Spa High-Rise Residents Frustrated by Construction Defects
February 07, 2013 —
CDJ STAFFIs this part of the spa treatment? A couple has sued over problems at Miraval Living, a luxury high-rise on the East Side of Manhattan. There was supposed to be ballroom dancing, culinary classes, and yoga. Anthony Argyrides's lawsuit notes that those didn't materialize. What they did get, he claims, was faulty plumbing, crumbling fixtures, and defective floor tiles. Mr. Argyrides claims that his front door "spontaneously fell of its hinges and nearly hit FiOS installation workers."
Meanwhile, building management has ended their agreement with Miraval and need to find someone else to operate the building's spa. Argyrides and his fellow building residents might need something more than a few deep calming breaths. He's suing for $5.5 million.
Read the court decisionRead the full story...Reprinted courtesy of
Pa. Contractor Pleads No Contest to Prevailing-Wage Charges, Pays Workers $20.7M
September 20, 2021 —
Tom Ichniowski - Engineering News-RecordPennsylvania construction contractor Glenn O. Hawbaker Inc. has pleaded no contest to counts of theft of worker pay—in alleged violation of state prevailing-wage laws—and will pay 1,267 workers restitution of $20.7 million in unpaid wages, Pennsylvania Attorney General Josh Shapiro said.
The company entered its plea to four felony counts of “theft by failure to make required disposition of funds received” on Aug. 3 before President Judge Pamela A. Ruest of the Centre County Court of Common Pleas in Bellefonte, Pa.
Reprinted courtesy of
Tom Ichniowski, Engineering News-Record
Mr. Ichniowski may be contacted at ichniowskit@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Paul Tetzloff Elected As Newmeyer & Dillion Managing Partner
June 03, 2019 —
Newmeyer & Dillion LLPNewmeyer & Dillion LLP, a prominent business and real estate law firm, selected Paul Tetzloff as the firm's Managing Partner. His term began on January 1, 2019. A business litigator, Tetzloff will now oversee the firm's strategic plan and manage the firm's day-to-day business affairs.
"The Firm is incredibly fortunate to have Paul stepping into the role as Managing Partner. His energy, intelligence, leadership, and drive make him uniquely qualified to lead this Firm for years to come," said former Managing Partner Jeff Dennis. "I am excited to watch where the Firm is headed – we have such an amazing opportunity to continue to develop to even greater heights, and Paul will be a huge part of making that happen."
Active in his community, Tetzloff sits on the board for HomeAid Orange County and the Marine Raider Association.
Tetzloff is succeeding Dennis, who served in the role from 2012 to 2018. "Jeff was our managing partner for seven years and he did an outstanding job. We owe Jeff a debt of gratitude for his service," said Tetzloff of his predecessor. "I'm looking forward to continuing to build on the groundwork laid to help the firm reach new levels in the years to come."
Dennis' leadership allowed the firm to grow substantially under his tenure, including opening a Las Vegas, Nevada office and establishing thriving practice areas throughout various industries. Dennis will focus his energy on overseeing the firm's growing Privacy and Data Security practice.
Paul Tetzloff
paul.tetzloff@ndlf.com
Practice Areas
Business Litigation
Construction Litigation
Real Estate Litigation
About Newmeyer & Dillion
For almost 35 years, Newmeyer & Dillion has delivered creative and outstanding legal solutions and trial results for a wide array of clients. With over 70 attorneys practicing in all aspects of business, employment, real estate, privacy & data security and insurance law, Newmeyer & Dillion delivers legal services tailored to meet each client's needs. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer & Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949.854.7000 or visit www.ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
Blockbuster Breakwater: Alternative Construction Method Put to the Test in Tampa Bay
August 14, 2023 —
Scott Judy - Engineering News-RecordOn June 7, 2023, Tampa Bay news reporters trekked to the Sunshine Skyway bridge for a Florida Dept. of Transportation press conference that would explain the mystery behind the hundreds of curiously shaped concrete structures lining nearly the entire length of the span’s mile-plus-long south fishing pier access road.
Reprinted courtesy of
Scott Judy, Engineering News-Record
Mr. Judy may be contacted at judys@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Seller Cannot Compel Arbitration for Its Role in Construction Defect Case<
March 01, 2012 —
CDJ STAFFThe buyer of a leaky home in Venice, California cannot be compelled to arbitration with the seller in a construction defect lawsuit, according to a decision in Lindemann v. Hume, which was heard in the California Court of Appeals. Lindemann was the trustee of the Schlei Trust which bought the home and then sued the seller and the builder for construction defects.
The initial owner was the Hancock Park Trust, a real estate trust for Nicholas Cage. Richard Hume was the trustee. In 2002, Cage agreed to buy the home which was being built by the Lee Group. Cage transferred the agreement to the Hancock Park Trust. Hancock had Richard Nazarin, a general contractor, conduct a pre-closing walk through. They also engaged an inspector. Before escrow closed, the Lee Group agreed to provide a ten-year warranty “to remedy and repair any and all damage resulting from water infiltration, intrusion, or flooding due to the fact that the door on the second and third floors of the residence at the Property were not originally installed at least one-half inch (1/2”) to one inch (1”) above the adjacent outside patio tile/floor on each of the second and third floors.”
