Not All Work is Covered Under the Federal Miller Act
May 24, 2021 —
David Adelstein - Florida Construction Legal UpdatesThe recent opinion out of the Eastern District Court of Virginia, Dickson v. Forney Enterprises, Inc., 2021 WL 1536574 (E.D.Virginia 2021), demonstrates that the federal Miller Act is not designed to protect ALL that perform work on a federal construction project. This is because NOT ALL work is covered under the Miller Act.
In this case, a professional engineer was subcontracted by a prime contractor to serve on site in a project management / superintendent capacity. The prime contractor’s scope of work was completed by January 31, 2019. However, the prime contractor was still required to inventory certain materials on site, which was performed by the engineer. The engineer claimed it was owed in excess of $400,000 and filed a Miller Act payment bond lawsuit on February 5, 2020 (more than a year after the project was completed).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
North Carolina Federal Court Holds “Hazardous Materials” Exclusion Does Not Bar Duty to Defend Under CGL Policy for Bodily Injury Claims Arising Out of Direct Exposure to PFAs
December 07, 2020 —
Paul A. Briganti - White and Williams LLPOn October 19, 2020, the U.S. District Court for the Western District of North Carolina held that a “hazardous materials” exclusion contained in a CGL policy did not preclude a duty to defend the insured against claims alleging bodily injury resulting from direct exposure to perfluorooctane sulfonate (PFOS) and perfluorooctanoic acid (PFOA), which are man-made chemicals within the group of per- and polyfluoroalkyl substances (PFAs).[1]
In Colony Insurance Company v. Buckeye Fire Equipment Company, the insured was named a defendant in hundreds of underlying suits relating to its manufacture of fire equipment containing aqueous film-forming foam (AFFF), a fire suppressant.[2] The underlying plaintiffs alleged that: (a) the AFFF contained PFOS and PFOA; (b) PFOA and PFOS are highly carcinogenic; and (c) exposure to AFFF contained in the defendants’ products caused bodily injury or property damage. Around a third of the underlying complaints alleged harm from both direct exposure to the foam and exposure through the environment. Representative language from those complaints was: “[d]uring [underlying plaintiff’s] employment as a firefighter and firefighter instructor, he was significantly exposed to elevated levels of PFOS and PFOA in their concentrated form as a result of regular contact with [d]efendant’s AFFF products and through PFOS and PFOA having contaminated the FireCollege well system.”
Read the court decisionRead the full story...Reprinted courtesy of
Paul A. Briganti, White and Williams LLPMr. Briganti may be contacted at
brigantip@whiteandwilliams.com
Protect Your Right To Payment By Following Nedd
August 03, 2022 —
Denise Motta - Gordon & Rees Construction Law BlogIn order to preserve your right to payment, you must satisfy the contractual requirements supporting a change order for the increased costs or time due to the delay. The key to the successful presentation of change order claims is educating your team on the following:
1. NOTICE
- Review the change order and notice provisions of your contracts. Make your contract searchable and insert the term “Noti” and look for the items listed below.
- Who: Check the designated representative for notice.
- It may not be the project manager.
- Confirm who can authorize the change order.
- Is owner approval required?
- Ensure that the party approving the change order has authority to do so.
- What: Check for specific information required by the contract.
- Provide ALL information available.
- If certain information is not yet available, state that the information will be provided when available.
- Reserve all rights to amend and submit additional information.
- Request both an increase to the Contract Sum and Contract Time.
- Make the request even if you do not believe the delay or time necessary will cause a significant impact.
