Fire Consultants Cannot Base Opinions on Speculation
May 20, 2019 —
Christopher Konzelmann - The Subrogation StrategistLarsen v. 401 Main St. Inc., 302 Neb. 454 (2019), involved a fire originating in the basement of the Quart House Pub (Pub) in Plattsmouth, Nebraska that spread to and damaged Plattsmouth Chiropractic Center, Inc., a neighboring business. Fire investigators could not enter the building because the structure was unsafe and demolished. The chiropractic center nevertheless sued the Pub alleging that its failure to maintain and replace basement mechanical equipment caused ignition.
To prove its claim, the plaintiff retained a mechanical engineer who reviewed documents and concluded that the fire “originated from a failure of one of the items of mechanical equipment located in the area of the [basement] boiler.” Importantly, however, the consultant could not determine the root cause of the fire, could not eliminate the possibility that the fire originated in a compressor, and could not rule out the building’s electrical service as the ignition source because it was outside his area of expertise. The consultant nevertheless found that the fire most likely would not have occurred if the Pub had regularly serviced and replaced the equipment when needed.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher Konzelmann, White and Williams LLPMr. Konzelmann may be contacted at
konzelmannc@whiteandwilliams.com
Use Your Instincts when Negotiating a Construction Contract
August 07, 2018 —
Christopher G. Hill - Construction Law MusingsI have often discussed the more “mechanical” aspects of contract negotiation and drafting here at Construction Law Musings. However, there is another, less objective (possibly) and more “feel” oriented aspect to construction contracting that can have as big an impact on your construction project. What am I talking about? Your instinct as a construction professional when looking the other party in the eye and getting a feel for the company or individual with whom you are contracting.
Why is this so important? Firstly, and this is a truism, no matter how well drafted your construction contract is (and it should be well drafted and reviewed by an experienced construction attorney), if the other party wishes to “play games” and not honor the terms of that contract, you could still very well end up in litigation with the attendant frustration and expense. Having a great looking, well thought out and at least reasonably “fair” construction contract may make the litigation process somewhat less painful but it does not completely avoid the risk of litigation. If the other party or parties to the contract decide not to pay you or perform as they promised, you are left to enforce whatever contract you have in place.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Court of Appeals Issues Decision Regarding Second-Tier Subcontractors and Pre-Lien Notice
February 06, 2023 —
Travis Colburn - Ahlers Cressman & SleightVelazquez Framing, LLC (“Velazquez”) v. Cascadia Homes, Inc. (“Cascadia”) is a Court of Appeals, Division 2 case where the primary issue on appeal was whether a second tier subcontractor was required to provide pre-lien notice under RCW 60.04 for its labor.
The defendant, Cascadia, was the general contractor that planned to build a home on property it owned in Lakewood, Washington.[1] High End Construction, LLC (“High End”), submitted a bid to Cascadia for framing work on the home. High End began work on Cascadia’s home, but later subcontracted with Velazquez to complete the framing work.[2] Velazquez did not submit a prelien notice for its work on Cascadia’s home, and Cascadia claimed it was unaware that High End subcontracted with Velazquez for framing at the project.
High End invoiced Cascadia and was paid for its work, but High End never paid Velazquez. Subsequently, Velazquez recorded a lien for both labor and materials, and later filed a complaint to foreclose its lien. Cascadia, due to the fact Velazquez did not provide it with prelien notice, moved for summary judgment, arguing prelien notice was required under RCW 60.04.031(1)[3] and the labor portion of a lien cannot be segregated where a subcontractor’s lien includes both labor and materials. Velazquez argued that no prelien notice was required under RCW 60.04.021[4] and RCW 60.04.031 and claimed that subcontractors can segregate the labor portion from the materials portion. The trial court granted Cascadia’s motion and ruled Velazquez did not fall within one of the exceptions for prelien notice in RCW 60.04.031(2), and therefore, could not enforce the lien. Velazquez appealed.
