CGL Insurer’s Duty to Defend Insured During Pre-Suit 558 Process: Maybe?
December 20, 2017 —
David Adelstein - Florida Construction Legal UpdatesIn earlier postings, I discussed the issue of whether Florida Statutes Chapter 558′s pre-suit construction defects process triggers a CGL insurer’s duty to defend. The issue was whether Florida’s 558 pre-suit notice of a construction defect and repair process met the definition of “suit” within a standard CGL policy.
A standard CGL policy defines the term “suit” as:
“Suit” means a civil proceeding in which damages because of “bodily injury,” “property damage” or “personal and advertising injury” to which this insurance applies are alleged. “Suit” includes:
a. An arbitration proceeding in which such damages are claimed and to which the insured must submit or does submit with our consent; or
b. Any other alternative dispute resolution proceeding in which such damages are claimed and to which the insured submits with our consent.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
A Court-Side Seat: Clean Air, Clean Water, Citizen Suits and the Summer of 2022
November 01, 2022 —
Anthony B. Cavender - Gravel2GavelThis is a selection of significant environmental and regulatory law cases decided by the federal courts after the Supreme Court’s 2021 Term concluded.
The U.S. Court of Appeals for the DC Circuit
National Association of Broadcasters v. Federal Communications Commission
On July 12, 2022, the DC Circuit held that an order of the FCC requiring radio broadcasters to follow a prescribed five-step process to verify the identity of program sponsors was not authorized by the Communications Act. According to the court, the FCC “decreed a duty that the statute does not require, and that the statute does not empower the FCC to impose.” Here, the agency failed to identify the statutory authority it needed to authorize the issuance of such an order. While certainly not as significant as the Supreme Court’s ruling in West Virginia v. EPA, decided only a few days before this decision was released, it is a strong reminder that the courts want to know if a challenged rule is authorized by law.
Humane Society of the U.S., et al., v. U.S. Department of Agriculture
On July 22, 2022, the court decided a case involving the steps the Administrative Procedure Act and the Federal Register Act require to be taken before a final agency rule is legally promulgated. Customarily, when there has been a change in Presidential administrations, the incoming administration “quietly” withdraws rules awaiting Federal Register publication without much ceremony. The majority of this panel agreed that public notice should have been provided to the regulated community to comment on the new administration’s action to pull back a new rule which had been made available for public inspection before Federal Register publication that would have strengthened the protections afforded “show horses,” as now required by law. The court noted that “it seems clear that filing with the Federal Register constituted promulgation of a regulation even though publication may not occur until a later date.” Circuit Judge Rao filed a strong dissent. “By cutting off agency discretion at public inspection, the majority imposes judicial burden on agency procedures that conflicts with circuit precedent, the statutory framework and a longstanding regulation permitting withdrawals prior to publication.” There could be a further review of this unique ruling.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Payment Bond Surety Entitled to Award of Attorneys’ Fees Although Defended by Principal
February 01, 2023 —
Garret Murai - California Construction Law BlogFor contractors involved in California public works projects the scenario is not uncommon: The general contractor awarded the public works project is required to obtain a payment bond for the benefit of subcontractors and suppliers and the payment bond surety issuing the payment bond requires the general contractor to defend and indemnify the surety from and against any claims against the payment bond.
In
Cell-Crete Corporation v. Federal Insurance Company, 82 Cal.App.5th 1090 (2022), the 4th District Court of Appeal examined whether a payment bond surety, who prevails in a claim against the payment bond, is entitled to statutory attorneys’ fees when the party actually incurring the attorneys’ fees was the general contractor, pursuant to its defense and indemnity obligations, as opposed to the surety itself.
The Cell-Crete Case
General contractor Granite Construction Company was awarded a public works contract issued by the City of Thermal known as the Airport Boulevard at Grapefruit Boulevard and Union Pacific Railroad Grade Separation Project. We’ll just call it the “Project.” Subcontractor Cell-Crete Corporation entered into a subcontract with Granite for lightweight concrete and related work.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Portion of Washington State’s Prevailing Wage Statute Struck Down … Again
July 04, 2023 —
Brett Hill & Mason Fletcher - Ahlers Cressman & SleightIn 2018, the Washington Legislature amended its prevailing wages statute adopting S.S.B 5493 and codified as RCW 39.12.015(3). RCW 39.12.015(3) changed how the Washington State Department of Labor and Industries’ industrial statistician set the prevailing wages for employees on public works projects, from a county-by-county basis to a “geographic jurisdiction” basis established in collective bargaining agreements (“CBA”) or if multiple CBAs, the CBA with the higher wage would prevail. This change proved problematic for contractors since it allowed a minority of employees to determine the prevailing wage through side agreements and limited meaningful wage negotiations by industry trade groups. Contrary to the previous rule wherein wages were set by the average or majority wage rate in a certain county (which was normally the collectively bargained wage) and provided some flexibility to the industrial statistician in determining the prevailing wage, now, RCW 39.12.015(3)(a) directs the industrial statistician to “establish the prevailing rate of wage by adopting the hourly wage … paid for the geographic jurisdiction established in [CBAs],” removing flexibility, and requiring the inclusion of CBA (which could encompass multiple counties) wage rates as a part of the prevailing wage formula.