Cage moved in and experienced water intrusion and flooding. The Lee Group was unable to fix the problems. Hume listed the home for sale. The Kamienowiczs went as far as escrow before backing out of the purchase over concerns about water, after the seller’s agent disclosed “a problem with the drainage system that is currently being addressed by the Lee Group.”
The house was subsequently bought by the Schlei Trust. The purchase agreement included an arbitration clause which included an agreement that “any dispute or claim in Law or equity arising between them out of this Agreement or any resulting transaction, which is not settled through mediation, shall be decided by neutral, binding arbitration.” The warranty the Lee Group had given to Hancock was transferred to the Schlei trust and Mr. Schlei moved into the home in May 2003.
Lindemann enquired as to whether the work done would prevent future flooding. Nazarin sent Schlei a letter that said that measures had been taken “to prevent that situation from recurring.” In February, 2004, there was flooding and water intrusion. Lindemann filed a lawsuit against the Lee Group and then added the Hancock Park defendants.
The Hancock Park defendants invoked the arbitration clause, arguing that Lindemann’s claims “were only tangentially related to her construction defect causes of action against the Lee Group.” On June 9, 2010, the trial court rejected this claim, ruling that there was a possibility of conflicting rulings on common issues of law. “With respect to both the developer defendants and the seller defendants, the threshold issue is whether there was a problem with the construction of the property in the first instance. If there was no problem with the construction of the property, then there was nothing to fail to disclose.” Later in the ruling, the trial court noted that “the jury could find there was no construction defect on the property, while the arbitration finds there was a construction defect, the sellers knew about it, and the sellers failed to disclose it.” The appeals court noted that while Hancock Park had disclosed the drainage problems to the Kamienowiczs, no such disclosure was made to Sclei.
The appeals court described Hancock Park’s argument that there is no risk of inconsistent rulings as “without merit.” The appeals court said that the issue “is not whether inconsistent rulings are inevitable but whether they are possible if arbitration is ordered.” Further, the court noted that “the Hancock Park defendants and the Lee Group have filed cross-complaints for indemnification against each other, further increasing the risk of inconsistent rulings.”
The court found for Lindemann, awarding her costs.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
New WOTUS Rule
November 13, 2023 —
David R. Cook Jr. - Autry, Hall & Cook, LLPThe U.S. Army Corps of Engineers amended the regulation to conform the definition of “waters of the United States” to conform to the Supreme Court’s ruling in
Sackett v. Environmental Protection Agency. See the prior blog post about the Supreme Court’s ruling:
Sackett v. Environmental Protection Agency – Construction and Utility Law | Atlanta | AHC Law
Federal Register :: Revised Definition of “Waters of the United States”; Conforming
Reprinted courtesy of
David R. Cook Jr., Autry, Hall & Cook, LLP
Mr. Cook may be contacted at cook@ahclaw.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Fannie Overseer Moves to Rescue Housing With Lower Risk to Lenders
May 21, 2014 —
Kathleen M. Howley – BloombergMelvin Watt, the overseer of Fannie Mae and Freddie Mac, broke five months of silence to help boost lending as slowing sales threatens the housing recovery.
Watt, 68, in his first speech as director of the Federal Housing Finance Agency, announced new rules to reduce the risk that lenders will have to repurchase bad mortgages. The changes, designed to allow banks to relax credit standards, probably will increase housing sales by 5 percent this year, said Stephanie Karol, an economist at Englewood, Colorado-based research firm IHS Inc.
“It means a restart for the real estate recovery,” said Mark Zandi, chief economist of Moody’s Analytics Inc. “We’re not going to get back on track until we start making credit more available to potential buyers.” He said he expects Watt’s moves to spur “meaningful” sales growth.
Read the court decisionRead the full story...Reprinted courtesy of
Kathleen M. Howley, BloombergMs. Howley may be contacted at
kmhowley@bloomberg.net
California Federal Court Finds a Breach of Contract Exclusion in a CGL Policy Bars All Coverage for a Construction Defect Action
July 19, 2021 —
Robert Dennison - Traub LiebermanThe Southern District of California published a decision in May 2021 in Associated Industries Ins. Co. v. Mt. Hawley Ins. Co., 2021 WL 1921016 (S.D. Cal. 5/12/21) concerning the scope of a breach of contract exclusion in a general liability insurance policy as applied to a construction defect action.
The suit was filed by Associated Industries Insurance Company against Mt. Hawley Insurance Company for equitable contribution for amounts spent to defend and indemnify the parties co-insured, referred to as JGCI in the decision. JGCI agreed to build a building for a third party pursuant to a written construction contract. The City of Davis issued a certificate of occupancy for the building on May 6, 2005. The City’s permits stated the building was final on that date. Mt. Hawley issued the first of several annual general liability insurance policies in September 2005.
Read the court decisionRead the full story...Reprinted courtesy of
Robert Dennison, Traub LiebermanMr. Dennison may be contacted at
rdennison@tlsslaw.com