Read the court decisionRead the full story...Reprinted courtesy of
Denise Motta, Gordon Rees Scully Mansukhani, LLPMs. Motta may be contacted at
dmotta@grsm.com
Changes To Commercial Item Contracting
May 29, 2023 —
Marcos R. Gonzalez - ConsensusDocsThe FAR Council has recently published two changes to commercial item contracting that clarify the definition of commercial services and simplify commercial item determinations (“CIDs”) for contracting officers (“COs”). Since the 1990s, the federal government has encouraged the purchase of commercial items to ease the regulatory burden on vendors who have not previously conducted federal business, encourage innovation, and lower prices[
1]. These different objectives (cost savings, broadening markets, innovation) often have corollary policies; for example, vendors who are not accustomed to the regulatory burdens of government business are encouraged to enter the market by being exempted from a slew of regulations (found in standard commercial items clause FAR 52.212-4). As a result, the regulations applicable to commercial item contracting are those required by statute and executive orders in addition to generic commercial terms that may be tailored due to potential variation in commercial terms.[
2]
Commercial Products v. Commercial Services
The first change, in effect since November 2021 pursuant to the 2019 National Defense Authorization (“NDAA”), split the old definition of “commercial item” into two separate definitions: “commercial product” and “commercial service.”[
3] We are now blessed with the following definitions of commercial products and services, respectively:
Commercial product means—
(1) A product, other than real property, that is of a type customarily used by the general public or by nongovernmental entities for purposes other than governmental purposes, and–
(i) Has been sold, leased, or licensed to the general public; or
(ii) Has been offered for sale, lease, or license to the general public;
Reprinted courtesy of
Marcos R. Gonzalez, Peckar & Abramson, P.C.
Mr. Gonzalez may be contacted at mgonzalez@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Pinnacle Controls in Verano
February 21, 2013 —
CDJ STAFFThe California Court of Appeals has applied the California Supreme Court’s recent Pinnacle decision to a new case, Verano Condominium Association v. La Cima Development. As in Pinnacle, La Cima sought to compel arbitration of construction defect claims with a homeowners association. The trial court denied La Cima’s attempt to compel arbitration on the grounds that the arbitration agreement was made with the individual homeowners and not the homeowners association. Further, it was determined that the CC&Rs “were unenforceable due to unconscionability.”
La Cima appealed, and the appeals court affirmed in part and reversed in part. After Pinnacle, La Cima sought a review. The Supreme Court of California directed the appeals court to vacate their earlier decision and reconsider, based on Pinnacle.
The Fourth Circuit Court has concluded that this conflicted with the ruling in Pinnacle. There, as in Verano, homeowners signed agreements that disputes with the developer would be settled through binding arbitration. The appeals court had found for the community association, but on review, the California Supreme Court reversed this decision.
The California Court of Appeals had two issue to consider in this review: whether the arbitration provisions applied to the homeowners association, and whether these provisions were unconscionable. The court concluded that “in light of Pinnacle it is clear the arbitration provisions set forth in the Verano CC&Rs constitute a valid agreement to arbitrate.” On the second question, the Verano CC&Rs were described by the court as “materially indistinguishable” from those in the earlier case. As the state Supreme Court found that those were not unconscionable, clearly neither were these.
The case was remanded for further proceedings and La Cima is entitled to recover the costs of the appeal.
Read the court decisionRead the full story...Reprinted courtesy of
Skanska Will Work With Florida on Barge-Caused Damage to Pensacola Bay Bridge
October 19, 2020 —
Jim Parsons - Engineering News-RecordFlorida Dept. of Transportation investigators continue to assess damage to the Pensacola Bay Bridge, which sustained multiple impacts from two construction barges unmoored by Hurricane Sally’s storm-driven waves on Sept. 15.
Reprinted courtesy of
Jim Parsons, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Denial of Coverage For Bodily Injury After Policy Period Does Not Violate Public Policy
May 12, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe Rhode Island Supreme Court agreed that the insurer had no coverage obligations for bodily injury occurring after the policy had been canceled. Hoesen v. Lloyd's of London, 2016 R.I. LEXIS 41 (R.I. March 24, 2016).
The plaintiff, Mark Van Hoesen, was seriously injured on July 23, 2012, when he fell from a deck of his house. He sued his contractor, Brian Leonard, alleging that the deck had been negligently constructed. Lloyd's, Leonard's insurer, was later named as a defendant. Lloyd's admitted it issued the policy to Leonard, but it was cancelled on August 29, 2007. Even if it had not been canceled, the policy had expired long before the injuries alleged in plaintiff's complaint occurred.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Review the Terms and Conditions of Purchase Orders- They Could be Important!
February 15, 2018 —
Christopher G. Hill – Construction Law MusingsThere are many moving parts on a commercial construction project. These range from site surveys to weather events to ordering materials. On most large construction projects, the prime contract and subcontracts are generally
drafted ahead of time and hopefully reviewed by both in house personnel and an
experienced construction attorney. However, there are situations, particularly where the contract may be one for service or provision of materials where individual purchase orders are issued as opposed to what would likely be looked at as a long form subcontract.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. Hill, PC