Reprinted courtesy of
Brett Hill, Ahlers Cressman & Sleight and
Mason Fletcher, Ahlers Cressman & Sleight
Mr. Hill may be contacted at brett.hill@acslawyers.com
Mr. Fletcher may be contacted at mason.fletcher@acslawyers.com
Read the court decisionRead the full story...Reprinted courtesy of
Contractor May Be Barred Until Construction Lawsuit Settled
November 06, 2013 —
CDJ STAFFIn July, Pamar Enterprises was constructing a water main in Bad Axe, Michigan and an error on their part sent water and sewage into homes. This was similar to what happened when they constructed a water main in 2007 in Lyon Township. Now Michigan Representative Terry Brown wants the state to stop awarding contracts to Pamar until the lawsuits are resolved. “I’ve asked [the Michigan Department of Transportation] not to have any more contracts with Pamar,” said Mr. Brown.
Mr. Brown is also seeking that the state withholds payments to Pamar. “I was assured that they would not be getting any more payments until the situation was satisfactorily resolved.”
In the 2007 case, Pamar won in Oakland County Circuit Court, but the Michigan Court of Appeals, found that Pamar failed in its “duty to exercise reasonable care when it entered onto an altered private property.”
Read the court decisionRead the full story...Reprinted courtesy of
ICE Said to Seek Mortgage Role Through Talks With Data Service
August 06, 2014 —
Matthew Leising, Jesse Hamilton and Jody Shenn – BloombergIntercontinental Exchange Inc. (ICE), best known for energy trading and its control of the New York Stock Exchange, is engaged in negotiations that would give it a foothold in the $9.4 trillion U.S. mortgage market.
ICE is in early stage talks to form a partnership with Mortgage Electronic Registration Systems Inc., which documents the ownership and resale of about half of U.S. home loans, according to a person familiar with the matter, who asked to not be identified because the discussions are private.
The Atlanta-based exchange owner has been gauging demand for derivatives that enable investors to bet on defaults by U.S. homeowners, Bloomberg News reported in May. ICE, which earns most of its revenue by owning one of the world’s largest derivatives markets, has recently expanded into new businesses such as equity trading with its 2013 purchase of NYSE Euronext and the administration of interest-rate benchmarks.
Mr. Leising may be contacted at mleising@bloomberg.net; Mr. Hamilton may be contacted at jhamilton33@bloomberg.net; Ms. Shenn may be contacted at jshenn@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Matthew Leising, Jesse Hamilton and Jody Shenn, Bloomberg
Property Damage, Occurrences, Delays, Offsets and Fees. California Decision is a Smorgasbord of Construction Insurance Issues
November 15, 2017 —
Garret Murai - California Construction Law BlogI read once that 97 percent of cases never go to trial. However, there are still the ones that do. And, then, there are the ones that do both. The following case, Global Modular, Inc. v. Kadena Pacific, Inc., California Court of Appeals for the Fourth District, Case No. E063551 (September 8, 2017), highlights some of the issues that can arise when portions of cases settle and other portions go to trial, the recovery of delay damages on a construction project through insurance, and the recovery of attorneys’ fees.
Global Modular, Inc. v. Kadena Pacific, Inc.
The U.S. Department of Veterans Affairs contracted with general contractor Kadena Pacific, Inc. (Kadena) to oversee construction of its Center for Blind Rehabilitation in Menlo Park, California. Kadena, in turn, contracted with subcontractor Global Modular, Inc. (Global) to construct, deliver and install 53 modular units totaling more than 37,000 square feet for a contract price of approximately $3.5 million.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Real Estate & Construction News Roundup (08/30/23) – AI Predicts Home Prices, Construction’s Effect on the Economy, and Could Streamline Communications for Developers
October 17, 2023 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, SV invests in a new green “mega-city” outside San Francisco, refunds are given to investors in fraudulent real estate deal, homebuyers are losing purchasing power, and more!
- With major tech companies like Google and Amazon laying off workers, those with computer science and related degrees are looking to construction as a place to start or restart their careers. (Zachary Phillips, Construction Dive)
- Although Silicon Valley is the haven for most tech startups, Israel has become a place where those in construction innovation can find support and funding. (Matthew Thibault, Construction Dive)
- For those who may be concerned about the future price of their home, it may be possible for AI to look at a house and predict its price with “striking accuracy.” (Jacob Zinkula, Business Insider)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team