How Will Today’s Pandemic Impact Tomorrow’s Construction Contracts?
October 26, 2020 —
Levi W. Barrett, Nathan A. Cohen & Mark A. Snyder - Peckar & AbramsonThe emergence of COVID-19 has created a new set of challenges in the already complex world of negotiating construction contracts. In the pre-COVID-19 era, general contractors, construction managers and those negotiating on their behalf, needed to balance a variety of fairly well-established legal risks and exposures and commercial realities with the need to maintain a positive relationship with their counterparty. While many are rightfully concerned with addressing the impacts of COVID-19 to their on-going projects, those negotiating new contracts now are undoubtedly cognizant that they are negotiating in the midst of an unpredictable future that is tipping the historical negotiating balance. The following presents some crucial areas to focus on when negotiating and drafting your contracts in this new era.
Contract Terms Through the COVID-19 Lens
Contractors should examine proposed new contracts carefully to identify rights that afford COVID-19 protections and identify contractual obligations that create COVID-19 commercial risks.
Specific attention should be paid to those sections relating to force majeure/excusable delay, emergencies, changes (including changes in law), contingency, suspension and termination, site investigation as well as all representations and warranties. The paramount concern in examining these provisions is to ensure that they not only entitle the contractor to relief for those unknown events, emergencies and changes, but that they also contain sufficient entitlement for the contractor to obtain both time extensions and financial compensation for unknown impacts of a known event – the COVID-19 pandemic.
Reprinted courtesy of
Levi W. Barrett, Peckar & Abramson, P.C.,
Nathan A. Cohen, Peckar & Abramson, P.C.and
Mark A. Snyder, Peckar & Abramson, P.C.
Mr. Barrett may be contacted at lbarrett@pecklaw.com
Mr. Cohen may be contacted at ncohen@pecklaw.com
Mr. Snyder may be contacted at msnyder@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Don’t Waive Too Much In Your Mechanic’s Lien Waiver
December 22, 2019 —
Christopher G. Hill - Construction Law MusingsIn the past few years, the Virginia General Assembly has, with certain caveats, precluded pre-furnishing waiver of mechanic’s lien rights. While this essentially outlawed the types of mechanic’s lien waiver clauses that pervaded construction contracts in Virginia, the key to the previous sentence is “pre-furnishing.” What the General Assembly left intact were the usual waivers of mechanic’s lien rights typically required to be provided to Owners and others in the payment chain in exchange for payment.
These lien waivers come in a few “flavors” from conditional to unconditional, partial to full. Their terms usually include an acknowledgement of receipt of payment (we’ll get to this later), and a statement that the one seeking payment knows of no possible claims by lower tier subcontractors and then waives all mechanic’s lien rights against the property for work performed and included in the request for payment. Often over my years as a Virginia construction attorney, I have noticed that these waivers are often signed without comment or review. They are just part of the process and more often than not are not even an issue for most projects. Of course, if they are an issue they can be a big one, and their terms can come back to bite a claimant that has not properly vetted them.
The first potential issue is waiving lien rights while acknowledging receipt prior to actual receipt of the check or wire. Many of the waiver forms that are out there list a payment amount, or possibly simply state that the waiver is in exchange for some small payment, and then state “receipt of which is acknolwedged” or something similar. The issue here is that receipt may not have happened yet because these lien waivers are submitted as part of the payment package in order to get paid in the first place. In short, should you sign the waiver prior to payment, you may have acknowledged a non-event and in the event of non-payment have a written document stating that you waived your claim to a lien for that money. What a court would do with this, I am unsure, but why risk it? My advice, be sure your waiver is contingent on actual clearance of payment as well as receipt.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Takeaways From Schedule-Based Dispute Between General Contractor and Subcontractor
September 09, 2024 —
David Adelstein - Florida Construction Legal UpdatesA recent opinion out of the Southern District of Florida, Berkley Insurance Co. v. Suffolk Construction Co., Case 1:19-cv-23059-KMW (S.D.Fla. July 22, 2024), provides valuable takeaways on schedule-based disputes between a general contractor and subcontractor on a high-rise project.
In a nutshell, the general contractor’s original project schedule was abandoned due to project delays and the project wasn’t being built by any updated project schedule. The subcontractor claimed the general contractor was mismanaging the schedule putting unreasonable manpower and supervision constraints on it, i.e., it was working inefficiently. A bench trial was conducted and the Court found in favor of the subcontractor’s arguments. The Court found the general contractor had unrelated delays and that work activities were no longer methodical but, simply, piecemeal demands. The Court also rejected any inadequate manpower arguments finding the subcontract did not place any manpower requirements on the subcontractor.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Despite Health Concerns, Judge Reaffirms Sentence for Disbarred Las Vegas Attorney
October 02, 2015 —
Beverley BevenFlorez-CDJ STAFFThe Las Vegas Review-Journal reported that the “life-threatening health and custody status of disbarred Las Vegas attorney Barry Levinson remained uncertain Thursday after a judge refused to reconsider his harsh prison sentence.” Levinson had been convicted of defrauding homeowners associations.
Brent Bryson, Levinson’s attorney, claims that the stress of custody issues has caused health problems for his client, reported the Las Vegas Review-Journal. Bryan stated that “Levinson had heart failure while in federal custody and needs either a special heart valve operation in Southern California or a heart transplant to survive.”
