COVID-izing Your Construction Contract
December 21, 2020 —
Frederick E. Hedberg - Construction ExecutiveThe global COVID-19 pandemic has changed the world forever, disrupting many industries, as well as creating unprecedented challenges that threaten many businesses. The construction industry is no different. Projects throughout the country have been adversely affected by unplanned work stoppages, delays, disruptions to the supply chain, price escalations and other unanticipated events.
It is critical that owners, developers, contractors and suppliers learn from their experiences over the past year and account for the COVID-19 pandemic when drafting and negotiating contracts for their projects.
First and foremost, parties should clearly define their rights and responsibilities to properly manage risks due to COVID-19 and its impacts. COVID-19 and other key related terms should be defined, relying on the CDC and state governments for guidance, to eliminate any uncertainties. The contract should also identify executive orders, guidelines and regulations that have been issued concerning COVID-19 by states, municipalities and other authorities that have jurisdiction where the project is located.
Reprinted courtesy of
Frederick E. Hedberg, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Hedberg may be contacted at fhedberg@rc.com
Read the court decisionRead the full story...Reprinted courtesy of
Application of Efficient Proximate Cause Doctrine Supports Coverage
January 06, 2012 —
Tred R. Eyerly - Insurance Law HawaiiRelying on the efficient proximate cause doctrine, the court determined coverage potentially existed for damage caused by water. Union Sav. Bank v. Allstate Indem. Co., 2011 U.S. Dist. LEXIS 134398 (S.D. Ind. Nov. 21, 2011).
The Tods purchased property that was mortgaged by Union Savings. The Tods obtained a Landlords Policy for the property from Allstate. When the Tods were in default on their loan, Union Savings notified them that foreclosure proceedings would commence. Union Savings sent an appraiser to the property who discovered water in the basement. Water and electricity to the building were off. Union Savings notified Allstate and later filed a formal claim under the mortgagee clause in the Landlords Policy. This clause stated, "A covered loss will be payable to the mortgagees named on the policy declaration. . . ."
Allstate denied coverage, citing exclusions for water damage.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
Engineer Probing Champlain Towers Debacle Eyes Possibility of Three Successive Collapses
July 05, 2021 —
Nadine M. Post - Engineering News-RecordThough the trigger may remain a mystery for some time, by the end of the week, the structural engineer probing the partial progressive collapse of a 40-year-old Surfside, Fla., residential condominium expects to complete a computer model of the unstable, 12-story remains of the building. The computer model of the still-standing wing of Champlain Towers South will initially be used to alert the search and rescue team to suspend operations if a hurricane is coming.
Reprinted courtesy of
Nadine M. Post, Engineering News-Record
Ms. Post may be contacted at postn@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Court Rules on a Long List of Motions in Illinois National Insurance Co v Nordic PCL
May 10, 2012 —
CDJ STAFFThe case Illinois National Insurance Co. v Nordic PCL, et al. “involves a dispute about whether insurance benefits are available to a general contractor who built structures that allegedly have construction defects. Plaintiffs Illinois National Insurance Company (‘Illinois National’) and National Union Fire Insurance Company of Pittsburgh, PA (‘National Union’) (collectively, the ‘Insurers’), commenced this action for declaratory relief against Defendant Nordic PCL Construction, Inc., f/k/a Nordic Construction, Ltd. ("Nordic"), on August 23, 2011.”
The court was asked to rule on a long list of motions: “Counterclaim Defendants’ Request for Judicial Notice in Support of Their (1) Motion to Dismiss the Counterclaim and (2) Motion to Strike Portions of the Counterclaim, ECF No. 16 (‘Request for Judicial Notice’); Counterclaim Defendants’ Motion to Dismiss Counterclaim Filed October 24, 2011, ECF No. 14 (‘Motion to Dismiss Counterclaim’); Counterclaim Defendants’ Motion to Strike Portions of the Counterclaim Filed October 24, 2011, ECF No. 15 (‘Motion to Strike’); Third-Party Defendant Marsh USA, Inc.’s Motion to Dismiss or, in the Alternative, Stay Proceedings in Favor of Pending State Action, ECF No. 33 (‘Marsh’s Motion To Dismiss Or Stay’); Defendant and Third-Party Plaintiff Nordic PCL Construction, Inc., f/k/a Nordic Construction Ltd.’s Substantive Joinder to Third-Party Defendant Marsh USA Inc.’s Motion to Dismiss or, in the Alternative, Stay Proceedings in Favor of Pending State Action, ECF No. 36 (‘Nordic’s Joinder’); and Third-Party Defendant Marsh USA, Inc.’s Motion for Judgment on the Pleadings on Counts V and VI of Defendant/Third-Party Plaintiff Nordic PCL Construction, Inc.’s Third-Party Complaint, ECF No. 29 (‘Marsh’s Motion for Judgment on the Pleadings’).”