Read the court decisionRead the full story...Reprinted courtesy of
Travis Colburn, Ahlers Cressman & SleightMr. Colburn may be contacted at
travis.colburn@acslawyers.com
The Condominium Warranty Against Structural Defects in the District of Columbia
July 24, 2023 —
Nicholas D. Cowie - Cowie Law GroupTHE CONDOMINIUM WARRANTY AGAINST STRUCTURAL DEFECTS
Condominium developers in Washington DC are required by statute to warrant against structural defects in residential condominiums. District of Columbia Condominium Act (“DC Condo Act”) § 42-1903.16(b). The warranty applies to both condominium common elements and each condominium unit. It requires a developer to repair structural defects, including any resulting damage to the condominium caused by a common element structural defect. DC Condo Act § 42-1903.16(a-1)(2). The statute creating this warranty is called the “Warranty Against Structural Defects,” contained in the DC Condo Act § 42-1903.16.
“Structural Defects” Defined
The warranty applies to “structural defects,” which are very broadly defined to include many types of construction defects. Structural defects are not just limited to defects in the supporting structure of the building. Rather, a structural defect can be any condition that:
“(A) Reduces the stability or safety of unit or common elements below standards commonly accepted in the real estate market,” or
(B) Restricts the normally intended use of all or part of the common elements of a unit and which requires repair, renovation, restoration, or replacement to serve the purpose for which it was intended.”
DC Condo Act § 42-1903.16(j)(6).
Read the court decisionRead the full story...Reprinted courtesy of
Nicholas D. Cowie, Cowie Law GroupMr. Cowie may be contacted at
ndc@cowielawgroup.com
Court Orders House to be Demolished or Relocated
April 26, 2011 —
Beverley BevenFlorezCDJ STAFFDecision Affirmed in Central Arkansas Foundation Homes, LLC v. Rebecca Choate
The Arkansas Court of Appeals affirmed the decision by the trial court in Central Arkansas Foundation Homes, LLC v. Rebecca Choate. In the trial case, Central Arkansas Foundation Homes (CAFH) sought payment for a home built for Choate, while Choate alleged that the builders committed multiple construction defects including using the wrong foundation materials and positioning the house in the wrong direction.
After the house was built, CAFH contacted Choate regarding payment, however, Choate alleged that the finished product did not match the contract. “ After CAFH completed construction, it obtained permanent home financing for Choate and tried to contact her to close the transaction. Choate did not respond until October 2005, when she sent CAFH a list of alleged construction defects, including that the house was facing in the wrong direction; that it was not built on a slab; and that the fireplace, garbage disposal, driveway, and storage area were missing. CAFH replied to Choate in writing, telling her that she had until January 6, 2006, to close on the house or CAFH would sell it. The correspondence enclosed worksheets showing that the amount Choate would owe at closing exceeded $94,000, which included interest that had accrued on the as-yet unpaid construction loan.”
Initially, the court found in favor of CAFH. “On April 18, 2007, Choate’s attorney withdrew from representing her. Soon thereafter, CAFH’s attorney asked the court to set a final hearing on the case. The attorney purportedly sent Choate a letter by regular mail on May 15, 2007, advising her that the case was set for trial on July 9, 2007. Choate, however, did not appear. CAFH did appear, and its general manager, John Oldner, testified to events leading up to the case and the amount of damages claimed. According to Oldner, the interest on the construction loan had accrued to the point that CAFH now sought $104,965.88 from Choate. The court found in favor of CAFH and entered judgment for that amount, plus attorney fees, on July 18, 2007. The court ruled that CAFH could sell the house and either remit any excess to Choate or look to Choate for the deficiency if the sales price did not cover the judgment.”
However, Choate successfully argued that she did not receive notice of the trial. A new trial was ordered, and the outcome was quite different. “On June 6, 2008, the circuit court entered judgment for Choate, ruling that the house was not in substantial compliance with the parties’ contract and that the contract should be rescinded. The court found that the house suffered from numerous construction defects, that the contract contemplated a slab rather than a concrete-pier foundation, and that CAFH ignored Choate’s complaints that the house was facing the wrong way. The judgment directed CAFH to hold Choate harmless on the construction loan, to deed Choate’s two acres back to her, and to remove the house from Choate’s property.”
