“Genuine” Issue of “Material” Fact and Summary Judgments
December 18, 2022 —
David Adelstein - Florida Construction Legal UpdatesThis is short article on summary judgments. A motion for summary judgment, as you may already know, is a procedural vehicle to try to dispose of issues or claims in a lawsuit, either partially or fully. The objective is that the moving party claims that there is no genuine issue of material fact and that they are entitled to a judgment (partially or finally) as a matter of law. See Florida Rule of Civil Procedure 1.510. In May of 2021, Florida adopted the federal summary judgment standard which theoretically means trial courts should grant more summary judgments, not less, based on the more rigorous standard.
There have been many articles that discuss Florida’s new summary judgment standard including how the standard used to be versus how it is supposed to be now that it is modeled after the federal standard. That isn’t the point of this posting. (Here is an article published in the Florida Bar Journal that provides a primer on summary judgments in case you are interested.)
The point of this posting is to understand the words “genuine” and “material” as underlined above when moving for or defending against a summary judgment. These words have important meaning in the context of motions for summary judgment. In other words, what is a genuine issue of material fact? This is a question that should not be overlooked because these are the facts you want to focus on and frame your arguments on when moving for or defending against a summary judgment. Notably, these are also the facts you want to introduce and emphasize at trial.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Court Finds No Occurrence for Installation of Defective flooring and Explains Coverage for Attorney Fee Awards
January 05, 2017 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Navigators Specialty Ins. Co. v. Moorefield Const. (No.G050759, filed 12/27/16), a California appeals court held that the knowing installation of flooring over a vapor-emitting slab was not an accident or occurrence, entitling the insurer to reimbursement of money paid as damages to settle a construction defect suit. But the court further held that there was no right of reimbursement for the portion of money payable under the policy’s supplementary payments coverage as costs for contractual prevailing party attorney’s fees.
Navigators insured Moorefield, the general contractor for a Best Buy store. Testing in construction revealed a vapor emission rate from the concrete slab above the approved standard for the flooring. The contractor’s personnel testified that it was normal to install the flooring regardless. Notwithstanding, the contractor’s personnel testified that they consulted the owner and were directed to proceed. In doing so, the contractor also expressly released the flooring subcontractor from any warranty claims.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Assessing Defective Design Liability on Federal Design-Build Projects
March 22, 2021 —
Dirk Haire, Adam Hamilton & Dana Molinari - ConsensusDocsA common misconception by many government officials is that a design-builder is always responsible for every design error or omission on a design-build project. This article examines the actual liability standard applied by the courts and boards of contract appeals when a design defect arises on a federal design-build project.
Background: Design-Build Contracts and the Spearin Doctrine
Design-build contracts combine the design and construction elements of a construction project into one contract. Design-build contracts often include two types of specifications: design and performance. Design specifications may set forth various parameters, such as precise measurements, tolerances, and materials. In doing so, the specifications create a fixed “roadmap” governing a contractor’s performance of the project. Performance specifications, on the other hand, set forth “operational characteristics” to achieve a particular objective or standard, but generally leave the details to the contractor.
Reprinted courtesy of
Dirk Haire, Fox Rothschild LLP,
Adam Hamilton, Fox Rothschild LLP and
Dana Molinari, Fox Rothschild LLP
Mr. Haire may be contacted at dhaire@foxrothschild.com
Mr. Hamilton may be contacted at ahamilton@foxrothschild.com
Ms. Molinari may be contacted at dmolinari@foxrothschild.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Litigation Roundup: “Hold the Pickles, Hold the Lettuce?”
October 02, 2023 —
Daniel Lund III - LexologyHold the pickles, hold the lettuce?
You can even hold the service… or at least proof of it!
In a dispute over the construction of a Burger King restaurant in Tupelo, Mississippi, a state court suit by the owner against its general contractor and architect was removed to federal court by one of the defendant parties, on the basis of the diversity of citizenship of the defendant parties from the plaintiff, per 28 U.S.C. § 1331(a).
For its part, plaintiff, upon achieving service of its state court complaint against the various defendants, filed a proof of service as to the party which sought to remove the case, but not as to the other defendants (even though the other defendants were served). Once the case was removed to federal court and after the deadline for removal has passed, plaintiff sought to have the matter remanded based on the lack of the consent of the entirety of the defendant group to the removal, in accordance with 28 U.S.C. § 1446 (“When a civil action is removed solely under section 1441(a), all defendants who have been properly joined and served must join in or consent to the removal of the action.”).
