Be Proactive, Not Reactive, To Preserve Force Majeure Rights Regarding The Coronavirus
March 30, 2020 —
David Adelstein - Florida Construction Legal UpdatesIf you are involved in construction, NOW is the time to consider the potential force majeure impacts associated with the pandemic Coronavirus. Things are beginning to drastically change on a minute-by-minute basis. From travel restrictions, to the suspension or cancellation of events on an international level, to company-wide policies and restrictions, the global uncertainty has led to the possibility that a force majeure delay will occur. Thinking otherwise is not being proactive. The Coronavirus, and the impacts / delays associated therewith, is beyond anyone’s control. Due to the uncertainty, it is hard to fathom at this time a reasonable challenge to someone’s reaction to this concern or their companywide response to the concern.
If you are a contractor, subcontractor, or even a supplier, my suggestions would be as follows:
- Revisit your contracts and see what type of force majeure language it has – anything relating to delays beyond your control or epidemics;
- Examine to see whether you have a basis for additional compensation AND additional time;
- Examine what type of notice you are required to provide for force majeure events;
- Be proactive – send notice now of the potentiality that this pandemic can impact / delay the job –no one should take offense to this letter as this pandemic has impacted all walks of life;
- If an impact occurs, send follow-up notice accordingly to ensure rights under the contract are preserved; and
- For future contracts, incorporate language that specifically addresses epidemics and pandemics now that the occurrence of this issue has become real.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Ownership is Not a Conclusive Factor for Ongoing Operations Additional Insured Coverage
November 15, 2017 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn McMillin Management Services v. Financial Pacific Ins. Co. (No. D069814, filed 11/14/17), a California appeals court held that an insurer had a duty to defend a general contractor under an “ongoing operations” additional insured (AI) endorsement for damage occurring after the named insured subcontractor completed its work, because the endorsement did not limit coverage solely to liability during the subcontractors’ ongoing operations, but rather, broadly provided coverage for liability “arising out of” such operations.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Wildfire Insurance Coverage Series, Part 6: Ensuring Availability of Insurance and State Regulations
August 03, 2022 —
Scott P. DeVries & Yosef Itkin - Hunton Insurance Recovery BlogBecause of the potential exposure associated with wildfires, many insurers have attempted to withdraw from the property coverage market in various states. In this post in the Blog’s Wildfire Insurance Coverage Series, we discuss the challenges businesses and individuals face in obtaining wildfire insurance coverage, and the regulatory scheme that is intended to help them secure adequate coverage.
Given the increasing exposures associated with climate change, numerous insurers have sought to withdraw from the wildfire-related coverage market or increase rates to a level where they are effectively unavailable. States have been resistant to their doing so. As one commentator reports, “[e]ven where insurers have tried to withdraw policies or raise rates to reduce climate-related liabilities, state regulators have forced them to provide affordable coverage anyway, simply subsidizing the cost of underwriting such a risk policy or, in some cases, offering it themselves.” At least 30 states have developed regulation, referred to as “Fair Access to Insurance Requirements” (FAIR), to ensure the continued availability of insurance. The FAIR plan provides a channel to insurance for property owners who would be stuck without any reasonable access to insurance without state intervention.
Reprinted courtesy of
Scott P. DeVries, Hunton Andrews Kurth and
Yosef Itkin, Hunton Andrews Kurth
Mr. DeVries may be contacted at sdevries@HuntonAK.com
Mr. Itkin may be contacted at yitkin@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Thank You Once Again for the Legal Elite Election for 2022
December 18, 2022 —
Christopher G. Hill - Construction Law MusingsThank you once again to those in the Virginia legal community who elected me to the Virginia Business Legal Elite in the Construction Law category for the 16th consecutive year. The 16 consecutive years of election to the Legal Elite in the Construction Category span my time as a solo construction attorney. The fact that you all have continued to elect “100%” of the lawyers at The Law Office of Christopher G. Hill, PC for the last 12 years is most gratifying and only confirms that my decision to “go solo” over 12 years ago was a good one. To be included in this list of top construction attorneys is both humbling and gratifying. For the complete list of the Virginia construction lawyers that were elected along with me, see the