District Judge Michael Villani suggested that Bryson should file a civil suit for the matter.
Read the court decisionRead the full story...Reprinted courtesy of
Court Concludes That COVID-19 Losses Can Qualify as “Direct Physical Loss”
September 28, 2020 —
Lorelie S. Masters & Jorge R. Aviles - Hunton Andrews KurthIn a victory for policyholders, a federal district court found that COVID-19 can cause physical loss under business-interruption policies. In Studio 417, Inc., et al. v. The Cincinnati Insurance Co., No. 20-cv-03127-SRB (W.D. Mo. Aug. 12, 2020), the court rejected the argument often advanced by insurers that “all-risks” property insurance policies require a physical, structural alteration to trigger coverage. This decision shows that, with correct application of policy-interpretation principles and strategic use of pleading and evidence, policyholders can defeat the insurance industry’s “party line” arguments that business-interruption insurance somehow cannot apply to pay for the unprecedented losses businesses are experiencing from COVID-19, public-safety orders, loss of use of business assets, and other governmental edicts.
The policyholders in Studio 417 operate hair salons and restaurants asserting claims for business interruption. In suing to enforce their coverage, the policyholders allege that, over the last several months, it is likely that customers, employees, and/or other visitors to the insured properties were infected with COVID-19 and thereby infected the insured properties with the virus. Their complaint asserts that the presence of COVID-19 “renders physical property in their vicinity unsafe and unusable.” Unlike some other complaints seeking to enforce such coverage, it also alleges that the presence of COVID-19 and government “Closure Orders” “caused a direct physical loss or direct physical damage” to their premises “by denying use of and damaging the covered property, and by causing a necessary suspension of operations during a period of restoration.”
Reprinted courtesy of
Lorelie S. Masters, Hunton Andrews Kurth and
Jorge R. Aviles, Hunton Andrews Kurth
Ms. Masters may be contacted at lmasters@HuntonAK.com
Mr. Aviles may be contacted at javiles@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Burden to Prove Exception to Exclusion Falls on Insured
April 19, 2022 —
Tred R. Eyerly - Insurance Law HawaiiIn a dispute between two insurers, the Ninth Circuit relied upon Nevada law in finding that the burden of proving that an exception to the exclusion applies was on the insured. Zurich Am. Ins. Co. v. Ironshore Specialty Ins. Co., 2022 U.S. App. LEXIS 1626 (9th Cir. Jan. 20, 2022).
Ironshore insured seven subcontractors. The policy included an exclusion providing there was no coverage for any property damage for the subcontractors' for "work performed prior to the policy inception." An exception to the exclusion provided that the exclusion did not apply to property damage that was "sudden and accidental and takes place within the policy period."
The seven subcontractors were sued for work they had performed. Zurich defended and indemnified the subcontractors. Zurich then sued Ironshore seeking contribution and indemnification for defense and settlement costs. The parties stipulated that all construction work at issue had been completed before the inception of Ironshore's policy and that none of the complaints against the subcontractors alleged that sudden and accidental damage had occurred after the inception of Ironshore's policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Colorado Supreme Court Issues Decisions on Statute of Limitations for Statutory Bad Faith Claims and the Implied Waiver of Attorney-Client Privilege
July 11, 2018 —
Jennifer Arnett-Roehrich - Gordon & Rees Insurance Coverage Law BlogThe Colorado Supreme Court has been busy the past two weeks, issuing a couple rulings that should be of interest to the insurance industry:
Statute of Limitations for Bad Faith Statute: In Rooftop Restoration, Inc. v. American Family Mutual Insurance Co., 2018 CO 44 (May 29, 2018), the Colorado Supreme Court held that the one-year statute of limitations that applies to penalties, does not apply to claims brought under C.R.S. 10-3-1116, Colorado’s statutory cause of action for unreasonable delay or denial of benefits. Section 10-3-1116 provides that a first-party claimant whose claim for payment of benefits has been unreasonably delayed or denied may seek to recover attorney fees, costs, and two times the covered benefit, in addition to the covered benefit. A separate Colorado statute, CRS 13-80-103(1)(d) provides a one-year statute of limitations for “any penalty or forfeiture of any penal statutes.” To arrive at the conclusion that the double damages available under section 10-3-1116 is not a penalty, the Court looked at yet another statutory provision, governing accrual of causes of action for penalties, which provides that a penalty cause of action accrues when “the determination of overpayment or delinquency . . . is no longer subject to appeal.” The Court stated that because a cause of action under 10-3-1116 “never leads to a determination of overpayment or delinquency . . . the claim would never accrue, and the statute of limitations would be rendered meaningless.” Para. 15. Presumably, the default two-year statute of limitations, provided by CRS 13-80-102(1)(i), will now be found to apply to causes of action seeking damages for undue delay or denial of insurance benefits.
Read the court decisionRead the full story...Reprinted courtesy of
Jennifer Arnett-Roehrich, Gordon & Rees Scully MansukhaniMs. Arnett-Roehrich may be contacted at
jarnett-roehrich@grsm.com
Real Estate & Construction News Roundup (4/10/24) – Hotels Integrate AI, Baby-Boomers Stay Put, and Insurance Affects Housing Market
May 06, 2024 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, DOT’s major grant programs, proptech’s solution to climate change risks, mortgage-locked sellers put their homes on the market, and more!
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team