Bond Principal Necessary on a Mechanic’s Lien Claim
September 07, 2020 —
Christopher G. Hill - Construction Law MusingsAs anyone that reads this construction law blog knows, mechanic’s liens are a big part of the Virginia landscape for a construction attorney like me.
One option for dealing with a mechanic’s lien here in Virginia that we have not discussed but so often is the ability to “bond off” a lien. In short, the Virginia statute allows a party to essentially substitute a bond valued at a court set multiple of the principal amount of the mechanic’s lien for the memorandum. In exchange, the lien is released of record. Any enforcement action can still proceed with security for the claimant and the property owner feeling better about things because there will be no lien on the title to the land.
In many ways this process provides an easier path to resolution for both owner and claimant. First of all, the claimant does not have to deal with a bank or other interest holders in the property (though a recent case discussed below reminds us that certain other parties are necessary). Second of all, the owner does not have the cloud on the title of a mechanic’s lien that may have been filed by a subcontractor over which he has no control.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
California Insurance Commissioner Lacks Authority to Regulate Formula for Estimating Replacement Cost Value
April 15, 2015 —
Valerie A. Moore and Christopher Kendrick – Haight Brown & Bonesteel LLPIn Assn. of Cal. Insurance Companies v. Jones ( No. B248622, filed 4/8/15), a California appeals court held that California’s Insurance Commissioner Dave Jones lacked the authority to promulgate California Code of Regulations, title 10, section 2695.183, which set out specific requirements for estimating replacement cost as part of any application or renewal for homeowners insurance.
The regulation was promulgated in 2010 in response to complaints from homeowners who lost their homes in the wildfires in Southern California in 2003, 2007, and 2008, and who discovered that they did not have enough insurance to cover the full cost of repairing or rebuilding their homes because the insurers’ estimates of replacement value were too low when they purchased the insurance.
Reprinted courtesy of
Valerie A. Moore, Haight Brown & Bonesteel LLP and
Christopher Kendrick, Haight Brown & Bonesteel LLP
Ms. Moore may be contacted at vmoore@hbblaw.com
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Newmeyer & Dillion Welcomes Three Associates to Newport Beach Office
January 26, 2017 —
Newmeyer & Dillion LLPNEWPORT BEACH, Calif. – JANUARY 24, 2017 – Enjoying rapid expansion in many primary practice areas, Newmeyer & Dillion LLP is pleased to welcome new associates
Jenny Guzman and
Jason Moberly Caruso, and welcomes back
Lily (Toubi) Razai to the Newport Beach office. The addition of these three associates fortifies the firm’s commitment to provide unparalleled service to our clients.
Firm Managing Partner,
Jeff Dennis, explained that each hire addresses the immediate and long-term needs of our clients, and firm's desire for strategic growth. "We always remain focused on what will allow us to better represent our clients, not just now but far into the future. We are excited to bring these three talented lawyers aboard as we continue to expand our capabilities across practice areas.”
Guzman, Caruso and Razai each practice business and real estate litigation, with Razai’s practice including land use and eminent domain matters. Caruso also practices construction law and Guzman's practice also focuses on business and real estate transactions.
Each attorney has unique strengths that continue to diversify the firm’s approach to their clients. In addition to serving clients in state and federal courts, Razai has extensive experience in alternative dispute resolution proceedings, and has served as a mediator in state courts. Awarded Super Lawyers 2016 Rising Star, Caruso utilizes his extensive judicial experience to argue on behalf of his clients at various levels from arbitration to the Ninth Circuit Court of Appeals. Guzman draws on her past experience in private equity and venture capital to protect businesses and help them achieve their full potential. These three associates, along with their diverse experience and cohesive strengths, further reinforce N&D’s foundation for continued growth and excellence.
About Newmeyer & Dillion
For more than 30 years, Newmeyer & Dillion has delivered creative and outstanding legal solutions and trial results for a wide array of clients. With over 70 attorneys practicing in all aspects of business, employment, real estate, construction and insurance law, Newmeyer & Dillion delivers legal services tailored to meet each client’s needs. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer & Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949-854-7000 or visit www.ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
Terminating A Subcontractor Or Sub-Tier Contractor—Not So Fast—Read Your Contract!
May 24, 2018 —
John P. Ahlers - Ahlers Cressman & Sleight PLLC BlogEvery few months I receive a call from a general contractor or subcontractor who has just terminated a subcontractor or sub-tier contractor for non-performance and is “checking in with me to see if there are any liability issues.” After the termination has taken place, if the termination is wrongful, there are serious legal consequences. Calling your lawyer after the fact will not cure missteps in the termination process. Termination for non-performance is a common term in most contract documents. As courts interpret contracts, however, the right to earn revenue from a contract is a substantial interest, and courts generally “abhor” forfeitures (termination) of that right. In other words, the courts will strictly determine whether the terminating party to a contract has complied with the termination process to the letter. A recent example from Connecticut is instructive in this regard. [1]
The general contractor on a large hospital project in Connecticut terminated its electrical subcontractor, hired others to finish the electrical subcontractor’s work, and then sued the electrical subcontractor for $26 million. The electrical subcontractor countersued the general contractor for $3.6 million of work that it had completed at the time of the termination which had not been paid for. The subcontractor claimed that due to the many changes that had occurred on the project, it stopped work because the changes altered the contract to the point that it was no longer the same contract. The subcontractor walked off the project and the general contractor then terminated the subcontractor and re-procured the work from other subcontractors.