2022 Virginia Business Legal Elite in Construction Law.
So without further ado, thank you to all of you who voted for me. I truly appreciate your continued confidence and support of my construction law practice. Your yearly votes always prod me to learn and continually improve to meet your expectations and keep my practice at this high level. I also couldn’t do this without the great support from friends and family (not to mention clients), so my gratitude goes out to these great folks.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Expanded Virginia Court of Appeals Leads to Policyholder Relief
January 29, 2024 —
Michael S. Levine & Olivia G. Bushman - Hunton Insurance Recovery BlogExercising its newly expanded jurisdiction that now permits Virginia’s intermediate appellate courts to hear insurance coverage disputes, the Court of Appeals recently reversed a lower court decision that allowed a two-year “Suits Against Us” provision to serve as a basis for an insurer’s refusal to reimburse repair and replacement costs incurred more than two years after the date of loss. Bowman II v. State Farm Fire and Casualty Co., Record No. 1256-22-3 (Nov. 21, 2023). CAV (unpublished opinion).
In the proceeding below, the circuit court found no justiciable controversy and dismissed the complaint where repairs to the policyholder’s fire-damaged home continued more than two years after the date of the fire. The circuit court relied on a two-year limitation in the policy that governed the period within which the policyholder must bring suit against the insurer.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Olivia G. Bushman, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Ms. Bushman may be contacted at obushman@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Texas Jury Awards $5.3 Million to Company Defamed by Union: Could it work in Pennsylvania?
December 21, 2016 —
Wally Zimolong – Supplemental ConditionsIn early September a Texas jury awarded a janitorial $5.3 million against the local chapter of the SEIU. The janitorial firm claimed that the SEIU damaged its reputation and caused it damages when it spread false, defamatory, and disparaging stories about the firm. Specifically, the janitorial firm claimed that the SEIU told the janitorial firms customer and potential customers that the firm “systematically failed to pay its employees for all hours worked, instructed janitors to work off the clock and had fired, threatened or refused to hire janitors who supported joining a union.” According to Law360.com, the union did this with “fliers, handbills, letters, emails, newsletters, speeches and postings on its website accused [the firm] of violating wage-and-hour and other labor laws.”
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
Florida’s Statute of Limitations / Repose for Actions Founded on Construction Improvement Modified
April 25, 2023 —
David Adelstein - Florida Construction Legal UpdatesOn April 13, 2023, Florida’s all-important four-year statute of limitations–Florida Statute s. 95.11(3)(c)–relating to actions founded on construction of an improvement of real property was modified. This is a key statute of limitations for ALL construction practitioners because it also includes the statute of repose for latent construction defects.
At the bottom of this posting is the current version fo s. 95.11(3)(c) with the underlined section being recent additions. (They hyperlink above will identify the deletions and additions.) Important things to note:
- Statute of Repose. The statute of repose has been reduced from 10 years to 7 years. There is now an objective date for when the repose period commences: “within 7 years after the date the authority having jurisdiction issues a temporary certificate of occupancy, a certificate of occupancy, or a certificate of completion, or the date of abandonment of construction if not completed, whichever date is earliest.”
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Superintendent’s On-Site Supervision Compensable as Labor Under Miller Act
March 13, 2023 —
David Adelstein - Florida Construction Legal UpdatesA recent Miller Act payment bond decision out of the District of Columbia Circuit Court of Appeals, U.S. f/u/b/o Civil Construction, LLC v. Hirani Engineering & Land Surveying, PC, 58 F.4th 1250 (D.C. Circ. 2023), dealt with the issue of whether a subcontractor’s superintendent constitutes recoverable “labor” within the meaning of the Miller Act and compensable as a cost under the Miller Act that typically views labor as on-site physical labor.
The issue is that the Miller Act covers “[e]very person that has furnished labor or material in carrying out work provided for in a contract.” Civil Construction, supra, at 1253 quoting 40 U.S.C. s. 3133(b)(1). The Miller Act does not define labor. The subcontractor claimed labor includes actual superintending at the job site. The surety disagreed that a superintendent’s presence on a job site constitutes labor as the superintendent has to actually perform physical labor on the job site to constitute compensable labor under the Miller Act.
The subcontractor argued its subcontract and the government’s quality control standards required detailed daily reports that verified manpower, equipment, and work performed at the job site. It further claimed its superintendent had to continuously supervise and inspect construction activities on-site: “[the] superintendent had to be on-site to account for, among other things, hours worked by crew members, usage and standby hours for each piece of equipment, materials delivered, weather throughout the day, and all work performed. These on-site responsibilities reflected the government’s quality control standards, under which the superintendent as ‘the most senior site manager at the project, is responsible for the overall construction activities at the site…includ[ing] all quality, workmanship, and production of crews and equipment.” Civil Construction, supra, at 1253-54.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com