Receiving a $0 Verdict and Still Being Deemed the Prevailing Party for Purposes of Attorney’s Fees
May 24, 2018 —
David Adelstein - Florida Construction Legal UpdatesLow and behold, a party can be the prevailing party for purposes of attorney’s fees even if that party is awarded $0. That’s right, even if the party is awarded a big fat zero, they can still be the prevailing party for purposes of being entitled to attorney’s fees. This is because a party is the prevailing party if they prevail on the significant issues in the case. A party can prevail on the significant issues even if that party is awarded $0. Whoa!
For example, in Coconut Key Homeowner’s Association, Inc. v. Gonzalez, 43 Fla.L.Weekly D1045a (Fla. 4th DCA 2018), a homeowner sued her homeowner’s association claiming the association breached its governing documents. There was a basis for fees under Florida’s homeowner’s association law (and there likely was a basis under the governing documents). At trial, the jury held that the association breached its governing documents, but awarded the homeowner nothing ($0). The trial court also issued injunctive relief in favor of the homeowner. The homeowner claimed she should be deemed the prevailing party for purposes of attorney’s fees; however, this was denied by the trial court based on the $0 verdict and no fees were awarded to the homeowner.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Wildfire Insurance Coverage Series, Part 4: Coverage for Supply Chain Related Losses
July 18, 2022 —
Scott P. DeVries & Yosef Itkin - Hunton Insurance Recovery BlogBusiness loss is not limited to fire or smoke damage to its own property – it often arises from damage to the supply chain. In this post in the Blog’s Wildfire Insurance Coverage Series, we look at what coverage may exist when wildfire damages an entity’s supply chain.
In many instances, while the insured property does not sustain fire or smoke damage, wildfires can wreak havoc on the business supply chain. For some, contingent business interruption coverage may be a solution. Contingent business interruption insurance extends coverage for the loss of prospective earnings because of an interruption in the insured’s supply chain that is caused by damage to property that the insured neither owns nor operates.[1] Typically, the property covered is of a supplier or customer. For example, in 2000, Ericsson Telecom A.B., a mobile phone manufacturer, presented a substantial contingent business interruption claim based on a fire that damaged a Royal Philips Electronics semiconductor plant. Royal Philips supplied critical components for Ericsson’s mobile phones. The fire caused Royal Philips to close its plant, halting Ericsson’s phone production for six weeks, resulting in substantial losses.
Reprinted courtesy of
Scott P. DeVries, Hunton Andrews Kurth and
Yosef Itkin, Hunton Andrews Kurth
Mr. DeVries may be contacted at sdevries@HuntonAK.com
Mr. Itkin may be contacted at yitkin@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
How the California and Maui Wildfires Will Affect Future Construction Projects
October 30, 2023 —
Susan Doering - Construction ExecutiveJust like any kind of fire, wildfires are caused by the presence of fuel and a spark. In the case of the
2017 fires in the wine country of California, along with the state's 2018
Camp Fire, the fuel was dry leaf litter, branches and downed trees. And the spark, in some cases, resulted from electric utility lines and, in other cases, due to contractor’s work.
More recently, this summer's Maui fires have taken hundreds of lives—deceased and missing—and burned more than 2,500 acres. Lahaina’s historic sites cannot be replaced, and estimates of the rebuild costs are near $5 billion. In Hawaii, the fuel was the same as in California: dried forest debris. It is alleged that the spark was from a powerline downed by extreme winds from Hurricane Dora. While sparks were present, it is the increased volume of fuel that has been the true source of the disastrous recent wildfires.
The increased presence of fuel is the result of recent changes in forestry-management practices, coupled with accelerated climatic shifts in recent years toward hotter, drier weather from 2011 to 2020 in California and 2022 to 2023 in Maui, increasing both frequency and severity.
Reprinted courtesy of
Susan Doering, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Everyone Wins When a Foreclosure Sale Generates Excess Proceeds
August 07, 2018 —
Ben Reeves - Snell & Wilmer Real Estate Litigation BlogIntroduction
When a foreclosure sale generates more money than needed to pay off the lien, the excess proceeds usually go first to creditors in the order of their priority, and second to the owner after creditors are paid in full. So, in truth, not everyone wins when a foreclosure sale brings in too much money. Amusingly, in Steinmetz v. Everyone Wins, the court awarded excess sale proceeds to….you guessed it…Everyone Wins, despite the owner’s argument that Arizona’s anti-deficiency statutes barred it from recovering anything.
In addition to supplying a clever title for this post, Steinmetz v. Everyone Wins provides an important analysis of how Arizona’s anti-deficiency statutes, homeowner’s assessment lien statutes, and foreclosure statutes apply when determining who “wins” when it comes to excess sale proceeds.
