Gru Was Wrong About the Money: Court Concludes that Lender Owes Contractor “Contractually, Factually and Practically”
November 07, 2022 —
Matthew DeVries - Best Practices Construction LawThis weekend was all about
The Rise of Gru. I love Gru so much that when my children ask for money, my best Gru-like voice belts back: “Now, I know there have been some rumors going around that the bank is no longer funding us….In terms of money, we have no money.” And that’s precisely what many lenders say on distressed projects when the owner fails to make final payment and the contractor looks to the bank for funding: “We have no money for you contractor!”
In
BCD Associates., LLC v. Crown Bank, CA No. N15c-11-062 (Super. Ct. Del, May 2, 2022), the trial court found that when a bank pays a contractor directly, it can create a legally binding relationship subject to the terms of the construction loan agreements with the owner.
The project involved a $13m construction loan between the lender and the owner to renovate a hotel. The owner and contractor entered into an AIA Contract for the construction management services. During construction the contractor would submit payment applications to the lender, who would review and approve the invoices for payment. The lender then would pay 90% of the approved payment application and hold back the remaining 10% as retainage. The contractor was supposed to be paid the final retainage upon completion, which it did not receive in accordance with the terms of the AIA Contract.
Read the court decisionRead the full story...Reprinted courtesy of
Matthew DeVries, Burr & Forman LLPMr. DeVries may be contacted at
mdevries@burr.com
Seventh Circuit Confirms Additional Insured's Coverage for Alleged Construction Defects
August 10, 2017 —
Tred R. Eyerly - Insurance Law HawaiiThe Seventh Circuit held that the underlying complaint alleged an occurrence by asserting that the painting subcontractor was negligent in causing damage to the building. Westfield Ins. Co. v. Nat'l Decorating Serv., Inc., 2017 U.S. App. LEXIS 12516 (7th Cir. July 13, 2017).
McHugh Construction, the general contractor for construction of a 24 story condominium building in Chicago, retained National Decorating Service, Inc. as a subcontractor to perform all of the painting work. This meant National Decorating would paint the exterior of the building with a protective coating that was a waterproof sealant.
After completion, the building's board of managers sued McHugh, National Decorating, and others for damages resulting from faulty workmanship. The third amended complaint alleged: (1) significant cracking of the exterior concrete walls, interior walls, and ceilings; (2) significant leakage through the exterior concrete walls, balconies, and windows; (3) defects to the common elements of the building; and (4) damage to the interior ceilings, floors, interior painting, drywall, and furniture in the units.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly - Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Exculpatory Provisions in Business Contracts
May 30, 2018 —
David Adelstein - Florida Construction Legal UpdatesAn exculpatory provision in a contract is a provision that relieves one party from liability for damages. It shifts the risk of an issue entirely to the other party. Such a provision is generally drafted by the party preparing the contract that is looking to eliminate or disclaim liability associated with a particular risk, oftentimes a risk within their control. These provisions are also known as limitation of liability provisions because they do exactly that — limit liability as to a risk. For this reason, they can be useful provisions based on the context of certain risks, and are provisions that are included in business contracts (such as construction contracts).
While such clauses are disfavored, they are enforceable if they are drafted clearly, unambiguously, and unequivocally. If they are unclear, ambiguous, or equivocal, they will construed against enforcement. See Obsessions In Time, Inc. v. Jewelry Exchange Venture, LLP, 43 Fla.L.Weekly D1033a (Fla. 3d DCA 2018) (finding exculpatory clause in lease ambiguous and, therefore, unenforceable as to lessor looking to benefit from the exculpatory clause).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Third Circuit Limits Pennsylvania’s Kvaerner Decision; Unexpected and Unintended Injury May Constitute an “Occurrence” Under Pennsylvania Law
December 22, 2019 —
Michael S. Levine & Michelle M. Spatz - Hunton Insurance Recovery BlogThe Third Circuit ruled on Friday that differing “occurrence” definitions can have materially different meanings in the context of whether product defect claims constitute an “occurrence” triggering coverage under general liability insurance policies. The Court held in Sapa Extrusions, Inc. v. Liberty Mutual Insurance Company, that product claims against Sapa may be covered under policies that define an “occurrence” as an accident resulting in bodily injury or property damage “neither expected nor intended from the standpoint of the insured.” However, the Court affirmed that coverage was not triggered under policies lacking the “expected” or “intended” limitation, reasoning that, under those policies, there was no question that the intentional manufacturing of Sapa’s product was too foreseeable to amount to an “accident.”
