The Colorado Court of Appeals Rules that a Statutory Notice of Claim Triggers an Insurer’s Duty to Defend.
October 23, 2012 —
David M. McLain, Higgins, Hopkins, McLain & RoswellGene and Diane Melssen d/b/a Melssen Construction (“Melssen”) built a custom home for the Holleys, during which period of time Melssen retained a CGL insurance coverage from Auto Owners Insurance Company. Soon after completion of the house, the Holleys noticed cracks in the drywall and, eventually, large cracks developed in the exterior stucco and basement slab. Thereafter, the Holleys contacted Melssen, the structural engineer, an attorney, and Auto-Owners, which assigned a claims adjuster to investigate the claim.
In April 2008, the Holleys sent Melssen a statutory notice of claim pursuant to C.R.S. § 13-20-803.5 (“NOC”). In this NOC, the Holleys claimed approximately $300,000 in damages related to design and construction defects. The Holleys also provided a list of claimed damages and estimated repairs, accompanied by two reports from the Holleys’ consultant regarding the claimed design and construction defects. In June 2008, Melssen tendered the defense and indemnity of the claim to Auto-Owners. While Auto-Owners did not deny the claim at that time, it did not inspect the property or otherwise adjust the claim. Thereafter, in October 2008, Auto-Owners sent Melssen a letter denying coverage on the basis that the damage occurred outside of the applicable policy period.
Ultimately, Melssen settled the claims against it for $140,000.
Read the full story…
Reprinted courtesy of David McLain, Higgins, Hopkins, McLain & Roswell, LLC. Mr. McLain can be contacted at mclain@hhmrlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Alleging Property Damage in Construction Defect Lawsuit
September 14, 2020 —
David Adelstein - Florida Construction Legal UpdatesWhen there is a construction defect lawsuit, there is an insurance coverage issue or consideration. As I have said repeatedly in other articles, it is all about maximizing insurance coverage regardless of whether you are the plaintiff prosecuting the construction defect claim or the contractor(s) alleged to have committed the construction defect and property damage. It is about triggering first, the insurer’s duty to defend, and second, the insurer’s duty to indemnify its insured for the property damage.
The construction defect claim and lawsuit begins with how the claim and, then, lawsuit is couched knowing that the duty to defend is triggered by allegations in the lawsuit (complaint). Thus, preparing the lawsuit (complaint) is vital to maximize the insurer’s duty to defend its insured.
In a recent opinion out of the Eleventh Circuit, Southern-Owners Ins. Co. v. MAC Contractors of Florida, LLC, 2020 WL 4345199 (11th Cir. 2020), a general contractor was sued for construction defects in the construction of a custom home. A dispute arose pre-completion and the owner hired another contractor to complete the house and remediate construction defects. The contractor’s CGL insurer originally provided a defense to the general contractor but then withdrew the defense and filed an action for declaratory relief asking for the declaration that it had no duty to defend the contractor because the underlying lawsuit did NOT allege property damage. The trial court agreed with the contractor and granted summary judgment in its favor finding that the underlying complaint did not allege property damage beyond defective work. But, on appeal, the Eleventh Circuit reversed.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Contract Change # 10: Differing Site Conditions (law note)
March 28, 2018 —
Melissa Dewey Brumback - Construction Law in North CarolinaPreviously, the A201 required a Contractor to provide notice to the Owner and Architect within 21 days after discovery of unforeseen site conditions. This notification is required prior to the conditions being disturbed, so as to allow the Design Team the ability to evaluate the site and determine the compensability of any such differing conditions.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North Carolina
Renters Trading Size for Frills Fuel U.S. Apartment Boom
July 16, 2014 —
Prashant Gopal – BloombergKatie Graham is living large. Just in a small apartment.
She moved into the new ParkCentral tower in Nashville, Tennessee, for its gym, rooftop deck with heated pool, and the bars and restaurants in the neighborhood below. She didn’t mind the size of the 562-square-foot (52-square-meter) studio.
“I just wanted to be in a good area and wanted good amenities, so I wasn’t looking for something huge,” said Graham, 25, who relocated from her hometown in Jackson, Tennessee, two hours away. “I’m by myself and don’t need all that. The bigger the area, the more furniture you have to buy.”
Young professionals are paying top-market rents to live in new upscale apartment towers sprouting in Nashville and other downtowns across the country. They’re sacrificing living space for a prime urban location and extras such as cooking classes, dog-wash stations and poolside Wi-Fi. Developers, in the biggest U.S. apartment-construction boom in almost a decade, are shrinking the size of units so they can command luxury rates without narrowing the pool of potential tenants.
