California Senator Proposes Bill to Require Contractors to Report Construction Defect Cases
January 04, 2018 —
David Suggs - Bert L. Howe & Associates, Inc.According to Renne Schiavone’s of Patch.com in her article “Sen. Hill Wants Contractors to Report Construction Defect Cases”, Senator Jerry Hill of San Mateo County proposed a bill on December 21st, 2017 requiring construction defect settlements to be reported by contractors to the licensing board. This proposal comes after the tragic incident that took place back on June 16, 2015 during which a balcony on the fifth floor of a Berkeley apartment complex collapsed. This resulted in the death of six students and serious injuries for an additional seven individuals.
An investigation revealed that three years prior to the balcony collapse, Segue Construction, who built the apartment complex, had paid $26.5 million in construction defect lawsuit settlements. Since the law doesn’t require these settlements to be reported by contractors, the Contractors State License Board (CSLB) wasn’t aware of the case.
"Working together we can take even stronger steps to protect the public by ensuring that this critically important data is accessible to the Contractors State License Board," said Senator Hill. Senate Bill 465 will aim to protect consumers with more regulation and transparency. Senator Hill is also working on Senate Bill 721 which would require periodic condo and apartment building inspections of exterior elevated walking surfaces, stairwells, and balconies.
Read the court decisionRead the full story...Reprinted courtesy of
Vinny Testaverde Alleges $5 Million Mansion Riddled with Defects
January 15, 2014 —
Melissa Zaya-CDJ STAFFFormer Tampa Bay Buccaneers quarterback Vinny Testaverde and his wife Mitzi filed suit December 20, 2013 claiming breach of contract and building code violations on their $5 million, Odessa, Florida mansion, according to the Tampa Tribune. The Testaverdes allege that their six-year old, 6,700 square foot home has multiple defects, including “wet floors and walls when it rains and a grand staircase leading to the front door that is sinking, taking with it two columns that support the porch roof,” The Tampa Tribune reports.
Gray Homes of Tampa Bay were contracted by the couple to build their mansion on Lake Keystone. The Tampa Tribune stated that several months before filing suit, the Testaverdes sent a certified letter to Gray Homes stating they had uncovered “a series of defects.” According to the article, Gray Homes had not yet responded to the Tampa Tribune’s message asking for a comment.
Read the court decisionRead the full story...Reprinted courtesy of
California Supreme Court Upholds Insurance Commissioner’s Authority to Regulate Replacement Cost Estimates
January 26, 2017 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPn Assn. of Cal. Insurance Companies v. Jones ( No. S226529, filed 1/23/17), the California Supreme Court reversed trial and appellate court decisions to hold that California’s Insurance Commissioner Dave Jones had the authority to promulgate California Code of Regulations, title 10, section 2695.183, which sets out specific requirements for estimating replacement cost as part of any application for or renewal of homeowners insurance.
The regulation was promulgated in 2010 in response to complaints from homeowners who lost their homes in the Southern California wildfires of 2003, 2007, and 2008, and who discovered that they did not have enough insurance to cover the full cost of repairing or rebuilding their homes because the insurers’ estimates of replacement value were too low when they purchased the insurance.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Policy's Operation Classification Found Ambiguous
May 21, 2014 —
Tred R. Eyerly – Insurance Law HawaiiProperty damage caused by a subcontractor's sheet piling was found to be within the policy's operation classification, which included "grading of land." Canal Indemn. Co. v. Margaretville of NSM, Inc., No. 13-13541 (11th Cir. April 15, 2014).
Canal issued a CGL policy to the insured. The policy had a classification limitation provision: “This insurance applies to bodily injury, property damage, personal injury, advertising injury or medical expense arising out of only those operations that are classified and shown on the Commercial General Liability Coverage Declarations . . .”
The policy's Declarations, in turn, referred to the operation classification as "Grading of Land - INCL. Borrowing, Filling or Back Filling." The policy did not define these terms.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Home Construction Slows in Las Vegas
November 27, 2013 —
CDJ STAFFAlthough home builders in the Las Vegas area are doing better than they were in 2012, growth is still slow and October saw a decline in the sale of new homes. However, as with other areas, the average home price actually increased over prior months, despite the cooling off the actual number of sales.
Taken as a whole though, 2013 looks a lot better than 2012, with 44% more homes sold this year. Dennis Smith, the president of Home Builders Research said that 2013 “will be remembered as ‘the year of recovery,’” but added that “there is still a long path ahead for everyone to feel a sense of comfort.”
Read the court decisionRead the full story...Reprinted courtesy of
Coverage Denied for Insured's Defective Product
October 15, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe court found there was no coverage obligations for the insured's defective product. Titanium Indus., Inc. v. Federal. Ins. Co., 2014 WL 4428324 (N.J. Super. Ct. App. Div. Sept. 10, 2014).
The insured, Titanium Industries, supplied titanium bar materials to Biomet Manufacturing Corporation. Biomet manufactured orthopedic implants and devises. The titanium was used to manufacture screws to incorporate into Biomet's products.
