Motions to Dismiss, Limitations of Liability, and More
January 23, 2023 —
Christopher G. Hill - Construction Law MusingsRemember BAE Sys. Ordnance Sys. V. Fluor Fed. Sols? I examined that case on two occasions previously here at Construction Law Musings. Previously the discussions were about the
mix (or lack thereof) between fraud and contract and about how
careful contract drafting is key.
In the
most recent opinion in this ongoing litigation from March of 2022, the Court examined various motions to dismiss the Complaint and Counterclaim in the matter. As a reminder, the basic facts are as follows.
The US Army Joint Munitions Command (“Army”) contracted with BAE Systems OrdnanceSystems, Inc. (“BAE”) to operate and maintain the Radford Army Ammunition Plant (“RFAAP”)under a basic ordering agreement (“BOA”). Under BOA Task Order 002, BAE contracted to replace the legacy NC facility at the RFAAP with a newer one (the “NC Project”). Initially, BAE subcontracted the NC Project to Lauren Engineers & Constructors (“Lauren”), but later terminated Lauren. Despite terminating Lauren, BAE’s timeline to complete the NC Project remained unchanged and BAE was required to use Lauren’s design for the NC Project. BAE gave interested bidders access to the Lauren design and other related documents and required the selected subcontractor to perform in accordance with the 85% complete Lauren design, that the Lauren design could be relied on for accuracy, and the selected subcontractor only had to complete the unfinished parts. Fluor Federal Solutions, LLC (“Fluor”) submitted a request for information (“RFI”) asking BAE about the standards referenced in the SOW. Fluor was unable to determine the completeness of the Lauren design but relied on BAE’s assertion that the design was 85% complete. BAE rejected Fluor’s initial bid as being too high given what BAE had already paid Lauren for its design and told Fluor to lower its bid because the design was close to complete. Fluor lowered its price and submitted another bid proposal that outlined a firm-fixed-price design/build that forecasted 32 months to complete the NC Project. BAE awarded Fluor an Undefinitized Contract Action (“UCA”) in the amount of $9 million dollars, later increased to $32 million. Under the UCA, Fluor began procuring materials and physical construction before a formal subcontract was agreed upon. On December 17, 2015, BAE and Fluor agreed to a fixed-price design and build subcontract (the “Subcontract”) in which Fluor agreed to design, construct, and partially commission the NC Project for $245,690,422.00, which included money spent already in the UCA. When this litigation began, Fluor was scheduled to complete its work by December 2020, 2.5 years beyond the originally agreed-upon completion date.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Bright-Line Changes: Prompt Payment Act Trends
September 16, 2024 —
Stephanie L. Cooksey - Peckar & Abramson, P.C.Untimely payment by the owner for contract work and additional work on construction projects can place an unfair financial burden on contractors and subcontractors. Most states have attempted to eliminate or mitigate this inequity in construction contracting through Prompt Payment Acts that govern payment deadlines and provide remedies for untimely payment. This article addresses the legislative trends aimed at minimizing the risk of non-payment, overdue payment, and withholding retainage in favor of downstream parties to a construction contract.
Fortifying Contractor Protections with “Bright-Line” Language
Over the last decade, states have been tightening prompt payment laws by replacing broad, general statutory language with bright-line rules. What is a bright-line rule? A specific or definite figure, a quantifiable marker—i.e., something owners, contractors, subcontractors, and suppliers should be aware of. Practically speaking, the more bright-line a prompt payment statute is, the greater the likelihood it will affect a construction project in your state.
A standard form construction contract, if not reviewed carefully, can create conflicts or confusion if it gives a party more leeway on payment deadlines than the applicable Prompt Payment Act. For example, consider an owner-issued Construction Change Directive (“CCD”) that requires a contractor to commence additional work immediately while a formal change order is negotiated. Consequently, a CCD can push financial burdens downstream, whether inadvertently or not, and may conflict with statutory payment deadlines. Nevertheless, an owner can be justified in its utilization of a CCD to maintain the project schedule. How should the parties competing interests be resolved?