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Indiana Court of Appeals Rules Against Contractor and Performance Bond Surety on Contractor's Differing Site Conditions Claim
April 03, 2013 —
Brian M. Falcon - Frost Brown Todd LLCEarlier this year, the Indiana Court of Appeals issued an important opinion that impacts contractors and sureties alike. The decision should give contractors in Indiana pause before ceasing work while a dispute with the owner is pending. Sureties also have been placed on notice that strict compliance with the terms of their bonds is amongst their best defenses to claims made by owners and bond claimants.
In Dave's Excavating, Inc. and Liberty Mutual Insurance Co. v. City of New Castle, Indiana, 959 N.E.2d 369 (Ind. Ct. App. 2012), the contractor (“Dave’s”) was the successful bidder on a public sanitary sewer and water main extension project. Dave's procured a performance bond from Liberty Mutual to guarantee its performance obligations to the owner (the "City"). After encountering what it deemed different subsurface conditions—and indeed after having been previously granted a change order to use excavated materials as backfill in light of the subsurface conditions on site—Dave’s placed the project engineer on notice of a differing site conditions claim. The total claim amounted to an 84% increase in the total contract price. With the claim, Dave's advised the project engineer it was ceasing further work until the project engineer provided direction.
While the project engineer reviewed the claim, it reminded Dave's of its contractual obligation to "carry on the work and adhere to the progress schedule during all disputes or disagreements with the OWNER." A dispute immediately occurred regarding whether Dave's was required to continue to work while the project engineer resolved the differing site condition claim. After Dave's maintained its position that it was not required to continue to work, the project engineer placed it on notice of default and copied the letter to Liberty Mutual.
Read the court decisionRead the full story...Reprinted courtesy of
Brian M. FalconBrian M. Falcon can be contacted at http://www.frostbrowntodd.com/contact.html
Yet Another Reminder that Tort and Contract Don’t Mix
January 25, 2021 —
Christopher G. Hill - Construction Law MusingsI have stated on numerous occasions here at Musings that in Virginia, contract claims and tort claims (read fraud) don’t mix. A recent case from the Federal District Court for the Eastern District of Virginia presents another example of this principle. In Itility LLC v. The Staffing Resource Group, Judge Ellis of the Alexandria Division, considered ITility’s claims of fraud and breach of contract against SRG and one of its officers based upon SRG’s alleged violation of its duties under a teaming agreement. The claim by ITility was that TSRG provided false and misleading resumes and thus damaged ITility. SRG filed a Motion to Dismiss and the Court was therefore required to resolve the following issues: (1) whether plaintiff’s fraud claim is barred by Virginia’s “source of duty” rule; (2) whether plaintiff’s claim for tortious interference with a business expectancy is barred by SRG’s participation in the business expectancy, and (3) whether the teaming agreement between the parties bars plaintiff’s claims for consequential and punitive damages.
Reprinted courtesy of
The Law Office of Christopher G. Hill
Mr. Hill may be contacted at chrisghill@constructionlawva.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Congratulations to Partner John O’Meara for Being Named as One of America’s Top 100 Civil Defense Litigators for Three Consecutive Years!
September 20, 2021 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPPlease join Bremer Whyte Brown & O’Meara, LLP in congratulating Woodland Hills Partner John O’Meara for being selected as one of America’s Top 100 Civil Defense Litigators for the third year in a row!
Membership among America’s Top 100 Civil Defense Litigators highlights the accomplishments of the nation’s most esteemed and skilled Civil Defense attorneys. Only 100 attorneys in each state receive this honor and candidates for membership are identified through third-party research or peer nominations by America’s Top 100 or elite attorneys in the community. Candidates are judged by the attorney’s lifetime legal achievements, professional experience, significant case results, peer reputation, client satisfaction, other notable honors, media notoriety, and community impact.
Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
A Behind-the-Scenes Look at Substitution Hearings Under California’s Listing Law
March 04, 2019 —
Garret Murai - California Construction Law BlogThe next case, JMS Air Conditioning and Appliance Service, Inc. v. Santa Monica Community College District, 2nd District Court of Appeal, Case No. B284068 (December 17, 2018), provides an interesting behind-the-scenes look at substitution hearings under the Subletting and Subcontracting Fair Practices Act.
The Subletting and Subcontracting Fair Practices Act
- The Subletting and Subcontracting Fair Practices Act (Public Contract Code Section 4100 et seq.), also commonly referred to as the “Listing Law,” requires that prime contractors on state and local public works projects “list” the following subcontractors in their bids:
- Subcontractors who are anticipated to perform work with a value in excess of 0.5% of the prime contractor’s total bid; and
Subcontractors, on street, highway and bridge projects, who are anticipated to perform work with a value in excess of the greater of: (a) 0.5% of the prime contractor’s total bid; or (b) in excess of $10,000.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel RosenMr. Murai may be contacted at
gmurai@wendel.com