OSHA’s Multi-Employer Citation Policy: What Employers on Construction Sites Need to Know
September 09, 2019 —
Phillip C. Bauknight - Construction ExecutiveMulti-employer worksites are a frequent occurrence in the construction industry as employees from various companies often occupy the same site while a project is being completed. While the need for employees from different companies may be necessary to perform the various tasks required by a project, the presence of multiple employers, and their employees, on the same worksite can result in an increased risk of safety hazards.
Companies performing construction work should be, and generally are, aware of OSHA’s ability to issue citations for workplace safety violations. What many companies may not know, however, is that OSHA’s ability to cite employers is not limited to workplace conditions that are unsafe only to that employer’s direct employees. Rather, OSHA also has the ability to cite an employer, and often does issue such citations, for conditions that could result in injury or death to another company’s employees.
The policy which provides OSHA with this citation ability is CPL 02-00-124 and is called the Multi-Employer Citation Policy (the “Policy”). Under the language of the Policy, OSHA has the ability to cite multiple employers for violations of the Occupational Safety and Health Act for the same hazardous workplace condition. Critically, responsibilities under the Policy do not depend on the employer’s job title but are determined by the employer’s role.
Reprinted courtesy of
Phillip C. Bauknight, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Bauknight may be contacted at
pbauknight@fisherphillips.com
You Can Take This Job and Shove It!
June 10, 2015 —
Garret Murai – California Construction Law BlogThat’s it.
You’ve had it.
They can take their job and shove it!
But can you really tell an owner on a construction project to proverbially shove it where the sun don’t shine?
Well, far be it for me to tread on your First Amendment Rights or stick my nose into the subsequently brought public disturbance charges against you. But can you legally tell an owner to shove it, and that you’re no longer going to perform work on their [insert expletive] project? Well, indeed you can, in limited circumstances, and it’s called a “Stop Work Notice.”
Note: A stop work notice is different from a stop payment notice.
What is a stop work notice?
A stop work notice is a notice given by a direct contractor to a project owner that the contractor will stop work if an amount owed to the contract is not paid within 10 days after notice is given.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Denial of Coverage For Bodily Injury After Policy Period Does Not Violate Public Policy
May 12, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe Rhode Island Supreme Court agreed that the insurer had no coverage obligations for bodily injury occurring after the policy had been canceled. Hoesen v. Lloyd's of London, 2016 R.I. LEXIS 41 (R.I. March 24, 2016).
The plaintiff, Mark Van Hoesen, was seriously injured on July 23, 2012, when he fell from a deck of his house. He sued his contractor, Brian Leonard, alleging that the deck had been negligently constructed. Lloyd's, Leonard's insurer, was later named as a defendant. Lloyd's admitted it issued the policy to Leonard, but it was cancelled on August 29, 2007. Even if it had not been canceled, the policy had expired long before the injuries alleged in plaintiff's complaint occurred.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Comparing Contracts: A Review of the AIA 201 and ConsensusDocs - Part II
March 28, 2018 —
Michael Sams and Amanda Cox – Construction Executive, A publication of Associated Builders and Contractors. All Rights Reserved.Part II of this three-part series compares and analyzes important contract sections in the AIA 201 (2007 and 2017 versions) and ConsensusDocs (2014 and 2017 versions), including Schedule/Time, Consequential Damages/LDs, Claims and Disputes/ADR.
Part I covered Financial Assurances, Design Risk, Project Management and Contract Administration. Part III will cover Insurance and Indemnification and Payment.
SCHEDULE/TIME
Relevant Sections:
- 2007 & 2017 A201: Section 3.10.1
- 2014 & 2017 ConsensusDocs: Section 6.2
AIA:
- Section 3.10.1 of the 2007 A201 requires that the Contractor promptly after being awarded the Contract, prepare and submit a construction schedule providing for Work to be completed within the time limits required in the Contract Documents.
- This schedule shall be revised at appropriate intervals.
- The 2017 edition breaks down the schedule to contain date of commencement, interim milestone dates, date of substantial completion, apportionment of Work by trade or building system, and the time required for completion of each portion of the Work.
- Under section 3.10.2 of the 2007 and 2017 versions, if the Contractor fails to provide a submittal schedule, the Contractor is not entitled to any additional compensation or a time extension based on the Owner’s or the Architect’s slow processing of submittals, regardless of how long they take.
ConsensusDocs 200:
- The 2017 Contract replaces the term Contract Time and instead requires a “Schedule of the Work…formatted in detailed precedence-style critical path method that (a) provides a graphic representation of all activities and events, including float values that will affect the critical path of the Work and (b) identifies dates that are critical to ensure timely and orderly completion of the Work.”
- The Constructor must submit an initial schedule to the Owner only before, “first application for payment” and thereafter on a monthly basis. (Section 6.2.1).
- The Owner is allowed to change the sequences provided in the schedule as long as it does not “unreasonably interfere with the Work.” (Section 6.2.2).