The coverage dispute arose from an underlying action in which Marvin, a window manufacturer, alleged that, between 2000 and 2010, Sapa sold it roughly 28 million defective aluminum window extrusions. Marvin alleged that the extrusions, which are metal frames that hold glass window panes in place, began to oxidize and break down shortly after they were installed, causing Marvin to incur substantial costs to fix and replace them.
Marvin sued Sapa in 2010 in Minnesota federal court, and the parties settled in 2013. Sapa sought coverage for the settlement from its eight general liability insurers for the period implicated by Marvin’s allegations. The insurers denied coverage and Sapa brought suit in the Middle District of Pennsylvania.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Michelle M. Spatz, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Ms. Spatz may be contacted at mspatz@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Depreciating Labor Costs May be Factor in Actual Cash Value
April 20, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe Minnesota Supreme Court considered a certified question from the the U.S. District Court regarding consideration of depreciating labor costs in determining the actual cash value of a loss. Wilcox v. State Farm Fire & Cas. Co., 2016 Min. LEXIS 50 (Minn. Feb. 10, 2016).
The insureds' home was damaged by hail. State Farm provided a written estimate that calculated the actual cash value of the loss. To estimate the actual cash value of the damaged property, State Farm first calculated the replacement costs of individual items, such as roof flashing, siding, fascia, gutters, and window screens. Next, State Farm subtracted the pre-loss depreciation of some, but not all, individual items. For example, State Farm depreciated the cost of removing and replacing certain materials, such as siding. State Farm did not depreciate the cost of the new siding separately from the cost of the labor required to install the new siding on the home. Instead, State Farm calculated the removal and replacement of the siding as a single cost, then depreciated the removal-and-replacement cost as a whole. The cost of labor to repair or replace the damaged property was referred to by the court as "embedded labor costs."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Travelers Insurance Sues Chicago for $26M in Damages to Willis Tower
May 15, 2023 —
Annemarie Mannion - Engineering News-RecordTravelers Property Casualty Co. is suing the City of Chicago and its water district for $26 million in damages caused when more than 1 million gallons of Chicago River water flooded into a 110-story skyscraper during a 2020 storm.
Reprinted courtesy of
Annemarie Mannion, Engineering News-Record
Ms. Mannion may be contacted at manniona@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Jinx: Third Circuit Rules in Favor of Teamsters in Withdrawal Case
July 28, 2018 —
Wally Zimolong - Supplemental ConditionsBad omen. Last week, I wrote about a Appeals Court decision that affirmed a contractor’s escape from an over $600,000 withdrawal liability assessment from the Laborers Union. The next day the Third Circuit (which covers PA, NJ, and DE) handed down a decision affirming a federal court’s decision to assess withdraw liability. This one shows the dark side of not reading and understanding your CBA.
The belligerents in the litigation were, Penn Jersey, a construction material supplier, and Teamsters Local 676. Their collective bargaining agreement contained a clause purportedly covering withdrawal liability. Specifically, the clause stated “should the Employer withdraw from the Agreement in the future, there will be no withdrawal liability. The CBA expired and Penn Jersey did not renew its agreement with the Teamsters.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
Construction Litigation Roundup: “Just Hanging Around”
August 14, 2023 —
Daniel Lund III - LexologyA subcontractor asserting a payment bond claim for “standby” time for its equipment on the Cline Avenue bridge project (over Indiana Harbor and Ship Canal in East Chicago, Indiana) received pushback from the payment bond surety.
In fact, the duration of the standby time occurred after the surety’s principal, the general contractor, had been placed in default and terminated on the general contract. According to the surety: “After termination of the contract… it is impossible for labor, materials, and equipment to have been furnished for use in performing the terminated contract.” The surety filed a motion for summary judgment.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com