That’s What I have Insurance For, Right?
December 31, 2014 —
Craig Martin – Construction Contractor AdvisorAh, the age old question, What does my insurance really cover? A federal court in Georgia recently weighed in on this issue in Standard Contractors, Inc. v. National Trust Insurance Company, and ruled that a contractor’s commercial general liability insurer did not have to pay for damage caused by a subcontractor.
Standard Contractors was hired to renovate the pool on an army base. Standard hired a subcontractor to for design and installation work. The subcontractor’s work was subpar in that the subcontractor omitted a number of parts, installed the wrong parts, and caused more than $400,000 in damage to the pool. Standard submitted a claim to its insurer seeking coverage for the loss under its commercial general liability policy.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
California Supreme Court Finds that When it Comes to Intentional Interference Claims, Public Works Projects are Just Different, Special Even
November 21, 2017 —
Garret Murai - California Construction Law BlogOriginally published by CDJ on April 20, 2017
Earlier, we reported on a California Court of Appeals decision – Roy Allan Slurry Seal, Inc. v. American Asphalt South, Inc. – which held for the first time that a second-place bidder on a public works contract could sue a winning bidder who failed to pay its workers prevailing wages, under the business tort of intentional interference with prospective economic advantage.
Fast forward nearly two years, several amicus briefs, and “one doghouse”* later and the California Supreme Court has . . . reversed.
The Roy Allan Slurry Seal Case
To catch you up, or rather, refresh your recollection . . .
Between 2009 and 2012, American Asphalt South, Inc. was awarded 23 public works contracts totaling more than $14.6 million throughout Los Angeles, Orange, San Bernardino and San Diego counties. Two of the losing bidders on those projects – Roy Allan Slurry Seal, Inc. and Doug Martin Contracting, Inc. – sued American in each of these counties for intentional interference with prospective economic advantage as well as under the Unfair Practices Act (“UPA”) (Bus. & Prof. Code §§ 17000 et seq.) and the Unfair Competition Law (“UCL”) (Bus. & Prof. Code §17200).
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Courthouse Reporter Series: Nebraska Court of Appeals Vacates Arbitration Award for Misconduct
November 18, 2024 —
Brendan J. Witry - The Dispute ResolverVacating an arbitration award is often seen as an uphill battle. Indeed, the U.S. Supreme Court has stated that “courts may only vacate an arbitrator’s decision ‘only in very unusual circumstances.’” Oxford Health Plans, LLC v. Sutter, 569 U.S. 564, 568 (2013). The Federal Arbitration Act provides limited grounds to seek the vacatur of an arbitration award. In Lund-Ross Constructors v. Duke of Omaga, LLC, ___ N.W.3d ___, 33 Neb.App.73, the Nebraska Court of Appeals found that an arbitrator’s conduct warranted the partial vacatur of the award, which granted relief to a subcontractor who filed a counterclaim after the arbitration hearing had closed.
Lund-Ross contracted with Duke of Omaha to build an apartment complex in Omaha. Lund-Ross, in turn, sub-contracted with A Raymond Plumbing. Following completion of the building, Owner withheld payment from Lund-Ross, who in turn, withheld payment from Raymond. Both Lund-Ross and Raymond filed mechanics liens and initiated suits; Raymond’s suit ultimately was dismissed for want of prosecution. Lund-Ross proceeded to arbitration with Owner, naming Raymond as a respondent. Raymond did not participate in the arbitration as a claimant at the time of the hearing.
Read the court decisionRead the full story...Reprinted courtesy of
Brendan J. Witry, Laurie & Brennan LLPMr. Witry may be contacted at
bwitry@lauriebrennan.com
Connecticut Court Finds Anti-Concurrent Causation Clause Enforceable
March 19, 2015 —
Tred R. Eyerly – Insurance Law HawaiiCanvassing both case law and scholarly authority, the court determined that the anti-concurrent cause (ACC) provision barred coverage for loss caused by Tropical Storm Irene. Lombardi v. Universal N. Am Ins. Co., 2015 Conn. Super. LEXIS 138 (Conn. Super. Ct. Jan. 21, 2015).
Tropical Storm Irene caused the insured's home to shift and move from its concrete pier foundation. The house later had to be demolished.
The insurer's expert concluded that the house was removed from the foundation by storm surge and not by wind. The damage caused by wind was limited to 24 feet of trim missing from the roof and about 70 square feet of shingles that were blown away. The insured's expert concluded the house was removed from its foundation due to a combination of wind and water forces. The insured's expert reported that "the water wave action most probably caused most damage to the dwelling support pilings, with wind conditions contributing to the wave action."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Commonwealth Court Holds That Award of Attorney's Fees and Penalties is Mandatory Under the Procurement Code Upon a Finding of Bad Faith
October 29, 2014 —
William J. Taylor and Michael Jervis – White and Willams LLPIn a decision regarding a payment claim by a highway contractor against the City of Allentown, the Commonwealth Court of Pennsylvania has held that an award of attorney's fees and penalties is mandatory under the terms of the Pennsylvania Procurement Code, 62 Pa.C.S. § 3901 et seq., upon a finding of bad faith by the non-paying government agency, even though the statute only states that a court “may” award such fees and penalties.
