Not If, But When: Newly Enacted Virginia Legislation Bans “Pay-If-Paid” Clauses In Construction Contracts
August 22, 2022 —
Joseph A. Figueroa & Thomas E. Minnis - ConsensusDocsRecently passed legislation in Virginia is likely to dramatically change contractual relationships between prime contractors and subcontractors in the Commonwealth. Abrogating well-established common-law principles set forth by the Supreme Court of Virginia, on April 27, 2022, the Virginia General Assembly, after receiving input from Virginia Governor Glenn Youngkin, passed Senate Bill 550 banning “pay-if-paid” clauses in public and private construction contracts. Contractors performing work in Virginia should take note of the new law, which goes into effect next year and will apply to any contracts executed after January 1, 2023.
The History Of Pay-if-Paid Clauses In Virginia
Broadly speaking, “pay-if-paid” clauses are a commonly used tool by prime contractors on construction projects to shift the risk to subcontractors in the event that the owner does not pay the prime contractor for work. Such clauses usually include language creating an express condition precedent to the subcontractor’s right to be paid for work under a subcontract, stating that the prime contractor shall be under no obligation to pay the subcontractor for work unless and until the prime contractor first receives payment for that work by the project owner. The “pay-if-paid” clause also has a less extreme cousin, the “pay-when-paid” clause, which merely delays the time in which the prime contractor is obligated to pay the subcontractor to the time in which the prime contractor is paid by the owner. It does not, however, extinguish the prime contractor’s ultimate obligation to pay the subcontractor.
Reprinted courtesy of
Joseph A. Figueroa, Watt, Tieder, Hoffar, & Fitzgerald, LLP (ConsensusDocs) and
Thomas E. Minnis, Watt, Tieder, Hoffar, & Fitzgerald, LLP (ConsensusDocs)
Mr. Figueroa may be contacted at jfigueroa@watttieder.com
Read the court decisionRead the full story...Reprinted courtesy of
ENR 2024 Water Report: Managers Look to Potable Water Reuse
July 15, 2024 —
Pam McFarland - Engineering News-RecordWith nearly all seven states within the 250,000-sq-mile Colorado River basin scrambling to conserve their apportionments from the river system’s increasingly depleted resources, interest in securing alternative local drinking water supplies is soaring.
Reprinted courtesy of
Pam McFarland, Engineering News-Record
Ms. McFarland may be contacted at mcfarlandp@enr.com
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
Drafting the Bond Form, Particularly Performance Bond Form
July 14, 2016 —
David Adelstein – Florida Construction Legal UpdatesOftentimes, when it comes to payment and performance bonds (in particular), the bond forms are drafted by the obligee. For example, an owner (as the obligee) may draft the bond forms that it wants its general contractor’s surety to execute. And, a general contractor (as the obligee) may draft the bond forms that it wants its subcontractors’ sureties to execute. As an obligee, it is always beneficial to draft the bond form (particularly the performance bond) that you want the surety to execute. The bond is to benefit you—the obligee—so having a hand in creating conditions to trigger the application of the bond is important, specifically when it comes to triggering a performance bond upon the bond-principal’s default.
Read the court decisionRead the full story...Reprinted courtesy of
David M. Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
BIM Meets Reality on the Construction Site
September 25, 2018 —
Aarni Heiskanen - AEC BusinessBIM models are mostly used by foremen on construction sites. But what if they could be made available for workers at the press of a button? This question was what the Finnish government-funded KIRA pilot project set out to answer. As a by-product, the project also produced augmented reality (AR) solutions for construction sites.
The research project was called ”Digitalization of a construction project based on role and location information” (RoPa). It was conducted by construction company Fira and engineering consultancy Sweco.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Colorado Supreme Court Weighs in on Timeliness of Claims Against Subcontractors in Construction Defect Actions
March 16, 2017 —
Jean Meyer - Colorado Construction LitigationOn February 27, 2017, the Colorado Supreme Court announced its decision in the Goodman v. Heritage Builders, No. 16SA193, 2017 CO 13 (Colo. February 27, 2017) case. In ten short pages, the Colorado Supreme Court completely reshuffled Colorado construction law with respect to application of the statutes of limitation and repose on third-party claims in construction defect cases. Specifically, the Colorado Supreme Court overruled a series of earlier Court of Appeals' decisions that found C.R.S. § 13-80-104(1)(b)(II) (“104(1)(b)(II)”) had no effect on the six-year statute of repose. For context, 104(1)(b)(II) permitted third-party actions for indemnity and contribution to toll until ninety days after the claims in the underlying action were resolved by settlement or judgment. In the construction context, 104(1)(b)(II) was intended to allow a general contractor’s claims against liable subcontractors to toll for the statutorily defined period. This allowed the general contractor to first focus its attention on defending the claims against and thereafter to pursue its claims against the subcontractors.
