Traub Lieberman Partner Jonathan Harwood Obtains Summary Judgment Determining Insurer Has No Duty to Defend or Indemnify
February 27, 2023 —
Jonathan R. Harwood - Traub LiebermanTraub Lieberman Partner Jonathan Harwood obtained summary judgment in favor of the Plaintiff determining that it had no duty to defend or indemnify an insured in a personal injury action, in a case brought in the Eastern District of New York.
The Plaintiff, an insurance provider (“the Insurer”), issued a General Commercial Policy (the “Policy”) to the Defendant, a commercial property owner (the “Property Owner”). In the underlying action, a former employee (the “Employee”) of a concrete vendor sued the Property Owner, and others, in New York Supreme Court, Queens County, for an injury that occurred on the street in front of the Property Owner’s premises during the course of repairs of sewer pipes that serviced the Property Owner’s premises.
Read the court decisionRead the full story...Reprinted courtesy of
Jonathan R. Harwood, Traub LiebermanMr. Harwood may be contacted at
jharwood@tlsslaw.com
Preparing For the Worst with Smart Books & Records
November 07, 2012 —
CDJ STAFFContractors are often too caught up in keeping the wheel of business churning to recognize deficiencies in how their records are managed. Working hard and working often tend to leave little time for consideration of your documents. But all too often I see the unthinkable, a contractor gets into trouble and has to call on its surety for help. At that point, you might finally get your first dose of reality about your records – and it can cost you.
Read the court decisionRead the full story...Reprinted courtesy of
Douglas Reiser of Reiser Legal LLC.Mr. Reiser can be contacted at
info@reiserlegal.com
Contractor Walks Off Job. What are the Owner’s Damages?
September 25, 2018 —
David Adelstein - Florida Construction Legal UpdatesWhat are your damages as the result of a breach of the construction contract? This is an important question, right? It is probably the most important part of your case. If you didn’t have damages, you wouldn’t be in a dispute. So, I repeat, what are your damages as the result of a breach of the construction contract? The below case explains dealing with a contractor that elected to walk off the job mid-construction.
In Forbes v. Prime General Contractors, Inc., 43 Fla.L.Weekly D20194a (Fla. 2d DCA 2018), owners hired a contractor to perform a residential renovation job for $276,000. The owners were to pay the contractor in five draw payments (common for residential jobs) where the third draw payment was due upon the contractor’s completion of the dry-in (as defined in the contract). After the contractor received the first two draw payments totaling $138,000 plus an additional $6,000 for updated architectural plans, the contractor claimed the job doubled in price and demanded that the owners pay the contractor the third draw payment immediately (before it was due) plus an additional $31,450. The contractor refused to continue unless the owners agreed to its terms, and then walked off the job when the owners would not agree to these terms (nor should the owners agree to those terms). At the time the contractor walked off the job, the owners’ home was not habitable due to the construction.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Handshake Deals Gone Wrong
May 22, 2023 —
Jessica Allain - ConsensusDocsThe construction industry has it fair share of “handshake deals”, oral agreements relying on the integrity of the people involved. But when it comes to protecting and enforcing legal rights, it is always a better idea to properly paper the deal and get it in writing. Otherwise, contractors relying on verbal promises may find themselves without any legal remedy should the deal go south. After all, it is not just a matter of trust, but also a way to document that everybody agrees on what the terms of the deal actually are.
For example, a recent case out of New York highlights the dangers of unwritten promises. In Castle Restoration, LLC v. Castle Restoration & Construction, Inc., No. 16349-15 (N.Y. App. Div. 2/9/22), 2022 NY Slip Op 50082(U), 2022 WL 402882, 2022 N.Y. Misc. LEXIS 485, Castle Inc. and Castle LLC entered into a deal for an asset sale to transfer equipment and a client list from Castle Inc. to Castle LLC. While that initial asset sale was properly papered with sale documents and a promissory note, the parties entered into a subsequent handshake/oral agreement where Castle LLC agreed to provide Castle Inc. with labor and materials on construction projects, and those goods and services would offset the payment obligation under the promissory note. But the problem was that the contract for the asset sale had a provision that the agreement could not be changed by oral agreement; rather, any changes had to be made in writing.