Read the court decisionRead the full story...Reprinted courtesy of
Peckar & Abramson, P.C.
Muir named Brown and Caldwell Eastern leader
January 09, 2023 —
Brown and CaldwellHARTFORD, Conn., Jan. 04, 2023 — Leading environmental engineering and construction services firm Brown and Caldwell today announces Senior Vice President Eric Muir has been promoted to leader of its growing Eastern business.
The largest of the company's regions with over 40 offices east of the Mississippi River, the Eastern business consists of clients in the water, wastewater, stormwater, environmental services, and water resources sectors.
Muir has a 20-year background in delivering highly technical civil and environmental engineering projects. He has held leadership and technical roles on some of the most complex projects encompassing water and wastewater treatment, distribution and collection, pumping, and conveyance systems. His experience includes master planning, detailed design, permitting, and construction services.
Since joining Brown and Caldwell in 2018, Muir's business development expertise and client-centric focus have played a key role in setting the company's regional strategic direction to achieve strong financial results.
"Eric is a highly strategic and inclusive leader, passionate about mentoring employees to reach their full potential," said Brown and Caldwell Chief Operating Officer Euan Finlay. "His deep knowledge of clients' environmental obstacles will enhance the positive impacts our teams have on the communities we serve."
Based in Connecticut, Muir will manage overall operations and lead the implementation of the firm's strategy in the East. He will continue the region's growth and lead efforts to make Brown and Caldwell the company of choice for clients, employees, and partners. He will work alongside regional leadership to align the firm's talent pool with clients to provide innovative, cost-effective solutions to challenges related to water quality, biosolids management, and aging infrastructure.
About Brown and Caldwell
Headquartered in Walnut Creek, California, Brown and Caldwell is a full-service environmental engineering and construction services firm with 52 offices and 1,800 professionals across North America and the Pacific. For 75 years, our creative solutions have helped municipalities, private industry, and government agencies successfully overcome their most challenging water and environmental obstacles. As an employee-owned company, Brown and Caldwell is passionate about exceeding our clients' expectations and making a difference for our employees, our communities, and our environment. For more information, visit www.brownandcaldwell.com
Read the court decisionRead the full story...Reprinted courtesy of
Investigation Continues on Children Drowning at Construction Site
August 13, 2014 —
Beverley BevenFlorez-CDJ STAFFTwo months ago, in Hobart, Illinois, two young boys (brothers) “drowned in an unsecured, excavated pit that filled with water” on a site owned by Goldschmidt Construction Services LLC of Hobart. The Post-Tribune reported that “Police Chief Richard Zormier said the department is waiting on reports from other agencies as it continues to investigate circumstances surrounding” the accident.
“We want to be thorough. The young boys deserve it. Their family deserves it,” Zormier told the Post-Tribune.
The family of the victims has filed a $60 million lawsuit against Goldschmidt Construction.
Read the court decisionRead the full story...Reprinted courtesy of
Bats, Water, Soil, and Bridges- an Engineer’s dream
December 31, 2014 —
Melissa Dewey Brumback – Construction Law in North CarolinaWant to know how bats may affect your engineering plans? Want to hear about cool new bridges? Read on.
Over the past month, I’ve had the pleasure of attending two events hosted by the North Carolina Chapter of the ACEC (American Council of Engineering Companies). The first of these was the Joint Transportation Conference, held in conjunction with the NC DOT. The second was the annual ACEC Engineering Excellence Awards. At both events, I learned interesting information that engineers should know. Today, I will discuss the Transportation Conference, including some new regulations and unusual design methods. I will save the highlights from the Excellence Awards for later this week.