However, beginning in 2008, in the Thermo Dev., Inc. v. Cent. Masonry Corp., 195 P.3d 1166 (Colo. App. 2008) case, the Colorado Court of Appeals began chipping away at the force of 104(1)(b)(II). This trend continued in the Shaw Constr., LLC v. United Builder Servs., Inc., 2012 COA 24, 296 P.3d 145 decision, the Sierra Pac. Indus., v. Bradbury, 2016 COA 132, _ P.3d_ decision, and culminating in the Sopris Lodging, LLC v. Schofield Excavation, Inc., 2016 COA 158, reh'g denied (Nov. 23, 2016) decision. Effectively, in these decisions, the Colorado Court of Appeals determined that third-party claims could not be brought beyond Colorado’s six-year statute of repose, regardless if they were brought within the ninety day tolling provision set forth in 104(1)(b)(II).
Read the court decisionRead the full story...Reprinted courtesy of
Jean Meyer, Higgins, Hopkins, McLain & Roswell, LLCMr. Meyer may be contacted at
meyer@hhmrlaw.com
Energy Company Covered for Business Interruption Losses Caused by Fire and Resulting in Town-Ordered Shutdown
February 15, 2021 —
David G. Jordan - Saxe Doernberger & Vita, P.C.In the case of NextSun Energy Littleton, LLC v. Acadia Ins. Co., the United States District Court of Massachusetts held that once direct physical damage from a covered peril causes a covered business interruption loss, any increase in the duration of such business interruption, due to the enforcement of an ordinance or law, extends the coverage period provided for lost income. The Court further held that a policy exclusion for business interruption due to the enforcement of any ordinance or law not in force at the time of the loss only applies when the ordinance or law itself, not the enforcement action that it authorizes, was not in force at the time of the loss.
The case involved a solar panel company, NextSun Energy Littleton (NextSun), that operated solar panel arrays providing electricity to the town of Littleton, Massachusetts. Due to a fire, 88 of the solar panels were damaged, and the Town immediately issued a “red-tag” order halting all energy-generating activity pending a safety inspection. The plaintiff purchased insurance for its panels along with “Energy Generating Income” (EGI) coverage, from the defendant, Acadia Ins. Co. (Acadia). The EGI policy covered “direct physical loss or damage” to “renewable energy generating equipment” and also covered the actual loss of surplus power income incurred during the interruption period. However, it excluded interruption of energy-generating income “caused by the enforcement of any ordinance, law, or decree … not in force at the time of loss.”
Read the court decisionRead the full story...Reprinted courtesy of
David G. Jordan, Saxe Doernberger & VitaMr. Jordan may be contacted at
DJordan@sdvlaw.com
White and Williams Earns National "Best Law Firm" Rankings from US News
November 02, 2017 —
White and Williams LLPWhite and Williams has achieved national recognition from US News and World Report as a "Best Law Firm" in the practice areas of Insurance Law and Media Law. Our Philadelphia, Boston, and New York offices have also been recognized in their respective metropolitan regions in several practice areas. Firms included in the “Best Law Firms” list are recognized for professional excellence with persistently impressive ratings from clients and peers. Achieving a tiered ranking signals a unique combination of quality law practice and breadth of legal experience.
National Tier 1
Insurance Law
National Tier 3
Media Law
Metropolitan Tier 1
Boston
Insurance Law
Product Liability Litigation - Defendants
Philadelphia
Personal Injury Litigation - Defendants
Real Estate Law
Tax Law
Metropolitan Tier 2
Philadelphia
Appellate Practice
Commercial Litigation
Construction Law
First Amendment Law
Insurance Law
Legal Malpractice Law- Defendants
Media Law
Trust & Estates Law
Metropolitan Tier 3
New York City
Bankruptcy and Creditor Debtor Rights/ Insolvency and Reorganization Law
Philadelphia
Patent Law
Read the court decisionRead the full story...Reprinted courtesy of
Construction Project Bankruptcy Law
February 05, 2014 —
Beverley BevenFlorez-CDJ STAFFGarret Murai, on the California Construction Law Blog, discusses the ins and outs of bankruptcy in construction projects. Murai discusses “bankruptcy basics” and answers questions regarding filing for project owners, general contractors, and subcontractors.
Murai explained the importance of learning about how bankruptcy affects construction projects: “Bankruptcy on a construction project is one of the biggest fears for owners and contractors. At best it can slow down a project and at worst it can cause a domino effect of bankruptcies as contractors and suppliers aren’t paid, causing the entire project to fail.”
Read the court decisionRead the full story...Reprinted courtesy of