Reprinted courtesy of
Jessica Allain, Jones Walker LLP (ConsensusDocs)
Ms. Allain may be contacted at jallain@joneswalker.com
Read the court decisionRead the full story...Reprinted courtesy of
2023 Executive Insights From Leaders in Construction Law
June 12, 2023 —
Construction ExecutiveIf a major project is interrupted or canceled, are there any laws that provide protection for unpaid contractors that have performed work?
Angela Richie
Partner, Co-Chair, Construction Practice Group
Gordon Rees Scully Mansukhani
With the current volatility and uncertainty in the economy, project interruptions and cancellations are on the rise; hence, you need to take steps now to make sure you have a method to get paid for the work you have performed.
For private projects, make sure you have followed the pre-lien notification requirements for the state in which the project is located before you start work, if they are required. Then, be sure to follow the lien notice and lien filing requirements for the state. Each state is different, so you want to be ready with the appropriate documentation in advance of the project interruption or cancellation.
Reprinted courtesy of
Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Allegations that Carrier Failed to Adequately Investigate Survive Demurrer
July 30, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe California Court of Appeal reversed the trial court's dismissal of a complaint alleging bad faith for the insurer's failure to adequately investigate the claim. Maslo v. Ameriprise Auto & Home Ins., 2014 Cal. App. LEXIS 564 (Cal. Ct. App. June 27, 2014).
The insured was injured in an auto accident caused by an uninsured motorist. The insured sought policy limits of $250,000 from the insurer. In response, the insurer demanded arbitration. The arbitrator awarded $164,120.91.
The insured sued, alleging the breach of the covenant of good faith and fair dealing. The First Amended Complaint (FAC) alleged the insured was not at fault. The police report found that the uninsured motorist was the sole cause of the accident. The insured provided the police report and medical records to the insurer. When the insured demanded the $250,000 policy limits, the insurer did not respond.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
URGENT: 'Catching Some Hell': Hurricane Michael Slams Into Florida
October 16, 2018 —
Associated Press (Jay Reeves & Brendan Farrington) - BloombergPanama City, Fla. (AP) -- Powerful Hurricane Michael slammed into the Florida Panhandle with terrifying winds of 155 mph Wednesday, splintering homes and submerging neighborhoods before continuing its destructive march inland across the Southeast. It was the most powerful hurricane to hit the continental U.S. in nearly 50 years and at least one death was reported during its passage.
Supercharged by abnormally warm waters of the Gulf of Mexico, the Category 4 storm crashed ashore in the early afternoon near Mexico Beach, a tourist town about midway along the Panhandle, a 200-mile (320-kilometer) stretch of white-sand beach resorts, fishing towns and military bases. After it ravaged the Panhandle, Michael entered south Georgia as a Category 3 hurricane — the most powerful in recorded history for that part of the neighboring state.
Read the court decisionRead the full story...Reprinted courtesy of
Bloomberg
Contract Should Have Clear and Definite Terms to Avoid a Patent Ambiguity
December 11, 2023 —
David Adelstein - Florida Construction Legal UpdatesIf you need more of a reason to have contracts with clear and definite terms, this case is it. This case exemplifies what can happen if the contract, not only does not have clear and definite terms, but contains a patent ambiguity. The contract will be deemed unenforceable which will make one of the contracting parties very unhappy!
In Bowein v. Sherman, 48 Fla.L.Weekly D2208a (Fla. 6th DCA 2023), the buyer and seller entered into a real estate transaction. The transaction was for $2 Million. The purchase-and-sale agreement included the address and legal description of a parcel to be sold. However, there was a section in the agreement called “Other Terms and Conditions” which identified that the offer was actually for four properties that were being sold by the seller. When it came to closing time, the seller refused to close because the seller disputed that the $2 Million purchase price was for all four of his properties. The buyer sued the seller for specific performance to force the sale which the trial court agreed in favor of the buyer. However, the appellate court did not.
First, the appellate court held that “[t]he equitable remedy of specific performance may be granted only where the parties have actually entered into a definite and certain agreement.” Bowein, supra (quotation and citation omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com