In A. Scott Enterprises, Inc. v. City of Allentown, Cmwlth. Ct. No. 2163 C.D. 2013, the plaintiff, A. Scott Enterprises, Inc. (Scott), won a contract with the City of Allentown (City) to construct a one mile roadway. Several weeks after commencing work, Scott learned that soil at the construction site was potentially contaminated with arsenic, and was instructed by the City to suspend its work. Because of the soil contamination, additional work would be required to complete the project and Scott submitted proposals for the additional work plus its suspension costs. However, the City never approved the additional work and the project was never completed. The City never paid Scott for costs incurred due to the suspension of the work and Scott filed suit to recover its losses. The jury found that the City had breached the contract with Scott and had acted in bad faith in violation of the Procurement Code, and awarded damages to Scott for its unreimbursed suspension costs. However, the trial court denied Scott’s request for an award of attorney's fees and penalty interest. Both Scott and the City appealed the final judgment to the Commonwealth Court, which reversed the trial court’s refusal to award attorney's fees and penalties.
Reprinted courtesy of
William J. Taylor, White and Williams LLP and
Michael Jervis, White and Williams LLP
Mr. Taylor may be contacted at taylorw@whiteandwilliams.com; Mr. Jervis may be contacted at jervism@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Lessons from the Sept. 19 Mexico Earthquake
October 19, 2017 —
Nadine M. Post - Engineering News-RecordOn the 32nd anniversary of the magnitude-8.1 earthquake that devastated Mexico City on Sept. 19, 1985, 41 U.S. seismic experts were in a workshop near Los Angeles, polishing a new tool to identify “killer” buildings: non-ductile concrete structures that often perform poorly in quakes. Suddenly, the attendees started getting pager alerts from the U.S. Geological Survey: A magnitude-7.1 quake had struck about 120 kilometers from Mexico City.
Read the court decisionRead the full story...Reprinted courtesy of
Nadine M. Post, ENRMs. Post may be contacted at
postn@enr.com
Updated 3/13/20: Coronavirus is Here: What Does That Mean for Your Project and Your Business?
March 16, 2020 —
Alexander Gorelik, Joshua E. Holt, Brian N. Krulick, Shoshana E. Rothman, A. Michelle West, & Brian S. Wood - Smith CurrieThe outbreak of COVID-19 (“coronavirus”) has wreaked a considerable human toll of death, physical suffering, fear, and anxiety internationally. Much of the fear and anxiety results from a lack of information or a full understanding about the spread of the disease, protection against infection, and treatment. At Smith, Currie & Hancock, we urge our clients, friends, and colleagues to take seriously, but calmly and prudently, the threat of this disease to protect yourselves, your loved ones, and your businesses. The first step in that process is to inform yourselves with reliable information. Toward that end, we direct your attention to the Centers for Disease Control and Prevention’s Coronavirus Disease 2019 website: https://www.cdc.gov/coronavirus/2019-ncov/index.html
In addition to the human toll, coronavirus has caused substantial disruptions to economies worldwide. In that regard, the adage “a picture is worth a thousand words,” is particularly foreboding. Satellite images taken by the U.S. National Aeronautics and Space Administration (NASA) of China at the outset of the coronavirus outbreak and approximately a month later show a dramatic decline in air pollution, signifying and illustrating a sharp decline in industrial activity and transportation caused by the disease.
Reprinted courtesy of Smith Currie attorneys
Alexander Gorelik,
Joshua E. Holt,
Brian N. Krulick,
Shoshana E. Rothman,
A. Michelle West, and
Brian S. Wood
Mr. Gorelik may be contacted at agorelik@smithcurrie.com
Mr. Holt may be contacted at jeholt@smithcurrie.com
Mr. Brian may be contacted at bnkrulick@smithcurrie.com
Ms. Shoshana may be contacted at serothman@smithcurrie.com
Ms. West may be contacted at amwest@smithcurrie.com
Mr. Wood may be contacted at bswood@smithcurrie.com
Read the court decisionRead the full story...Reprinted courtesy of
Energy Company Covered for Business Interruption Losses Caused by Fire and Resulting in Town-Ordered Shutdown
February 15, 2021 —
David G. Jordan - Saxe Doernberger & Vita, P.C.In the case of NextSun Energy Littleton, LLC v. Acadia Ins. Co., the United States District Court of Massachusetts held that once direct physical damage from a covered peril causes a covered business interruption loss, any increase in the duration of such business interruption, due to the enforcement of an ordinance or law, extends the coverage period provided for lost income. The Court further held that a policy exclusion for business interruption due to the enforcement of any ordinance or law not in force at the time of the loss only applies when the ordinance or law itself, not the enforcement action that it authorizes, was not in force at the time of the loss.
The case involved a solar panel company, NextSun Energy Littleton (NextSun), that operated solar panel arrays providing electricity to the town of Littleton, Massachusetts. Due to a fire, 88 of the solar panels were damaged, and the Town immediately issued a “red-tag” order halting all energy-generating activity pending a safety inspection. The plaintiff purchased insurance for its panels along with “Energy Generating Income” (EGI) coverage, from the defendant, Acadia Ins. Co. (Acadia). The EGI policy covered “direct physical loss or damage” to “renewable energy generating equipment” and also covered the actual loss of surplus power income incurred during the interruption period. However, it excluded interruption of energy-generating income “caused by the enforcement of any ordinance, law, or decree … not in force at the time of loss.”
Read the court decisionRead the full story...Reprinted courtesy of
David G. Jordan, Saxe Doernberger & VitaMr. Jordan may be contacted at
DJordan@sdvlaw.com