important steps to follow and timelines to be met in order to pursue this remedy.
First, Understand Your Preliminary Notice Deadline
Working within deadlines is absolutely crucial to preserving mechanics lien rights under California law. The deadlines differ, depending on whether you are a “direct” contractor, also known as “original” or “prime” contractor (one who contracts directly with the property owner) or a subcontractor or material supplier. The process begins with the serving of a “preliminary notice” no later than 20 days after the party serving the preliminary notice begins supplying labor or materials to the project. Direct contractors are only required to serve the preliminary notice on the construction lender (Civil Code section 8200-8216), whereas subcontractors and material suppliers must serve not only the construction lender, but also the owner and direct contractor (see Civil Code section 8200(e)).
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Illinois Federal Court Applies Insurer-Friendly “Mutual Exclusive Theories” Test To Independent Counsel Analysis
November 09, 2020 —
Jeremy S. Macklin - Traub Lieberman Insurance Law BlogInsureds often request independent counsel when insurers agree to provide a defense subject to a reservation of rights, pursuant to which an insurer takes the position that certain damages may not be indemnifiable. Requests for independent counsel are often rooted in fear that a defense attorney who has a relationship with the insurer may be incentivized to defend the insured in a way that maximizes the potential for the insurer to succeed on its coverage defenses. As explained by the Illinois Supreme Court in Maryland Cas. Co. v. Peppers, 355 N.E.2d 24 (Ill. 1976), when a conflict of interest arises between an insurer and its insured, the attorney appointed by the insurer is faced with serious ethical questions and the insured is entitled to its own attorney.
Illinois courts generally follow the rule that an insured is entitled to independent counsel upon a showing of an actual conflict. In Builders Concrete Servs., LLC v. Westfield Nat’l Ins. Co., No. 19 C 7792, 2020 WL 5518474 (N.D. Ill. Sept. 14, 2020), the U.S. District Court for the Northern District of Illinois recently addressed a dispute between an insurer and its insured about independent counsel.
Westfield insured Builders Concrete Services (BCS). Focus Construction hired BCS as a subcontractor to perform concrete work on a new apartment building. BCS’ work included pouring concrete for structural columns, one of which buckled and failed. BCS sued Focus Construction for withholding payment, and Focus Construction counter-sued for breach of contract and negligence relating to BCS’ alleged faulty work that caused the column to fall. Focus Construction’s counterclaim alleged that the column failure damaged other parts of the building on which Builders did not perform work.
Read the court decisionRead the full story...Reprinted courtesy of
Jeremy S. Macklin, Traub LiebermanMr. Macklin may be contacted at
jmacklin@tlsslaw.com
Court Rejects Anti-SLAPP Motion in Construction Defect Suit
September 01, 2011 —
CDJ STAFFThe California Court of Appeals has upheld the denial of an anti-SLAPP motion in Claredon American Insurance Company v. Bishop, Barry, Howe, Haney & Ryder. This case was triggered by a water intrusion problem at a condominium complex, the Terraces at Emerystation, built and sold by Wareham Development Corporation. The insurer, Claredon, retained Risk Enterprise Management as the third party claims administrator. REM retained the law firm Bishop, Barry, Howe, Haney & Ryder. The construction defect case was settled in 2007 and the condo owners moved back by early 2008.
Due to issues with the claims settlement, Claredon filed against REM for “professional negligence, indemnity, apportionment and contribution,” with a cross-complaint that the cross-defendants negligently defended the developer, Wareham.
In response, the cross-defendants filed a motion to strike the cross-complaint under the anti-SLAPP statute. The trial court denied this motion and now this has been upheld by the appeals court.
The court noted that “The fundamental thrust of the cross-complaint is not protected litigation-related speech and petitioning activity undertaken on another’s behalf in a judicial proceeding.”
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
When is Construction Put to Its “Intended Use”?
July 31, 2013 —
Brady Iandiorio, Higgins, Hopkins, McLain & Roswell, LLCDefining words and phrases in the law can be a tricky proposition. In everyday life one would presume to know what the phrase “intended use” would mean, but when it comes to litigation, oftentimes the definitions become much more nuanced.
On March 12, 2013, in the Bituminous Cas. Corp. v. Hartford Cas. Ins. Co. v. Canal Ins. Co., WL 950800 (D. Colo. 2013) case, Senior District Court Judge Wiley Y. Daniel denied Third-Party Defendant Canal Insurance Company’s (“Canal”) motion to dismiss Third-Party Plaintiff Hartford Casualty Insurance Company’s (“Hartford”) third-party complaint. The case arose out of a liability insurance coverage dispute related to an underlying construction defect lawsuit. In the construction defect suit, a plaintiff homeowner’s association brought a suit against a developer and a general contractor (“GC”) among others. While the underlying action was settled, a dispute remained between Bituminous Casualty Corporation, which insured the GC, and Hartford, which insured the developer.
Hartford asserted third-party claims against Canal seeking a declaration of Canal’s obligations and contribution in the event Hartford owed any defense or indemnity obligations to the GC. Hartford’s claims are based on the premise that Canal owed a duty to defend and/or indemnify the GC in the underlying action.
Read the court decisionRead the full story...Reprinted courtesy of
Brady IandiorioBrady Iandiorio can be contacted at
Iandiorio@hhmrlaw.com
Washington’s Court of Appeals Protects Contracting Parties’ Rights to Define the Terms of their Indemnity Agreements
March 19, 2024 —
Margarita Kutsin - Ahlers Cressman & Sleight PLLCIt has long been the law in Washington that contracting parties are free to draft contractual indemnity agreements to allocate risk arising from performance of the work, and Courts will generally enforce those agreements as written. This well-settled principle was recently reaffirmed in King County v. CPM Development Corp., dba ICON Materials[1] a decision from Division I of the Washington Court of Appeals, wherein one party to an indemnity agreement attempted to evade its contractual obligations by arguing that certain common law indemnity principles supersede the written terms. This appeal followed a multi-week jury trial from which the client and Ahlers Cressman and Sleight legal team, including Lindsay Watkins, Klien Hilliard, and Christina Granquist, obtained a seven-figure judgment in the client’s favor, including an award of all attorneys’ fees and costs.
ICON was the general contractor on a Vashon Island Highway Pavement project for King County. Part of the work on the project involved hauling away and disposing of ground milled asphalt (the “millings”) at King County-approved sites. ICON and D&R Excavating Inc., (“D&R”) executed a subcontract for D&R to perform that work. The subcontract incorporated the contract between ICON and King County, including the obligation to stockpile millings only at approved sites. D&R, however, did not obtain the requisite approvals from King County, and placed the millings at various sites on the Island, including locations that King County explicitly rejected.
Read the court decisionRead the full story...Reprinted courtesy of
Margarita Kutsin, Ahlers Cressman & Sleight PLLCMs. Kutsin may be contacted at