The Court of Appeals “found that Choate would be unjustly enriched by retaining the benefit of the septic systems and utility lines that CAFH installed on her land. The court therefore awarded $5340 to CAFH as a quantum-meruit recovery for the value of that work. CAFH contends that the award is not sufficient, but we see no clear error.” In the end, the Court of Appeals provided this reason for declining to reverse the trial court’s decision: “The court in this case apparently concluded that the house constructed by CAFH was so fundamentally at odds with Choate’s contractual expectations that she was not unjustly enriched and should simply be, as nearly as possible, returned to the status quo ante. Accordingly, the court ordered the house removed from her property and permitted CAFH to either relocate the house or salvage the house’s materials and unused appliances. We decline to reverse the court’s weighing of the equities in this manner.”
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Corrective Action Protest Grounds for GSA Schedule Federal Construction Contractors
September 09, 2024 —
Marissa L. Downs - The Dispute ResolverA contract awarded, protested, terminated, appealed, then reinstated. It’s no secret that federal construction procurements are plagued with uncertainty. From delays, constructive suspensions, compromised supply chains, the litigation-laden critical path method, and the mandate for all construction materials used in federally funded projects for infrastructure to be produced in the United States under the Build America, Buy America Act (BABAA) (to name just a few traditional and emerging favorites), just one of these issues could fill the rest of anyone’s month with substantive research. To add one more, which is entirely unique to bid protests, federal contractors–including construction contractors–listed in a General Service Administration (GSA) Schedule may have new grounds to have a contract award reinstated that was terminated by a federal agency pending a GAO decision.
GAO Protest
An initial GAO protest filed by Deloitte & Touche LLP (Deloitte) argued that the National Geo-Spatial Intelligence Agency (Agency) wrongfully made an award to Kearney & Company, P.C. (Kearney) when the Agency: (1) improperly evaluated quotes; and (2) failed to conduct a proper best-value tradeoff analysis. At issue was a competed task order with Kearney under a GSA FSS multiple-award contract. Before the GAO issued an opinion, however, it held an unrecorded predictive-outcome conference with Deloitte and Kearney where the only mutual consensus was the likely ineligibility of all offerors for the relevant award. The Agency subsequently elected to take corrective action, terminating Kearney’s contract award for convenience, amending the solicitation to avoid issues (including undisputed issues) addressed in the GAO protest. After the Agency adopted their corrective action, the GAO protest was dismissed as academic and moot.
Read the court decisionRead the full story...Reprinted courtesy of
Marissa L. Downs, Laurie & Brennan, LLPMs. Downs may be contacted at
mdowns@lauriebrennan.com
Illinois Attorney General Warns of Home Repair Scams
November 27, 2013 —
CDJ STAFFAfter storms damaged homes in Illinois, Lisa Madigan, the state’s Attorney General, warned consumers “to be cautious and on alert for scammers trying to take advantage of people in need of assistance.” Ms. Madigan noted that home repair scammers go into areas with storm damage convince homeowners to pay more than they should to repair storm damage.
Read the court decisionRead the full story...Reprinted courtesy of
Event-Cancellation Insurance Issues During a Pandemic
September 07, 2020 —
Lorelie S. Masters & Latosha M. Ellis - Hunton Andrews KurthAs the effects of coronavirus continue, organizations and companies now are considering whether events in late 2020 and early 2021 can take place or need to be converted to virtual events. What insurance effects will those changes and cancellations have? Consideration of these important decisions requires a review of both event-cancellation insurance and a consideration of force majeure and other such issues.
On the insurance front, years ago, many policyholders purchased event-cancellation insurance for events in 2020, 2021, and even as far out as 2024. Such policies, purchased before the middle of March 2020, generally contain explicit coverage “buy-backs” for losses from “communicable disease.” That is, the policyholders paid an extra, specifically identified premium to remove any exclusion for communicable disease from these policies. Typically, these policies do not use the word, “virus”, but rather use “communicable disease”; and exclude neither. Those policies typically cover a specified amount of net profit and include additional coverages for “Cost of Remedial Action”, “Future Marketing Expense”, etc., over and above that specified amount of coverage.
Reprinted courtesy of
Lorelie S. Masters, Hunton Andrews Kurth and
Latosha M. Ellis, Hunton Andrews Kurth
Ms. Masters may be contacted at lmasters@HuntonAK.com
Ms. Ellis may be contacted at lellis@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of