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers Cressman & Sleight PLLCMr. Ahlers may be contacted at
john.ahlers@acslawyers.com
Fundamental Fairness Trumps Contract Language
September 24, 2014 —
Craig Martin – Construction Contractor AdvisorThe Texas Supreme Court recently ruled that a “no-damages-for-delay” clause would not be enforced where the delay was caused by the owner. The court’s ruling flies squarely in the face of the contract language that attempted to insulate the owner from any delay claims, even those it caused.
In the case of Zachary Construction v. Port of Houston underlying contract, proposed by the Port of Houston, was heavy handed, to say the least. The contract provided:
“[Contractor] shall receive no financial compensation for delay or hindrance to the Work. In no event shall the Port Authority be liable to [Contractor] … for any damages arising out of or associated with any delay or hindrance to the Work, regardless of the source of the delay or hindrance, including events of Force Majeure, AND EVEN IF SUCH DELAY OR HINDRANCE RESULTS FROM, ARISES OUT OF OR IS DUE IN WHOLE OR IN PART, TO THE NEGLIGENCE, BREACH OF CONTRACT OR OTHER FAULT OF THE PORT AUTHORITY. [Contractor’s] sole remedy in any such case shall be an extension of time.”
Wow, that’s some one-sided language. If the contract was enforced, the contractor could not get any damages for delay, even those damages caused by the active interference of the Port of Houston.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Fifth Circuit: Primary Insurer Relieved of Duty to Defend Without Release of Liability of Insured
March 02, 2020 —
Bethany L. Barrese & Ashley McWilliams - Saxe Doernberger & Vita, P.C.In Aggreko, LLC v. Chartis Specialty Ins. Co.,1 the Fifth Circuit affirmed a decision by the Texas District Court and held that a Covenant Not to Execute constituted a “settlement” sufficient to exhaust policy limits and terminate a primary insurer’s duty to defend.
This case arose out of a wrongful death suit filed by the parents of James Brenek II (“Brenek”). In 2014, Brenek was fatally electrocuted by an electrically energized generator housing cabinet while performing work on a rig in Texas for Guichard Operating Company, LLC (“Guichard”), a Louisiana-based drilling subcontractor. Guichard had leased the generator from Aggreko, LLC (“Aggreko”). A rental agreement between Guichard and Aggreko required Guichard to maintain commercial general liability insurance during the lease period and list Aggreko and the rig owner, Rutherford Oil Corporation (“Rutherford”), as additional insureds under
the policy.
Guichard’s primary insurance carrier, The Gray Insurance Company (“Gray”), agreed to defend and indemnify Aggreko and Rutherford in the wrongful death suit. The Gray policy had a limit of $1,000,000, subject to a $50,000 self-insured retention.
Reprinted courtesy of
Bethany L. Barrese, Saxe Doernberger & Vita, P.C. and
Ashley McWilliams, Saxe Doernberger & Vita, P.C.
Ms. Barrese may be contacted at blb@sdvlaw.com
Ms. McWilliams may be contacted at amw@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Law Firm Settles Two Construction Defect Suits for a Combined $4.7 Million
October 25, 2013 —
CDJ STAFFConstruction Lawyers, LLP has announced that it has settled two Florida construction defect suits, both of which were filed by condominium associations. The first of these involved the Estates at Park Central Condominium Association, a 244-unit condominium complex in Orlando Florida. The condominium association alleged leaks into balconies and garages, and deficiencies in stucco application. After nearly three years since the filing of the lawsuit, and only weeks before the trial was to begin, the case was settled for $2 million.
The second case has also spent the last three years in mediation, however its trial date was further away. The Grand Venezia Condominium Owners Association alleged construction defects including leaking roofs and windows, and improperly installed stucco, leading to dry rot and water damage. The condominium community comprises 336 units in Clearwater, Florida and the units were originally built as apartments. Here, the settlement with the contractor was for $2.75 million. A lawsuit against the developer continues.
Read the court decisionRead the full story...Reprinted courtesy of
Business Interruption, Food Spoilage Claims Resulting from Off Premise Power Failure Denied
June 02, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe insurer denied the insured restaurant's claim for food spoilage and loss of business income when a flood elsewhere caused a power outage. N. Spy Food Co., LLC v. Tower Nat'l. Ins., 2016 N.Y. Misc. LEXIS 1033 (N.Y. Sup. Ct. March 22, 2016).
Tower denied the claim based on an investigation which revealed that the claims resulted from an off premises power failure. The utility company verified that the cause of the power failure was due to flood, a cause excluded under the policy. The food loss and business interruption, therefore, did not result from direct physical loss or damage by a covered cause, justifying the denial of the claim.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com