Read the court decisionRead the full story...Reprinted courtesy of
Ben Reeves, Snell & WilmerMr. Reeves may be contacted at
breeves@swlaw.com
The Connecticut Appellate Court Decides That Construction Contractor Was Not Obligated To Continue Accelerated Schedule to Mitigate Its Damages Following Late Delivery of Materials by Supplier
April 11, 2022 —
Robert M. Barrack - Gordon & ReesIn United Concrete Prods. v. NJR Constr., LLC, 207 Conn. App. 551, 263 A.3d 823 (2021), the Connecticut Appellate Court has issued a decision that should be of interest to the Connecticut construction industry and the construction bar. The lawsuit arose out of the late delivery of materials on a construction project, which is a frequent problem on construction projects. In United Concrete Products, the defendant general contractor, NJR Construction, LLC (“NJR”) was retained by the State of Connecticut Department of Transportation (“DOT”) to replace a bridge over the Hockanum River (“Project”). Id. at 555-58 (2021). The Prime Contract provided that NJR with an eight-week time-frame to perform the work, at which time the road would be closed to traffic. Id. The Prime Contract also provided for a bonus of $3,000 for each day the road was opened to traffic prior to the eight week deadline of August 8, 2016, and for liquidated damages of $3,000 for each day the road remained closed beyond the deadline. Id.
NJR subsequently entered into a purchase order (“Subcontract”) with the plaintiff, United Concrete Products, Inc. (“United”), whereby United agreed to provide certain concrete components for the Project, including ten pre-stressed concrete beams. Id. The Subcontract required that United deliver the concrete beams by June 7, 2016, but, NJR did not actually schedule the delivery until June 29, 2016. Id. Nevertheless, even with that schedule NJR could have reopened the road by July 19, 2016, which would have allowed it to receive the full $60,000 incentive bonus. However, United did not deliver the concrete beams until July 26, 2016, which caused NJR to lose the incentive bonus, be assessed liquidated damages by the DOT, and to incur additional delay damages. Id. After deducting the amount of $179,500 in damages that it incurred due to United’s late delivery of the beams, NJR paid United the balance of $66,074.75. Id.
Read the court decisionRead the full story...Reprinted courtesy of
Robert M. Barrack, Gordon Rees Scully Mansukhani, LLPMr. Barrack may be contacted at
rbarrack@grsm.com
California Bullet Train Clears Federal Environmental Approval
June 30, 2014 —
Michael B. Marois – BloombergThe U.S. Federal Railroad Administration has approved an environmental review needed to begin building a portion of a $68 billion California high-speed rail line that has been mired in lawsuits.
The agency, part of the Transportation Department, said in a release that it cleared a 114-mile (183-kilometer) stretch of the project in the Central Valley.
The California High-Speed Rail Authority has been blocked from selling bonds to begin construction of the first U.S. bullet train until a court decides whether details of the financing were adequately disclosed.
Read the court decisionRead the full story...Reprinted courtesy of
Michael B. Marois, BloombergMr. Marois may be contacted at
mmarois@bloomberg.net
Drones, Googleplexes and Hyperloops
March 05, 2015 —
Garret Murai – California Construction Law BlogI don’t know if it’s just me, or if there has been a lot of news lately about technology and construction:
Although flying in the face of some bad press recently, the use of drones in construction. And we’re talking about more than just cameras with propellers.
Battle of the (tech) Titans, as Google battles it out with the likes of LinkedIn and Microsoft for development rights in Mountain View, California for its futuristic new Googleplex. And we’re talking about more than just cameras with propellers.. And Google is only the most recent tech titan with development plans. Facebook’s Frank Gehry-designed campus expansion is in the works and Apple’s “spaceship” campus has already broken ground. We’ve come a long way since the HP garage in Palo Alto, baby!
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Quick Note: Be Careful with Pay if Paid Clauses (Both Subcontractors and General Contractors)
June 17, 2015 —
Christopher G. Hill – Construction Law MusingsAside from waiver of lien rights (something that will be illegal in Virginia after July 1, 2015), the most troublesome contractual impediment to payment for a subcontractor or supplier on a project often is the “pay if paid” clause. As a general rule, in Virginia, these clauses where drafted in the proper fashion, are enforceable. As I have said many times, in Virginia freedom of contract almost always wins out.
While this is the case, I emphasize that such clauses must be very explicit and specific. Furthermore, and in something that should be obvious, these clauses are generally limited by the Courts of Virginia to only be enforceable and to only forgive the need for payment if the upstream contractor on the construction job has not been paid for the work that the sub claiming non payment has done.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com