Randy Okland Honored as 2019 Intermountain Legacy Award Winner
January 06, 2020 —
Jennifer Seward - Engineering News-RecordA passion for construction is in Randy Okland’s blood. His family’s business, Salt Lake City’s Okland Construction, was founded in 1918 by his grandfather, John Okland, a Norwegian immigrant and shipbuilder. Randy swept the floors and cleaned and fueled company vehicles while working as a laborer and later as a carpenter and concrete former. After graduating from the University of Utah, Randy worked full time at Okland, eventually taking over leadership of the company from his father in 1980.
Jennifer Seward, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
New Change Order Bill Becomes Law: RCW 39.04.360
July 08, 2024 —
Brett M. Hill - Ahlers Cressman & Sleight PLLCA new statute (RCW 39.04.360) became effective on June 6, 2024, and it applies to extra work performed by contractors and subcontractors on public and private projects in Washington State. The intent of the original bill was to allow contractors and subcontractors to get paid sooner for undisputed additional work. The statute does not apply to private residential projects of 12 units or less. The statute allows for recovery of interest for contractors/subcontractors at 1% per month (12% per year) on the value of the additional work if the statute is violated.
Here are the requirements of the new statute:
- Public and private owners must issue a change order for the undisputed amount of additional work performed by a contractor, subcontractor, or supplier no later than 30 days after the work is satisfactorily completed and the change is requested by the contractor.
- General contractors, and subcontractors with lower-tier subs, must issue a change order to their subcontractors impacted by the change within 10 days after receipt of the approved change order from the owner/upper-tier contractor.
Read the court decisionRead the full story...Reprinted courtesy of
Brett M. Hill, Ahlers Cressman & Sleight PLLCMr. Hill may be contacted at
brett.hill@acslawyers.com
That’s Common Knowledge! Failure to Designate an Expert Witness in a Professional Negligence Case is Not Fatal Where “Common Knowledge” Exception Applies
June 03, 2019 —
Lyndsey Torp - Snell & Wilmer Real Estate Litigation BlogIn reversing summary judgment for defendants, the California Fourth District Court of Appeal recently held that homeowners suing their real estate broker for negligence did not need an expert witness to establish the elements of their causes of action. Ryan v. Real Estate of the Pacific, Inc. (2019) 32 Cal. App. 5th 637. Typically, expert witnesses are required to establish the standard of care in professional negligence cases. But in Ryan, the court of appeal held that the “common knowledge” exception applied despite this general rule, because the conduct required by the particular circumstance of the case was within the common knowledge of a layman. The conduct in question here? The broker’s failure to disclose to his client that the client’s neighbor told him that she planned extensive renovations that would obstruct the client’s property’s ocean views.
Ryan and Patricia Ryan (the Ryans) hired defendant Real Estate of the Pacific, Inc., doing business as Pacific Sotheby’s International Realty (Sotheby’s) and defendant real estate broker to sell their residence in La Jolla, California. During an open house at the residence, a neighbor informed the Ryan’s real estate broker that she planned extensive renovations at her home that would, among other things, permanently obstruct the Ryan’s westerly ocean views and take several years to complete. The real estate broker never informed the Ryans of this, nor the subsequent buyer. The subsequent buyer purchased the property for $3.86 million, and defendants received $96,500 as commission for the sale. The day after escrow closed, the buyers learned of the renovations, and sought to rescind the purchase. Based on advice of defendants, the Ryans refused, and the dispute proceeded to arbitration. The buyer obtained a rescission of the purchase, with the Ryans order to pay damages, interest, and attorneys’ fees and costs in excess of $1 million. The Ryans then sued Sotheby’s and the real estate broker to recover these amounts and damages caused by defendants’ alleged negligence.