Biomet notified the insured of a potential defect in some of the titanium material, described as "alloy segregation," i.e., the failure of alloys in a metal to completely melt, causing the alloy to separate and undermine the strength of the finished product. The insured and Biomet negotiated a settlement, which included lost profits and the cost of returning the titanium.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
History of Defects Leads to Punitive Damages for Bankrupt Developer
March 01, 2012 —
CDJ STAFFThe South Carolina Court of Appeals has ruled that evidence of construction defects at a developer’s other projects were admissible in a construction defect lawsuit. They issued their ruling on Magnolia North Property Owners’ Association v. Heritage Communities, Inc. on February 15, 2012.
Magnolia North is a condominium complex in South Carolina. The initial builder, Heritage Communities, had not completed construction when they filed for bankruptcy protection under Chapter 11. The remaining four buildings were completed by another contractor. The Property Owners’ Association subsequently sued Heritage Communities, Inc. (HCI) alleging defects. The POA also sued Heritage Magnolia North, and the general contractor, BuildStar.
The trial court ruled that all three entities were in fact one. On appeal, the defendants claimed that the trial court improperly amalgamated the defendants. The appeals court noted, however, that “all these corporations share officers, directors, office space, and a phone number with HCI.” Until Heritage Communities turned over control of the POA to the actual homeowners, all of the POA’s officers were officers of HCI. The appeals court concluded that “the trial court’s ruling that Appellants’ entities were amalgamated is supported by the law and the evidence.”
Heritage also claimed that the trial court should not have allowed the plaintiffs to produce evidence of construction defects at other Heritage properties. Heritage argued that the evidence was a violation of the South Carolina Rules of Evidence. The court cited a South Carolina Supreme Court case which made an exception for “facts showing the other acts were substantially similar to the event at issue.” The court noted that the defects introduced by the plaintiffs were “virtually identical across all developments.” This included identical use of the same products from project to project. Further, these were used to demonstrate that “HCI was aware of water issues in the other projects as early as 1998, before construction on Magnolia North had begun.”
The trial case ended with a directed verdict. Heritage charged that the jury should have determined whether the alleged defects existed. The appeals court noted that there was “overwhelming evidence” that Heritage failed “to meet the industry standard of care.” Heritage did not dispute the existence of the damages during the trial, they “merely contested the extent.”
Further, Heritage claimed in its appeal that the case should have been rejected due to the three-year statute of limitations. They note that the first meeting of the POA was on March 8, 2000, yet the suit was not filed until May 28, 2003, just over three years. The court noted that here the statute of limitation must be tolled, as Heritage controlled the POA until September 9, 2002. The owner-controlled POA filed suit “approximately eight months after assuming control.”
The court also applied equitable estoppel to the statute of limitations. During the time in which Heritage controlled the board, Heritage “assured the unit owners the construction defects would be repaired, and, as a result, the owners were justified in relying on those assurances.” Since “a reasonable owner could have believed that it would be counter-productive to file suit,” the court found that also prevented Heritage from invoking the statute of limitations. In the end, the appeals court concluded that the even apart from equitable tolling and equitable estoppel, the statute of limitations could not have started until the unit owners took control of the board in September, 2002.
Heritage also contested the jury’s awarding of damages, asserting that “the POA failed to establish its damages as to any of its claims.” Noting that damages are determined “with reasonable certainty or accuracy,” and that “proof with mathematical certainty of the amount of loss or damage is not required,” the appeals court found a “sufficiently reasonable basis of computation of damages to support the trial court’s submission of damages to the jury.” Heritage also claimed that the POA did not show that the damage existed at the time of the transfer of control. The court rejected this claim as well.
Finally, Heritage argued that punitive damages were improperly applied for two reasons: that “the award of punitive damages has no deterrent effect because Appellants went out of business prior to the commencement of the litigation” and that Heritages has “no ability to pay punitive damages.” The punitive damages were upheld, as the relevant earlier decision includes “defendant’s degree of culpability,” “defendants awareness or concealment,” “existence of similar past conduct,” and “likelihood of deterring the defendant or others from similar conduct.”
The appeals court rejected all of the claims made by Heritage, fully upholding the decision of the trial court.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Alert: AAA Construction Industry Rules Update
June 07, 2021 —
Christopher G. Hill - Construction Law MusingsThe American Arbitration Association has made some needed updates to their Construction Industry Arbitration and Mediation Rules, effective July 1, 2015. Among the changes listed at their website are:
- A mediation step for all cases with claims of $100,000 or more (subject to the ability of any party to opt out).
- Consolidation and joinder time frames and filing requirements to streamline these increasingly involved issues in construction arbitrations.
- New preliminary hearing rules to provide more structure and organization to get the arbitration process on the right track from the beginning.
- Information exchange measures to give arbitrators a greater degree of control to limit the exchange of information, including electronic documents.
- Availability of emergency measures of protection in contracts that have been entered into on or after July 1, 2015.
- Enforcement power of the arbitrator to issue orders to parties that refuse to comply with the Rules or the arbitrator’s orders.
- Permissibility of dispositive motions to dispose of all or part of a claim or to narrow the issue in a claim.
Read the court decisionRead the full story...Reprinted courtesy of