Reprinted courtesy of
Michael Sams , Kenney & Sams and
Amanda Cox, Kenney & Sams
Read the court decisionRead the full story...Reprinted courtesy of
A Behind-the-Scenes Look at Substitution Hearings Under California’s Listing Law
March 04, 2019 —
Garret Murai - California Construction Law BlogThe next case, JMS Air Conditioning and Appliance Service, Inc. v. Santa Monica Community College District, 2nd District Court of Appeal, Case No. B284068 (December 17, 2018), provides an interesting behind-the-scenes look at substitution hearings under the Subletting and Subcontracting Fair Practices Act.
The Subletting and Subcontracting Fair Practices Act
- The Subletting and Subcontracting Fair Practices Act (Public Contract Code Section 4100 et seq.), also commonly referred to as the “Listing Law,” requires that prime contractors on state and local public works projects “list” the following subcontractors in their bids:
- Subcontractors who are anticipated to perform work with a value in excess of 0.5% of the prime contractor’s total bid; and
Subcontractors, on street, highway and bridge projects, who are anticipated to perform work with a value in excess of the greater of: (a) 0.5% of the prime contractor’s total bid; or (b) in excess of $10,000.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel RosenMr. Murai may be contacted at
gmurai@wendel.com
Homeowner may pursue negligence claim for construction defect, Oregon Supreme Court holds
March 01, 2011 —
Lori Bauman, Ater Wynne LLPIn Abraham v. T. Henry, Oregon’s court of appeals held that a Oregon’s court of appeals holds that a homeowner may sue builder for common law negligence absent a contractual provision that forecloses such a claim. Plaintiff homeowners hired defendant contractors to build a house. When plaintiffs discovered defects in the construction years later, they sued for negligence.
The Court of Appeals held that the parties’ contractual relationship did not prevent a negligence claim, and that plaintiffs were entitled to pursue a negligence per se claim based on a violation of the Oregon Building Code.
The Supreme Court affirmed, but on a somewhat different basis. First, according to the Court, a construction defect claim concerns damage to property — and not mere economic losses — and thus is not barred by the economic loss doctrine. Second, the existence
Read Full Story...
Read the court decisionRead the full story...Reprinted courtesy of
Does the Russia Ukraine War Lead to a Consideration in Your Construction Contracts?
April 04, 2022 —
David Adelstein - Florida Construction Legal UpdatesMaterial costs are still affecting the construction industry. Supply chain impacts too. The volatility started with COVID-19 (and, in certain cases, before with the imposition of tariffs) and has continued through present date.
But what about the war between Russia and Ukraine and the impact this has had or may have on the supply chain? I think the spillover from the war (with oil, gas, the energy sector, etc.), including the imposition of any sanctions, is not fully realized other than the concern exists in an economy that is already battling through material costs and supply chain disruptions.
How does this affect you?
It may not.
Or you may regularly enter into construction contracts in which you would be smart to address material costs and supply chain impacts. The reason being is that everything from a risk standpoint should begin with your construction contract. Not addressing an issue does not actually mitigate the risk. Confronting the issue does mitigate the risk because you are contractually addressing a concern and know where the other party stands relating to that concern so that business decisions can be made.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Client Alert: Naming of Known and Unknown Defendants in Initial Complaints: A Cautionary Tale
September 24, 2014 —
R. Bryan Martin & Whitney L. Stefko – Haight Brown & Bonesteel LLPOn September 12, 2014, the Ninth Circuit Court of Appeals, in Butler v. National Community Renaissance of California, upheld a district court's dismissal of certain defendants named in amended complaints, affirming the necessity of naming those known and unknown defendants in Plaintiff's original complaint.
In April 2009, Plaintiff Zina Butler filed an action in federal district court, naming a single defendant, National Community Renaissance Corporation ("National"), for an alleged warrantless search of Plaintiff's apartment on April 18, 2007. The single page complaint asserted that the apartment manager provided a Section 8 investigator, a City employee and Sherriff deputies keys to Plaintiff's apartment and conducted a search in violation of her Fourth Amendment rights. Shortly after, Plaintiff filed a first amended complaint, with the only change being the addition of defendant, the Housing Authority of the County of Los Angeles ("HACoLA") in the caption. In May 2009, the court (on its own accord) dismissed the first amended complaint with leave to amend as "it [was] unclear whom Plaintiff intend[ed] to sue."
In June 2009, Plaintiff filed a second amended complaint, identifying National and HACoLA in the caption as defendants, but separately identifying several other individuals and entities allegedly involved in the incident occurring in April of 2007 in the complaint's statement of facts. The Court, once again, dismissed the second amended complaint with leave to amend for the same reasons it dismissed Plaintiff's first amended complaint.
Reprinted courtesy of
R. Bryan Martin, Haight Brown & Bonesteel LLP and
Whitney L. Stefco, Haight Brown & Bonesteel LLP
Mr. Martin may be contacted at bmartin@hbblaw.com; Ms. Stefko may be contacted at wstefko@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of