Read the court decisionRead the full story...Reprinted courtesy of
Prashant Gopal, BloombergMr. Gopal may be contacted at
pgopal2@bloomberg.net
Candis Jones Named to Atlanta Magazine’s 2022 “Atlanta 500” List
February 14, 2022 —
Candis Jones - Lewis Brisbois NewsroomAtlanta, Ga. (February 11, 2022) - Atlanta Partner Candis R. Jones has been named to Atlanta Magazine’s 2022 “Atlanta 500” list of the most powerful business leaders in Atlanta. This is the second year in a row she has received this recognition.
To compile this list, the publication reviewed nominations from the public and consulted experts across various sectors. The magazine’s editors and writers considered not only the status of the nominees within their respective organizations, but also whether the nominees were visionary by, for example, leading programs for their communities or creating opportunities for employees.
Read the court decisionRead the full story...Reprinted courtesy of
Candis Jones, Lewis BrisboisMs. Jones may be contacted at
Candis.Jones@lewisbrisbois.com
Be Careful How You Terminate: Terminating for Convenience May Limit Your Future Rights
January 19, 2017 —
Brett M. Hill - Ahlers & Cressman, PLLC BlogMany construction contracts contain a termination clause that allows a contractor to be terminated either for convenience or for cause. Termination for convenience and termination for cause clauses have been discussed previously on the blog
here,
here and
here. The distinction between a termination for convenience or for cause is an important one.
If a contractor is terminated for convenience, the rights of the party who has terminated the contractor for convenience could be limited in the future. This is specifically true as to any defects in the terminated contractor’s work that are discovered after the termination for convenience.
This issue was addressed in an Oregon Court of Appeals case where a general contractor attempted to recover costs incurred in correcting a terminated subcontractor’s work after the subcontractor was terminated for convenience. Shelter Prods. v. Steel Wood Constr., Inc., 257 Or. App 382 (2013). In that case, the subcontractor sued the general contractor for its termination expenses. The general contractor asserted an offset/backcharge claim for damages incurred by the general contractor in correcting the subcontractor’s defective work. The general contractor had incurred the costs after it had terminated the subcontractor. The general contractor did not notify the subcontractor that its work was defective and did not give the subcontractor an opportunity to cure before the repairs were completed.
Read the court decisionRead the full story...Reprinted courtesy of
Brett M. Hill, Ahlers & Cressman, PLLCMr. Hill may be contacted at
bhill@ac-lawyers.com
Washington Court Limits Lien Rights of Construction Managers
August 17, 2011 —
Douglas Reiser, Builders Council BlogA newly filed, yet unpublished, court opinion opines that a construction manager cannot file a construction lien in Washington state. So, how far reaching is this opinion?
In the case of Blue Diamond Group Inc. v. KB Seattle 1, Inc., et al, a New York construction manager filed a lien against the Westfield Southcenter Mall in Tukwila, Washington. The lien was filed after the owner of a coffee stand failed to pay Blue Diamond for consulting services used in the construction of a kiosk.
Blue Diamond served as the owner’s agent, assisting with managing subcontractors, vendors and other tasks. The manager’s tasks also included paying invoices, managing deliveries, setting schedules and other site managerial tasks. Blue Diamond was not registered as a contractor under Washington’s RCW 18.27.
Read the full story…
Read the court’s decision…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Read the court decisionRead the full story...Reprinted courtesy of
Expansion of Statutes of Limitations and Repose in K-12 and Municipal Construction Contracts
March 27, 2019 —
Henry Bangert - Colorado Construction LitigationThe purpose of this whitepaper is to bring attention to a trend in K-12 and municipal construction contracts, which expands the time periods for law suits against construction professionals.
Introduction and Background
Under Colorado statute, the period of time within which a legal action for construction defects may be brought against a construction professional in Colorado is two years from when the claimant (or its predecessor in interest) discovers or in the exercise of reasonable diligence should have discovered the physical manifestations of a defect (the “Statute of Limitations”), but in no case may an action be brought more than six years after substantial completion of the improvement, unless the claim arises in the fifth or sixth year after substantial completion, in which event the action may be brought within two years of such date, i.e., up to eight years after substantial completion (the “Statute of Repose”). See C.R.S. § 13-80-104. While the triggering events differ for the Statute of Limitations and Statue of Repose, the periods are intended to run concurrently to limit the period of time an action may be brought against construction professionals for construction defects to, at most, eight years after substantial completion. Importantly, these limitations periods may be expanded by agreement.
Prior to 1986, Colorado law provided for a 10-year Statute of Repose. However, in 1986, Colorado’s legislature shortened the Statute of Repose time limit to the current six (or up to eight) year period. In 1986, Colorado also redefined the date the claim arises from the date the defect was discovered or should have been discovered to the date the physical manifestation of a defect was discovered or should have been discovered. Therefore, after 1986, the two-year limitations period could begin to run when a claimant should have discovered the manifestation of a defect, even if the claimant did not recognize that a defect existed.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at