Read the court decisionRead the full story...Reprinted courtesy of
Lyndsey Torp, Snell & WilmerMs. Torp may be contacted at
ltorp@swlaw.com
SEC Climate Change Disclosure Letter Foreshadows Anticipated Regulatory Changes
November 08, 2021 —
Karen C. Bennett & Jane C. Luxton - Lewis BrisboisWashington, D.C. (October 13, 2021) - In late September 2021, the Division of Corporation Finance of the Securities and Exchange Commission (SEC) issued a Sample Letter providing guidance to companies on how their climate disclosures will be analyzed for compliance with material risk reporting obligations. The Sample Letter precedes the SEC’s issuance of mandatory climate-related disclosure rules anticipated by year-end and signals a greater focus on specific information used to support securities filings, a development that businesses should take seriously.
The Sample Letter builds on climate change guidance the SEC issued in 2010 and identifies nine categories of disclosures the SEC suggests may be material risks that must be disclosed. These include:
- Consistency between a company’s corporate social responsibility report and its SEC filings;
- Risks associated with climate-related legislation, regulation, or policy, and resulting compliance costs;
- Litigation risks related to climate change; and
- Risks linked to an array of operational and market factors, including capital expenditures, continuity of business operations, supply chain stability, changing demand, reputation, availability of credit and insurance, and other climate-change related potential impacts on the financial condition of the company.
Reprinted courtesy of
Karen C. Bennett, Lewis Brisbois and
Jane C. Luxton, Lewis Brisbois
Ms. Bennett may be contacted at Karen.Bennett@lewisbrisbois.com
Ms. Luxton may be contacted at Jane.Luxton@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
The Privette Doctrine and Its Exceptions: Court of Appeal Grapples With the Easy and Not So Easy
November 18, 2024 —
Garret Murai - California Construction Law BlogIn
CBRE v. Superior Court, 102 Cal.App.5th 639 (2024), the 4th District Court of Appeal grappled with a thorny and not-so-thorny issue involving injured parties under the Privette doctrine. The less thorny issue was whether application of the Privette doctrine depends on whether a written contract exists between the parties. Spoiler: It does not. The thorny issue was whether the Hooker exception to the Privette doctrine – which applies when a landowner exercises control over a project – should apply where a landowner directs a contractor to perform work that is at odds with legal requirements.
The CBRE Case
Property Reserve, Inc. owns an office building managed by CBRE in San Diego, California. On April 9, 2019, PRI entered into a lease agreement with a new tenant for a suite in the building. The lease required that PRI perform certain tenant improvements.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Repair of Part May Necessitate Replacement of Whole
February 10, 2012 —
CDJ STAFFJudge Gleuda E. Edmonds, a magistrate judge in the United States District Court of Arizona issued a ruling in Guadiana v. State Farm on January 25, 2012. Judge Edmonds recommended a partial summary judgment in favor of the plaintiff.
Ms. Guandiana’s home had water damage due to pluming leaks in September 2004. She was informed that polybutylene pluming in her house could not be repaired in parts “it must be completely replaced.” She had had the plumbing replaced. State Farm denied her claim, arguing that “the tear-out provision did not cover the cost of accessing and replacing those pipes that were not leaking.”
In September 2007, State Farm filed a motion to dismiss. The court rejected this motion, stating that “If Guadiana can establish as a matter of fact that the system that caused the covered loss included all the pipes in her house and it was necessary to replace all the pipes to repair that system, State Farm is obligated to pay the tear-out costs necessary to replace all the pipes, even those not leaking.”
In March 2009, State Farm filed for summary judgment, which the court granted. State Farm argued that “the tear-out provision only applied to ‘repair’ and not ‘replace’ the system that caused the covered leak.” As for the rest of the piping, State Farm argued that “the policy does not cover defective materials.”
In December 2011, Ms. Guadiana filed for summary judgment, asking the court to determine that “the policy ‘covers tear-out costs necessary to adequately repair the plumbing system, even if an adequate repair requires replacing all or part of the system.”
