History of Defects Leads to Punitive Damages for Bankrupt Developer
March 01, 2012 —
CDJ STAFFThe South Carolina Court of Appeals has ruled that evidence of construction defects at a developer’s other projects were admissible in a construction defect lawsuit. They issued their ruling on Magnolia North Property Owners’ Association v. Heritage Communities, Inc. on February 15, 2012.
Magnolia North is a condominium complex in South Carolina. The initial builder, Heritage Communities, had not completed construction when they filed for bankruptcy protection under Chapter 11. The remaining four buildings were completed by another contractor. The Property Owners’ Association subsequently sued Heritage Communities, Inc. (HCI) alleging defects. The POA also sued Heritage Magnolia North, and the general contractor, BuildStar.
The trial court ruled that all three entities were in fact one. On appeal, the defendants claimed that the trial court improperly amalgamated the defendants. The appeals court noted, however, that “all these corporations share officers, directors, office space, and a phone number with HCI.” Until Heritage Communities turned over control of the POA to the actual homeowners, all of the POA’s officers were officers of HCI. The appeals court concluded that “the trial court’s ruling that Appellants’ entities were amalgamated is supported by the law and the evidence.”
Heritage also claimed that the trial court should not have allowed the plaintiffs to produce evidence of construction defects at other Heritage properties. Heritage argued that the evidence was a violation of the South Carolina Rules of Evidence. The court cited a South Carolina Supreme Court case which made an exception for “facts showing the other acts were substantially similar to the event at issue.” The court noted that the defects introduced by the plaintiffs were “virtually identical across all developments.” This included identical use of the same products from project to project. Further, these were used to demonstrate that “HCI was aware of water issues in the other projects as early as 1998, before construction on Magnolia North had begun.”
The trial case ended with a directed verdict. Heritage charged that the jury should have determined whether the alleged defects existed. The appeals court noted that there was “overwhelming evidence” that Heritage failed “to meet the industry standard of care.” Heritage did not dispute the existence of the damages during the trial, they “merely contested the extent.”
Further, Heritage claimed in its appeal that the case should have been rejected due to the three-year statute of limitations. They note that the first meeting of the POA was on March 8, 2000, yet the suit was not filed until May 28, 2003, just over three years. The court noted that here the statute of limitation must be tolled, as Heritage controlled the POA until September 9, 2002. The owner-controlled POA filed suit “approximately eight months after assuming control.”
The court also applied equitable estoppel to the statute of limitations. During the time in which Heritage controlled the board, Heritage “assured the unit owners the construction defects would be repaired, and, as a result, the owners were justified in relying on those assurances.” Since “a reasonable owner could have believed that it would be counter-productive to file suit,” the court found that also prevented Heritage from invoking the statute of limitations. In the end, the appeals court concluded that the even apart from equitable tolling and equitable estoppel, the statute of limitations could not have started until the unit owners took control of the board in September, 2002.
Heritage also contested the jury’s awarding of damages, asserting that “the POA failed to establish its damages as to any of its claims.” Noting that damages are determined “with reasonable certainty or accuracy,” and that “proof with mathematical certainty of the amount of loss or damage is not required,” the appeals court found a “sufficiently reasonable basis of computation of damages to support the trial court’s submission of damages to the jury.” Heritage also claimed that the POA did not show that the damage existed at the time of the transfer of control. The court rejected this claim as well.
Finally, Heritage argued that punitive damages were improperly applied for two reasons: that “the award of punitive damages has no deterrent effect because Appellants went out of business prior to the commencement of the litigation” and that Heritages has “no ability to pay punitive damages.” The punitive damages were upheld, as the relevant earlier decision includes “defendant’s degree of culpability,” “defendants awareness or concealment,” “existence of similar past conduct,” and “likelihood of deterring the defendant or others from similar conduct.”
The appeals court rejected all of the claims made by Heritage, fully upholding the decision of the trial court.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Real Estate & Construction News Round-Up 05/04/22
May 23, 2022 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogConstruction payment apps are on the rise, the European Union proposes to block Russians from buying European real estate, warehouse vacancy rates hit a 27-year low, and more.
- The Metaverse Group has made itself one of the most prominent virtual land owners, having invested more than $10 million into digital real estate purchases. (Katie Canales, Business Insider)
- The European Union proposed to block Russians from buying European real estate in its six package of sanctions following Russia’s invasion of Ukraine. (Jorge Valero and Alberto Nardelli, Bloomberg)
- Although smart office buildings are able to easily identify viruses, they are susceptible to hacks, raising privacy and cybersecurity concerns in the market. (Konrad Putzier, The Wall Street Journal)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
How Many Bridges Does the Chesapeake Bay Need?
August 03, 2022 —
Ethan McLeod - BloombergSteve Kline, a 7th-generation Marylander, knows well the vacation tradition of driving across the twin spans of the Chesapeake Bay Bridge for trips to the beach resort of Ocean City. His grandfather, an ironworker, helped build the bridge’s first span, which opened in 1952.
He’s also very familiar with another seasonal rite: wading through the infamous miles-long traffic backups that last from Memorial Day through the end of summer.
