Standard For Evaluating Delay – Directly from An Armed Services Board Of Contract Appeal’s Opinion
October 04, 2021 —
David Adelstein - Florida Construction Legal UpdatesSometimes, it is much better to hear it from the horse’s mouth. That is the case here. The Armed Services Board of Contract Appeal’s (ASBCA) opinion in Appeals of -GSC Construction, Inc., ASBCA No. 59402, 2020 WL 8148687 (ASBCA November 4, 2020) includes an informative discussion of a contractor’s burden when it encounters excusable delay and, of importance, the standard for evaluating delay. It’s a long discussion but one that parties in construction need to know, appreciate, and understand. EVERY WORD IN THIS DISCUSSION MATTERS.
Construction projects get delayed and with a delay comes money because time is money. Many claims are predicated on delay. These can be an owner assessing liquidated damages due to a delayed job or a contractor seeking its costs for delay. Either way, the standard for evaluating delay and the burdens imposed on a party cannot be understated and, certainly, cannot be overlooked. For this reason, here is the discussion on evaluating delay directly from the horse’s mouth in the Appeal of-GSC Construction, Inc.:
The critical path is the longest path in the schedule on which any delay or disruption would cause a day-for-day delay to the project itself; those activities must be performed as they are scheduled and timely in order for the project to finish on time. Wilner v. United States, 23 Cl. Ct. 241, 245 (1991). In Yates-Desbuild Joint Venture, CBCA No. 3350 et al., 17-1 BCA ¶ 36,870, our sister board compiled an excellent and very helpful synopsis of the standards for evaluating delay claims, which I adopt nearly verbatim among the discussion that follows.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
New Jersey Court Upholds Registration Requirement for Joint Ventures Bidding on Public Works Contracts
December 16, 2023 —
Nicholas J. Zaita & Brian Glicos - Peckar & Abramson, P.C.Introduction
In a matter of “first impression,” on November 30, 2023, the Appellate Division affirmed the New Jersey Superior Court decision in
Ernest Bock & Sons-Dobco Pennsauken Joint Venture v. Township of Pennsauken and Terminal Construction Corp., finding that the New Jersey Public Works Contractor Registration Act, N.J.S.A. 34:11-56.48 to -56.57 (“PWCRA” or the “Act”), applies to a joint venture formed for the sole purpose of bidding on a public works contract. Therefore, the Court held that the PWCRA requires any joint venture bidding on public works projects in New Jersey to be registered under the Act at the time of bid submission. Accordingly, the Township of Pennsauken acted within its authority and properly rejected the bid submission of the Ernest Bock & Sons-Dobco Joint Venture which was not registered under the Act in the name of the joint venture at the time of its bid submission, despite the individual members of the joint venture being registered.
Reprinted courtesy of
Nicholas J. Zaita, Peckar & Abramson, P.C. and
Brian Glicos, Peckar & Abramson, P.C.
Mr. Zaita may be contacted at nzaita@pecklaw.com
Mr. Glicos may be contacted at bglicos@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Exploring Architects’ Perspectives on AI: A Survey of Fears and Hopes
March 19, 2024 —
Aarni Heiskanen - AEC BusinessRIBA, the Royal Institute of British Architects, ran a survey in late 2023 with 500 respondents on the impact of AI on their profession. The study also explored the near-term outlook for AI adoption and use. The results reveal divided opinions among architects. A popular view is that AI threatens the profession, even though a larger portion sees tools like AI as necessary in the coming years.
The Present Use of AI
The respondents were asked, for the projects they are currently working on, how often their practice used AI in any way.
In all, 41% said that they use AI to some degree. Of those, 43% agree that AI has improved efficiency in the architectural design processes, while 24% disagree.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Bad Faith Claim for Inadequate Investigation Does Not Survive Summary Judgment
May 20, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe insured's claim for bad faith investigation regarding their hail damage claim did not survive the insurer's motion for summary judgment. Amarillo Hospitality Tenant, LLC v. Mass. Bay Ins. Co., 2015 U.S. Dist. LEXIS 56228 (N. D. Tex. April 29, 2015).
A hailstorm caused damage to the Courtyard Marriot. The day after the storm, the insured inspected the roof of the hotel and observed damage to a sign and some aluminum vent tubes. No damage to the roof itself was observed. Subsequently, leaks were found on the tenth floor of the hotel. A public adjuster concluded that the roof had sustained damage during the hailstorm.
The insured filed a claim with Massachusetts Bay Insurance Company. The insurer paid for the cost of repairing the damaged sign. To determine whether the damage to the roof was caused by the hailstorm, the insurer hired Donna Engineering, who conducted two inspections of the roof. Both inspections concluded that the hailstorm did not cause damage to the roof. Consequently, the claim was denied.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Team Temporarily Stabilizes Delaware River Bridge Crack
February 02, 2017 —
Justin Rice - Engineering News-RecordThe team temporarily stabilizing the Delaware River Bridge and planning its permanent repair also are trying to find a precedent for the bridge’s uncommon fracture. Connecting the Pennsylvania and New Jersey turnpikes, the 61-year-old symmetrical truss bridge was shut down indefinitely on Jan. 20, when a complete fracture in a steel truss was discovered below the bridge deck.