In her ruling, Judge Edmonds noted that Ms. Guadiana’s claim is that “the water damage is a covered loss and she is entitled to tear-out costs necessary to repair the pluming system that caused that covered loss.” She rejected State Farm’s claim that it was not obligated to replace presumably defective pipes. Further, she rejected State Farm’s argument that they were only responsible for the leaking portion, noting “Guadiana intends to prove at trial that this is an unusual case where repair of her plumbing system requires replacement of all the PB plumbing.”
Judge Edmonds concluded by directing the District Court to interpret the tear out issue as “the tear-out provision in State Farm’s policy requires State Farm to pay all tear-out costs necessary to repair the plumbing system (that caused the covered loss) even if repair of the system requires accessing more than the leaking portion of the system.”
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Housing Affordability Down
November 20, 2013 —
CDJ STAFFIn what Rick Judson, the chairman of the National Association of Home Builders, describes as a “‘perfect storm’ scenario,” home prices and interest rates are up “at the same time that the cost of building homes is rising due to tightened supplies of building materials, developable lots and labor.” Residential housing is becoming less affordable.
David Crowe, the Chief Economist for the NAHB, attributes this to “higher mortgage rates and the more than year-long steady increase in home prices,” but he notes that “a family earning a median income can afford 65% of homes recently sold.”
For the last four quarters, the San Francisco-San Mateo-Redwood City area in California holds the dubious distinction of being the nation’s least affordable area. There, a family earning the area’s median income of $101,200 (nearly double the national median) could only afford 16% of the homes sold in the area.
Read the court decisionRead the full story...Reprinted courtesy of
Texas Legislature Puts a Spear in Doctrine Making Contractor Warrantor of Owner Furnished Plans and Specifications
May 31, 2021 —
Paulo Flores, Timothy D. Matheny & Jackson Mabry - Peckar & Abramson, P.C.The Texas Legislature has just sent Senate Bill 219 (“S.B. 219”) to the Governor for signature; if this legislation is signed by the Governor, it will further erode the Texas legal doctrine that makes the contractor the warrantor of owner-furnished plans and specifications unless the prime contract specifically places this burden on the owner.
Background
49 states follow what is known as the Spearin doctrine (named after the U.S. Supreme Court case of United States v. Spearin) in which owners warrant the accuracy and sufficiency of owner-furnished plans and specifications. Texas, on the other hand, follows the Texas Supreme Court created Lonergan doctrine, which has been an unfortunate presence in Texas construction law since 1907. In its “purest form,” as stated by the Texas Supreme Court, the Lonergan doctrine prevents a contractor from successfully asserting a claim for “breach of contract based on defective plans and specifications” unless the contract contains language that “shows an intent to shift the burden of risk to the owner.” Essentially, this then translates into the contractor warranting the sufficiency and accuracy of owner-furnished plans and specifications, unless the contract between them expressly places this burden on the owner. Over the years some Texas courts of appeal had ameliorated this harsh doctrine, but in 2012, the Texas Supreme Court indicated Lonergan was still the law in Texas, in the case of El Paso v. Mastec. In 2019, the Texas Legislature took the first step toward hopefully abrogating the Lonergan doctrine by implementing a new Chapter 473 to the Texas Transportation Code with respect to certain projects undertaken by the Texas Department of Transportation, and Texas political subdivisions acting under the authority of Chapters 284, 366, 370 or 431 of the Transportation Code, adopting, as it were, the Spearin Doctrine in these limited, transportation projects. Now, the legislature has further chipped away at the Lonergan doctrine with the passage of S.B. 219.
Reprinted courtesy of
Paulo Flores, Peckar & Abramson, P.C.,
Timothy D. Matheny, Peckar & Abramson, P.C. and
Jackson Mabry, Peckar & Abramson, P.C.
Mr. Flores may be contacted at PFlores@Pecklaw.com
Mr. Matheny may be contacted at tmatheny@pecklaw.com
Mr. Mabry may be contacted at jmabry@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of