Doing Construction Lead Programs the Right Way
October 16, 2018 —
Natalie Craigmile - Construction InformerRunning a construction business takes hard work. When you are working on a job, it can be difficult to find time to spend on marketing and advertising. If you are short on time, buying leads through construction lead programs could be a good way to meet new customers, grow your business, and find your next job. Keep reading to learn more about some of the pros and cons of buying leads.
A construction lead generation service exists solely to connect home owners with local home improvement contractors. They market across different construction specialties and reach customers who are looking for construction companies. Once they capture the ‘lead’, which is essentially the contact information and a few project details of that potential customer, they sell the lead to one or more local contractors in their network.
Read the court decisionRead the full story...Reprinted courtesy of
Natalie Craigmile, Construction Informer
Be Careful with Good Faith Payments
February 24, 2020 —
Christopher G. Hill - Construction Law MusingsSometimes doing the expedient thing and what looks good at the time can come back to bite you. Just ask 3M Company.
In Faneuil, Inc. v. 3M Co., the Virginia Supreme Court considered a customer services subcontract between Faneuil and 3M relating to a toll collection contract 3M entered into with ERC. The subcontract had a “pay if paid” clause in it requiring payment to 3M from ERC before ERC was required to pay Faneuil, a written change order provision and a base monthly payment to Faneuil for the services that could be reduced in the event of less than expected toll collections. Further, the subcontract stated that if either party settled 3rd party claims, that settlement would not bind the other party to the subcontract absent consent or Court order.
Faneuil was then alleged to have been required to provide “Special Services” relating to manual identification of license plates and other information necessary for toll billing due to 3M’s alleged failure to provide adequate imaging services. Faneuil requested (without written change order) and 3M promised to pay extra for these services. When 3M was slow to pay for the special services, Faneuil did what you would expect and threatened to stop providing them. Instead of contesting the right to the work, 3m made sporadic “good faith” payments to induce continued Special Services from Faneuil. Eventually 3M’s issues caused ERC to stop payments and thus 3M stopped paying Faneuil. 3M then settled the payment claims with ERC and still failed to pay Faneuil.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Coronavirus Is Starting to Slow the Solar Energy Revolution
March 09, 2020 —
Bloomberg NewsThe coronavirus outbreak is threatening to slow the global solar-energy revolution as it cuts the supply of key equipment for solar and wind farms in China and beyond.
As cases of the disease mounted over the past week, manufacturers including Trina Solar Ltd. sounded the alarm over production delays while developers like Manila Electric Co. in the Philippines said projects would be held up.
“If the virus outbreak lasts beyond the first quarter and spreads to more geographies, as is currently happening in Korea and Italy, then it may very well slow down global renewable energy deployment,” said Ali Izadi-Najafabadi, head of analysis in Asia for BloombergNEF which has downgraded its outlook for installations this year.
Read the court decisionRead the full story...Reprinted courtesy of
Bloomberg
ADA Compliance Checklist For Your Business
February 06, 2019 —
Danielle Carter - Bremer Whyte Brown & O'Meara LLPThe Americans with Disabilities Act (ADA) protects people with disabilities against discrimination in three important settings:
1. Employment (ADA Title I)
2. Government Services and Public Transportation (ADA Title II)
3. Commercial Facilities and Places of Public Accommodation (ADA Title III)
Since business owners typically act as both employers and facility managers, they must pay careful attention to Title I and Title III of the ADA. A business owner’s ADA compliance checklist should include the following:
1. ADA Compliance Audit for Structural Accessibility. The ADA and its accompanying regulations set forth detailed legal standards and requirements for accessible design, which specify, for example, the minimum width of doors to conference rooms, the maximum height of public drinking fountains, and the maximum thickness of hallway carpeting. Many older buildings were built without features that accommodate people with disabilities, such that the ADA may require improvements to be made to existing facilities.