1. It’s a cave, it’s a bat, it’s bats, man!
Did you know that your future bridge project may be affected by the Northern Long-Eared Bat? It’s true. Right now, the federal government is considering listing the bat on the Endangered Species List, due to the 98-99% mortality rate the bats are experiencing due to “white nose syndrome”. Over 1,700 projects in North Carolina could be impacted, including work on bridges, culverts, abandoned buildings, and guardrails–essentially, any activity involving tree clearing, structure demolition/removal, or structure maintenance. On November 26th, 2014, the US Fish and Wildlife Service extended the comment period to discuss the implications of listing the bat on the endangered species list. If the bat is listed, there is no grandfathering of projects. All projects will immediately be required to engage in protective activities. Stay tuned, but be aware that your transportation projects could be affected starting sometime next year.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North CarolinaMs. Brumback may be contacted at
mbrumback@rl-law.com
Traub Lieberman Chair Emeritus Awarded the 2022 Vince Donohue Award by the International Association of Claim Professionals
August 07, 2022 —
Richard K. Traub - Traub LiebermanTraub Lieberman is pleased to announce that firm Chair Emeritus Richard Traub has been awarded the 2022 Vince Donohue Award by the International Association of Claim Professionals (IACP).
The IACP provides a forum for senior Claim leaders from across the globe to build relationships with their peers, enhance their knowledge of strategic claim issues and trends, freely exchange views and ideas in order to improve the development, leadership and professionalism of its members and foster goodwill and better business among insurance organizations worldwide. Attorneys at Traub Lieberman have been longstanding members and Diamond Sponsors of the IACP.
Read the court decisionRead the full story...Reprinted courtesy of
Richard K. Traub, Traub LiebermanMr. Traub may be contacted at
rtraub@tlsslaw.com
Fraud and Construction Contracts- Like Oil and Water?
December 31, 2014 —
Christopher G. Hill – Construction Law MusingsWe have discussed the interaction of fraud and breach of contract actions on occasion here at Construction Law Musings. In most cases the two do not mix. Between the economic loss rule and the general desire of Virginia courts to keep contract actions and tort actions separate, most of the time it is impossible to make a fraud action relating to a contract stick in a construction context.
The Virginia Supreme Court recently confirmed this fraud/contract distinction. As discussed in the Virginia Real Estate Land Use & Construction Law blog (Thanks Heidi!), Station No. 2, LLC v. Lynch, et. al. strongly re-states the Virginia courts’ strong reluctance to allow a breach of contract turn into a claim for fraud. Without re-iterating the great discussion of the facts of the case found in the post by Heidi Meizner, suffice it to say that certain contractual promises between and among the parties were not fulfilled much to Station 2, LLC’s detriment.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Dispute Over Exhaustion of Primary Policy
May 20, 2015 —
Tred R. Eyerly – Insurance Law HawaiiIn a dispute between the excess and primary carriers, the Fifth Circuit determined the primary policy was exhausted, triggering coverage under the excess policy. Amerisure Mut. Ins. Co. v. Arch Spec. Ins. Co., 2015 U.S. App. LEXIS 6627 (5th Cir. April 21, 2015).
Amerisure issued a CGL policy to Admiral Glass & Mirror Co. The policy provided excess over any coverage under a controlled insurance program policy. Arch issued an Owner Controlled Insurance Program (OCIP) policy to Endeavor Highrise, LP and to its contrators and subcontractors for bodily injury and property damage arising out of the construction of the Endeavor Highrise. Admiral was a subcontractor insured under the OCIP.
The OCIP had combined bodily injury and property damage limits of $2,000,000 per occurrence, a general aggregate limit of $2,000,000 and a products-completed operations aggregate limit of $2,000,000. The OCIP contained a Supplementary Payments provision which provided that Arch would pay "[a]ll expenses we incur" in connection with any covered claim, and that "[t]hese payments will not reduce the limits of insurance." Endorsement 16, however, expressly deleted and replaced this statement with: "[supplementary payments] will reduce the limits of insurance." The OCIP also provided that Arch's duty to defend ended "when we have used up the applicable limit of insurance in the payment of judgments or settlements."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com