Read the court decisionRead the full story...Reprinted courtesy of
Justin Rice, ENRMr. Rice may be contacted at
ricej@enr.com
Hake Law Attorneys Join National Law Firm Wilson Elser
April 02, 2014 —
Beverley BevenFlorez-CDJ STAFFIn a press release published on PRWEB, the national law firm Wilson Elser announced “that Bill Hake, founder of Bay Area–based Hake Law, and 15 members of his team, including attorneys, paralegals and staff, have joined the firm’s San Francisco office effective April 1.”
Specifically, “Wilson Elser has added a total of four partners from Hake Law, including Bill Hake, Melissa Ippolito, Nicolas Martin and Lucy Hoff, and four associates, including Gardiner McKleroy, Jeremy Berla, Molly Friend and Whitney Barnecut, bringing the total attorney headcount in Wilson Elser’s San Francisco office to 40.”
According to the release, “Hake Law was primarily a defense litigation firm focused on product liability, construction defects, D&O, catastrophic injury, toxic tort, white collar criminal, class action and complex litigation defense.” Wilson Elser is a “full-service and leading defense litigation law firm… with nearly 800 attorneys in 25 offices in the United States, one in London and through a network of affiliates in key regions globally.”
Read the court decisionRead the full story...Reprinted courtesy of
Background Owner of Property Cannot Be Compelled to Arbitrate Construction Defects
November 07, 2012 —
CDJ STAFFIn Truppi v. Pasco Engineering, John Quattro sued Property Management Contractors, Inc. over construction defects in William Truppi’s home. All parties are named in the suit. The California Court of Appeals ruled that Property Management Contractors, Inc. (PMCI) could not compel Mr. Quattro to arbitration.
The background of the case involves two houses built in Encinitas, California by PCMI: one for Mr. Truppi at 560 Neptune, and one for Mr. Quattro at 566 Neptune. Both contracts contained an arbitration provision. Mr. Quattro signed the contract for his residence and Mr. Truppi signed the other. Mr. Quattro then sued PCMI and its principal, William Gregory. Mr. Quattro claimed to be the true contracting party for the 560 Neptune residence and a third party beneficiary of the contract Mr. Truppi signed, and stated that PCMI was aware of this.
PCMI in a demurrer stated that Quattro “had only a ‘prospective beneficial interest in the property upon its eventual sale or lease.’” Mr. Quattro amended his complaint to account for the issues raised by PCMI. The court rejected PCMI’s demurrer to the amended complaint.
Finally, PCMI and Gregory asserted that Quattro was “not the real party in interest” and could not sue. PCMI continues to assert that Quattro lacks standing, but their attorney sent Quattro an e-mail stating, “While my client disputes that you are a party, and that you lack standing to assert the claim, to the extent you do so I believe you are obligated to proceed by way of arbitration.”
The court did not cover the issue of Quattro’s standing in the case, only if he could be compelled to arbitration. The court affirmed the lower court’s finding that Quattro could not be compelled to arbitrate the construction defect claim as neither he nor Gregory signed the contract in an individual capacity. Further, the court noted that PCMI and Gregory “denied the existence of an agreement between themselves and Quattro on the 560 contract,” and cannot compel arbitration on a non-existent agreement. And while non-signatories can, in some situations be compelled to arbitrate, the court found that “these cases are inapplicable because here they seek to have the alleged third party beneficiary (Quattro) compelled by a nonsignatory (Gregory).” The arbitration clause in question “expressly limited its application to persons or entities that signed the 560 contract.”
As Mr. Quattro was not a signatory to that agreement, the court found that he could not be held to its arbitration provision.
Read the court decisionRead the full story...Reprinted courtesy of
Construction Contract’s Scope of Work Should Be Written With Clarity
March 06, 2023 —
David Adelstein - Florida Construction Legal UpdatesThe scope of work section in your construction contract should never be overlooked. In numerous instances, it is overlooked which leads to a dispute as to the precise nature of the scope of work. This dispute could be the result of an ambiguity in the scope of work section. Or it could be the result of an omission. Or it could be the result of a lack of clarification. Or it could be the result of not properly reviewing and vetting the scope of work section. This is a section—whether included in the body of your contract or attached as an exhibit—you absolutely, positively want clarity. Otherwise, you are potentially setting yourself up for a future dispute that could include (i) an additional work / change order dispute, (ii) an incomplete work dispute, or (iii) a failure to properly perform your work dispute. These are all disputes you want to avoid, and many times can avoid, by going through and negotiating the scope of work section to bring clarity to this section. Remember, clarity is a positive. Ambiguity or uncertainty is a negative.
An example of such an avoidable scope of work dispute can be found in All Year Cooling and Heating, Inc. v. Burkett Properties, Inc., 2023 WL 2000991 (Fla. 4th DCA 2023). Here, an air conditioning contractor was hired to install six new split air conditioning systems. The scope of work provided that there were currently “two split systems that are currently existing, working perfectly and are not to be replaced as part of this contract.” The property manager claimed the air conditioning contractor was required to bring these two existing split air conditioning systems up to code as the contract provided that notwithstanding anything to the contrary, the contractor “will certify and shall ensure that all split systems in the building, upon completion of all the work, will be fully compliant with all codes and regulations and shall be responsible for any costs relates to the implementation and/or remediation of same.”
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com