Read the court decisionRead the full story...Reprinted courtesy of
Danielle Carter, Bremer Whyte Brown & O'Meara LLPMs. Carter may be contacted at
info@bremerwhyte.com
Naughty or Nice. Contractor Receives Two Lumps of Coal in Administrative Dispute
January 21, 2019 —
Garret Murai - California Construction Law BlogSo, how were your holidays? Hopefully you were good and didn’t receive a lump of coal from Santa. For one contractor, 2018, wasn’t such a good year. And as its name, Black Diamond, suggests, it did indeed receive a black diamond from the courts. Actually, two of them.
Contractors’ State License Board v. Superior Court (Black Diamond No. 1)
In Contractors’ State License Board v. Superior Court, Court of Appeals for the First District, Case No. 1154476 (October 11, 2018), the Contractors State License Board (“CSLB”) brought disciplinary proceedings against Black Diamond Electric, Inc. (“Black Diamond”), a C-10 Electrical Contractor, for violating: (1) Labor Code section 108.2, which requires individuals performing work as electricians to be certified; and (2) Labor Code section 108.4, which permits uncertified persons seeking on-the-job experience to perform electrical work so long as they are under the direct supervision of a certified electrician.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel RosenMr. Murai may be contacted at
gmurai@wendel.com
Assessments Underway After Hurricane Milton Rips Off Stadium Roof, Snaps Crane Boom in Florida
November 05, 2024 —
James Leggate - Engineering News-RecordHurricane Milton and tornados it spurred killed at least five people and knocked out power to 4 million homes and businesses in Florida after making landfall Oct. 9 near Siesta Key in Sarasota County. With assessments and rescues still underway, state officials say the damage was not as bad as it could have been.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
DRCOG’s Findings on the Impact of Construction Defect Litigation Have Been Released (And the Results Should Not Surprise You)
November 13, 2013 —
Derek Lindenschmidt — Higgins, Hopkins, McLain & Roswell, LLC.The downward trend in attached-housing construction in Colorado is well-known and discussed often within the region’s construction, insurance, finance, and legal communities. In recent years, builders and insurers in particular have striven to bring greater awareness to local governments and lawmakers regarding the impact that construction defect lawsuits have on the builders’ ability to introduce desirable, affordable, yet cost-efficient attached-housing options, such as condominiums and townhomes, into the marketplace. The Denver Regional Council of Governments (“DRCOG”) has been aware of the builders’ and insurers’ plight, largely because of the impact that the scarcity of affordable attached-housing has had on their respective communities.
On October 29th, DRCOG released its long-awaited Denver Metro Area Housing Diversity Study, prepared by Economic & Planning Systems, Inc., which investigated the factors contributing to the recent (downward) attached-housing development trends and conditions. The Study evaluated factors including changing financing and insurance requirements for builders and homebuyers, the impacts of foreclosures, changes in prospective homebuyer demographics, economic conditions which limit options for prospective homebuyers, and the costs and risks associated with construction defect regulations and lawsuits.
Despite the retorts and rebukes of the naysayers, the negative impact of construction defect regulations and lawsuits on Colorado’s housing market is significant.
Read the court decisionRead the full story...Reprinted courtesy of
Derek LindenschmidtDerek Lindenschmidt can be contacted at
lindenschmidt@hhmrlaw.com
Appeals Court Rules that Vertical and Not Horizontal Exhaustion Applies to Primary and First-Layer Excess Insurance
August 31, 2020 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Santa Fe Braun v. Ins. Co. of North America (No. A151428, filed 7/13/20), a California appeals court relied on Montrose Chemical Corp. of California v. Superior Court (2020) 9 Cal.5th 215 (Montrose III), to hold that absent express policy wording to the contrary, horizontal exhaustion of all primary insurance is not required in order to trigger first-layer excess coverage.
Beginning in 1992, Braun was sued for asbestos injuries from refineries it constructed and maintained. Braun had primary coverage and multiple layers of excess coverage for the relevant time period. After defending for years, the primary insurers reached a settlement under which they paid their limits into a trust which would fund the ongoing defense and settlements. Certain of the excess insurers settled and also contributed to the trust.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of