Georgia Appellate Court Supports County Claim Against Surety Company’s Failure to Pay
August 30, 2017 —
David R. Cook Jr. - Autry, Hanrahan, Hall & Cook, LLPIn 2015, Hall County (Georgia) brought legal action against Selective Insurance Company of America, Inc., the surety company for contractor Ruby Forrest. Hall County had contracted Ruby Forrest to complete and maintain sidewalk systems within three residential subdivisions that Ruby Forrest owned and was developing. Ruby Forrest did not complete the work as promised, and Hall County brought action against the contractor’s surety to recover under performance / maintenance bonds for uncompleted work and to assert bad faith claim for punitive damages and attorney fees.
Selective Insurance did not dispute that it had issued the bonds, that Ruby Forrest did not complete the sidewalk systems within the bond periods or their extensions, or that Hall County provided Selective Insurance with timely notice of Ruby Forrest’s failure to complete the work. Instead, Selective Insurance asserted that the original claim by Hall County was time-barred under a provision in the bonds that stated that “the Issuer will have no more liability after” the expiration date of the bond.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hanrahan, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Stick to Your Guns on Price and Pricing with Construction Contracts
December 20, 2021 —
Christopher G. Hill - Construction Law MusingsIn recent posts here at Construction Law Musings, I have discussed the need for clarity of contract, trusting your gut, and assuring that your contract has the necessities. All of these bits of advice (along with my usual advice of working with an experienced construction attorney) are true with regard to commercial construction contracts and apply ten fold in a residential construction (read working for a single/family owner on their house). With a residential project, you, as a construction contractor, are likely to be dealing with the difficult combination of an owner with little or no experience relating to how a construction project is supposed to work and an owner that is emotionally invested in the project because it is their home.
Because of the above, and the fact that your project is likely the biggest single investment that the owner has made outside of possibly a prior house, the residential owner will likely be looking over your shoulder and may very well attempt to negotiate down some of the costs that they perceive as the project moves forward. In short, the average person 1. does not know how much the project truly costs the contractor, and 2. feels that because they hold the cash, they can and should have some control over the individual costs of the construction thus making those costs, and by extension, their contract, negotiable right up until the end.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
In Review: SCOTUS Environmental and Administrative Decisions in the 2020 Term
August 10, 2021 —
Anthony B. Cavender - Gravel2GavelSeveral decisions of interest were issued in the 2020 term, which stretched from October 2020 until early July 2021. This review will concentrate on environmental and administrative law cases.
Texas v. New Mexico
On December 14, 2020, the Court issued its ruling in an Original Action. Water is precious in the Pecos River Valley, and the distribution of water is governed by the Pecos River Compact. Here, Texas complained that New Mexico illegally was seeking delivery credits for evaporated water credits but the Court agreed that New Mexico was entitled to these credits under the provisions of the River Master’s Manual.
Florida v. Georgia
On April 1, 2021, in another waters right ruling on an Original Action filed in the Supreme Court, the Court rejected Florida’s claims that Georgia’s use of interstate waters harmed Florida’s businesses. Florida had to satisfy a heavy burden of proof, which it failed to do.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Account for the Imposition of Material Tariffs in your Construction Contract
March 28, 2018 —
David Adelstein – Florida Construction Legal UpdatesAfter Hurricane Irma, I wrote an article that contractors should revisit the
force majeure provisions in their construction contracts. Not later. But Now.
The force majeure provision is an important provision in a construction contract to account for certain uncertainties that you have NO control over.
Recently, another reason has given rise to contractors needing to revisit their force majeure provisions, as well as any provisions dealing with material escalations. Not later. But now. The
imposition of raw steel and aluminum tariffs (tax on imported goods) and the back-and-forth regarding a potential trade war leads to the kind of uncertainty that should be assessed as a risk.
A risk in both time and cost from material escalations.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
California Case Adds Difficulties for Contractors & Material Suppliers
August 20, 2014 —
Beverley BevenFlorez-CDJ STAFFGarret Murai in his California Law Blog declared that “things just got a lot tougher for contractors and material suppliers in the Golden State.” In his blog, Murai analyzed the recent case Golden State Boring & Pipe Jacking, Inc. v. Eastern Municipal Water District, Case No. E054618 (July 23, 2014), in which “the California Court of Appeals for the Fourth Appellate District found that a subcontractor’s public works payment bond claim was time barred because its stop payment notice was served ‘before’ a notice of completion was recorded.”