But Kline, president of the nonprofit Eastern Shore Land Conservancy, is not on board with the state’s proposed multibillion-dollar fix — a new 4.3-mile-long crossing, to be built alongside the two current spans of the Bay Bridge. In April, the Maryland Transportation Authority (MDTA) announced it had received federal approval to use this route for a potential new, wider bridge that would be likely to eventually replace its older siblings, addressing the notorious summer bottlenecks for decades to come. And on June 10, at a press conference held near the bridge’s eastbound ramp, Maryland Governor Larry Hogan announced that he would commit $28 million in bridge toll revenue to fund the second phase of an environmental impact study on the idea.
Read the court decisionRead the full story...Reprinted courtesy of
Ethan McLeod, Bloomberg
Real Estate & Construction News Roundup (04/26/23) – The Energy Transition and a Bit of Brick-and-Mortar Blues
May 01, 2023 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn today’s roundup, Americans can buy homes with bitcoin, new tech aims to engineer a novel building material, federal investments boost the coastline (and construction sales), and more.
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Almost Nothing Is Impossible
October 30, 2018 —
Brian N. Krulick - Smith CurrieIn today’s ever-changing legal and political climate, contractors are being forced to deal with events and circumstances that seemed improbable just a short time ago. These changing circumstances have led some contractors to question whether they are required to continue performing in the face of uncertainty and, in many cases, potentially large losses. The doctrines of impossibility and impracticability, if proven, can serve as powerful defenses and excuse performance of a construction contract. However, contractors should exercise great caution before relying on these defenses as an excuse for nonperformance, as the consequences of stopping work without proper justification can be disastrous.
Read the court decisionRead the full story...Reprinted courtesy of
Brian N. Krulick, Smith CurrieMr. Krulick may be contacted at
bnkrulick@smithcurrie.com
General Indemnity Agreement Can Come Back to Bite You
October 21, 2019 —
Christopher G. Hill - Construction Law MusingsI talk about payment bonds often here at Construction Law Musings. I talk a bit less about performance bonds and even less about the General Indemnity Agreements (GIA) that are signed by companies and their principals as part of the agreement between a construction company and its bonding company for the provision of these bonds. However, this does not mean that these GIA’s are not important. In fact, these are the agreements that allow a bonding provider to recoup any money paid out pursuant to either a payment or performance bond.
A 2018 case illustrates their importance. In Allegheny Cas. Co. v. River City Roofing, LLC, the Court considered a claim by Allegheny seeking both specific performance of the collateral agreement and reimbursement of certain expenses and investigative costs expended by Allegheny pursuant to its performance bond. Allegheny sought to be reimbursed for certain payments for siding work, investigative costs, and costs spent enforcing the GIA. Allegheny further sought to force the defendants to post sufficient collateral. To do so, Allegheny sued in the Eastern District of Virginia and then moved for summary judgment stating that the GAI uneuivocally required such a result due to the good faith payment for the siding work and the plain language of the GIA.
In response, the Defendants, River City Roofing and its principals that had personally guaranteed the indemnity, argued that the GIA did not apply to the siding work because only the roofing contract was subject to the performance bond and that any bond claims for which collateral was demanded were inchoate and therefore not proper for specific performance.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Revel Closing Shows Gambling Is No Sure Thing for Renewal
September 03, 2014 —
Christopher Palmeri – BloombergThe Revel Casino Hotel was envisioned as a playground for Wall Streeters who hated flying to Las Vegas. Instead, it’s become a money pit for the banks and money managers who spearheaded the New Jersey project, and the losses will keep coming even after closing today.
The Atlantic City resort, built at a cost of $2.4 billion, ceased operations after two bankruptcies and a 10-month search for a buyer. Barring a sale, the new owners may be Wells Fargo & Co. and JPMorgan Chase & Co., which provided $125 million in court-approved funding. Previous backers also included Capital Group Cos., the third-largest manager of U.S. mutual funds, and Morgan Stanley, the original investor.
The resort fell prey to poor timing, bad design and a misreading of the local market. The Revel saga shows what can go wrong when bankers stray from what they know, according to Charles Geisst, a professor of finance at Manhattan College in New York and author of the book “Wall Street: A History.”
Read the court decisionRead the full story...Reprinted courtesy of
Christopher Palmeri, BloombergMr. Palmeri may be contacted at
cpalmeri1@bloomberg.net
U.K. Developer Pledges Building Safety in Wake of Grenfell
April 19, 2022 —
Ryan Hesketh - BloombergCrest Nicholson Plc intends to sign the building safety pledge set up in the aftermath of the Grenfell fire in 2017 to improve standards that may cost the U.K. developer as much as 120 million pounds ($157 million).
The company’s best estimate of further liability as a result of the pledge would be 80 million pounds to 120 million pounds, according to a statement Tuesday. Since 2019, Crest Nicholson has recorded 47.8 million pounds of net charges from obligations imposed after the fire at Grenfell Tower in London in which flammable cladding materials contributed to the deaths of 72 people.
The Secretary of State for the Department for Levelling Up, Housing and Communities announced in January the government’s intention to increase the legal obligation on developers to fix potentially dangerous buildings. Since then, Crest Nicholson has engaged in “intensive dialogue” with the government about the new guidelines, resulting in the decision to sign the pledge, the firm said in the statement.
The new restrictions will be enacted in law through proposed amendments to the Building Safety Bill that is currently passing through parliament. Crest Nicholson is currently considering whether any further regulatory approvals are required in respect of the proposed laws, according to the statement.
Read the court decisionRead the full story...Reprinted courtesy of
Ryan Hesketh, Bloomberg