Murai explained the importance of the ruling and how it changed the status quo: “Whereas before, it was commonly understood that you could serve a stop payment notice ‘during’ construction (after all, that was the point wasn’t it, to stop construction funds before they are paid out), now you may have only have a 30 day window (probably less) to serve a stop notice within 30 days after a notice of completion or notice of cessation is recorded.”
Read the court decisionRead the full story...Reprinted courtesy of
Design-Build Contracting: Is the Shine Off the Apple?
March 09, 2020 —
John P. Ahlers - Ahlers Cressman & Sleight PLLCThe design-build delivery method offers many benefits to owners. Among the cited benefits are that projects are generally completed faster, at a lower cost, by allowing innovative approaches through early and continual contractor involvement in the design process. The design contractor serves as a single point of contact responsible for both the design and construction of the project.
The Washington State Department of Transportation (“WSDOT”) utilized the design-build procurement method on the largest project ($2 billion) of its type in the state of Washington: the Highway 99 Tunnel, which was finished almost three years late after the tunnel-boring machine (“Bertha”) broke down six years ago. The sorted tale of the SR-99 Tunnel Project was the source of many of this firm’s blog articles.[1] The State of Washington staunchly maintained that the design-build contract protected its taxpayers from covering the repair costs to the tunnel-boring machine when it broke down in 2013. Bertha did not resume tunneling for almost two years, putting on hold removal of the Alaska Way viaduct and rebuilding of the Seattle Waterfront without an elevated highway.
In December 2013, the contractor for the project, Seattle Tunnel Partners (“STP”), contended that a 110-foot long 8” steel pipe which Bertha hit caused the breakdown. That pipe had been installed for groundwater testing by WSDOT in 2002 during its preliminary engineering for the viaduct replacement project. The project’s Dispute Review Board (“DRB”) composed of three tunneling experts found that the pipe constituted a “differing site condition” for which the State was responsible to disclose to contractors. The Board, whose views were non-binding, did not opine about how much damage the undisclosed pipe cost.[2] In other words, the mere fact that a differing site condition occurred did not establish that there was a causal connection between the damages which STP was seeking (in excess of $600 million) and the differing site condition (the 8” steel pipe which WSDOT lawyers at trial derisively referred to as “nothing more than a toothpick for Bertha’s massive cutter head”). STP maintained that Bertha had made steady progress except for three days immediately after hitting the pipe. It didn’t help the contractors’ case that during the discovery phase of the two-month trial, WSDOT lawyers uncovered documents showing that the contractor’s tunnel workers encountered and logged the pipe before digging began.[3]
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers Cressman & Sleight PLLCMr. Ahlers may be contacted at
john.ahlers@acslawyers.com
St Louis County Approves Settlement in Wrongful Death Suit
August 13, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to the StarTribune, the St Louis County Board agreed to pay $100,000 to settle with the family of a teenager who had been killed in a car crash. The family purported that “an improperly placed road construction sign contributed to the accident that caused her death.”
Defendants in the suit included the county, Benchmark Engineering, and Jola & Sopp Excavating. The county board settled, but denied liability.
Read the court decisionRead the full story...Reprinted courtesy of
Coverage Denied Where Occurrence Takes Place Outside Coverage Territory
December 11, 2018 —
Tred R. Eyerly - Insurance Law HawaiiThe court held there was no coverage for construction defect claims that occurred outside the coverage territory. Foremost Signature Ins. Co. v. Silverboys, 2018 U.S. Dist. LEXIS 154524 (S.D. Fla. Sept. 11, 2018).
Solo Design, LLC, a Miami-based design company, entered into a contract with Silverboys, LLC (Owner) to provide interior design services in conjunction with the renovation of the Owner's vacation home in the Bahamas. Solo retained Whittingham, a Bahamian architect, as a subcontractor to serve as project manager.
Owner sued Solo, Whittingham and others in Florida for breach of contract, fraud, conversion and negligence when the project did not go as planned. The underlying complaint alleged intentional misconduct, lying about qualifications and the progress of the project, submitting false invoices, requesting money for services that were not performed, etc. Owner alleged that the damages included: (a) the cost to repair substandard work; (b) loss of use of the home due to delay; and (c) overcharges for furnishings, contract fees, and expenses. The underlying complaint set forth only a few instances of physical injury to the home, including mold on the ceiling in the master shower, faulty millwork on the children's playroom bookshelf, and a defective front door and resysta facade.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com