In result, the court reached the following decisions: “The court GRANTS IN RELEVANT PART the Insurers’ Request for Judicial Notice to the extent it covers matters relevant to these motions; GRANTS IN PART the Insurers’ Motion to Dismiss Counterclaim, but gives Nordic leave to amend the Counterclaim in certain respects; DENIES the Insurers’ Motion to Strike; DENIES Marsh’s Motion To Dismiss Or Stay and Nordic’s Joinder; and GRANTS Marsh’s Motion for Judgment on the Pleadings.”
The court provides a bit of background on the case: “This action arises out of alleged construction defects involving two projects on which Nordic acted as the general contractor. Nordic is a defendant in a pending state court action with respect to one of the projects and says it spent more than $400,000 on repairs with respect to the other project. Nordic tendered the defense of the pending state court action to the Insurers and sought reimbursement of the cost of repairs already performed. The Insurers responded by filing this action to determine their rights under the insurance policies issued to Nordic.”
Furthermore, the court presented a brief procedural history: “The Insurers commenced this declaratory action in this court on August 23, 2011. The Complaint asserts two claims, one seeking a declaration that the Insurers have no duty to provide a defense or indemnification regarding the Safeway Action, the other seeking such a declaration regarding the Moanalua Claims. Along with its Answer, Nordic filed a Counterclaim against the Insurers. The Counterclaim asserts breach of contract, breach of the covenant of good faith and fair dealing, misrepresentations and omissions of material fact, and bad faith, and seeks declaratory relief against the Insurers.”
The procedural history continues: “Nordic also filed a Third-Party Complaint against Marsh, the broker that had procured the Policies from the Insurers for Nordic. Nordic alleges that it reasonably believed that the Policies would provide completed operations insurance coverage for the types of construction defects alleged in the Safeway Action and Moanalua Claims. The Third-Party Complaint asserts breach of contract, negligence, promissory estoppel, breach of fiduciary duties, implied indemnity, and contribution and equitable subrogation.”
In conclusion, “The court GRANTS IN RELEVANT PART the Insurers’ Request for Judicial Notice. With regard to the Insurers’ Motion to Dismiss Counterclaim, the court GRANTS the motion as to Count I (breach of contract), Count II (duty of good faith and fair dealing), Count III (fraudulent and negligent misrepresentation), the portion of Count IV (bad faith) premised on fraud, and Count IV (declaratory relief). The court DENIES the motion as to Count IV (bad faith) that is not premised on fraud. Except with respect to the "occurrence" issue, which the court disposes of here on the merits, and Count V, which concerns only a form of relief, Nordic is given leave to amend its Counterclaim within three weeks of the date of this order. The court DENIES the Insurers’ Motion to Strike, DENIES Marsh’s Motion to Dismiss or Stay and Nordic’s Joinder, and GRANTS Marsh’s Motion for Judgment on the Pleadings with respect to Counts V and VI of the Third-Party Complaint.”
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Orlando Commercial Construction Permits Double in Value
October 01, 2013 —
CDJ STAFFThis August, permits were taken out for $102.3 million of commercial construction projects, a 95% increase over last August’s $52.4 million. Meanwhile, residential construction was up by a third, jumping from $205.6 million to $274.1 million. Overall that sent construction up by 46% in the Orlando area.
The construction industry is a major one in the Orlando area and its recovery provides some hope for the region.
Read the court decisionRead the full story...Reprinted courtesy of
Contractors Sued for Slip
June 28, 2013 —
CDJ STAFFA man on his way to a safety meeting slipped fell on a gangway. He’s saying that the roofing paper on the gangway was improperly secured and is now suing the contractor for negligence. Donald Methvien claims that his damages exceed $50,000.
Read the court decisionRead the full story...Reprinted courtesy of
Insurer's Judgment on the Pleadings Based Upon Expected Injury Exclusion Reversed
October 30, 2018 —
Tred R. Eyerly - Insurance Law HawaiiThe appellate court reversed the trial court's granting of a judgment on the pleadings based upon the expected injury exclusion in a homeowner's policy. Allstate Indemn. Co. v. Contreras, 2018 Ill. App. LEXIS 170964 (Ill. Ct. App. July 20, 2018).
Alejandra Contreras owned Jasmine's Day Care. Her husband, Adan Contreras, was not an employee of the Day Care. Alejandra and Adan had a homeowner's policy which provided day care liability coverage through an endorsement.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
General Contractor’s Professional Malpractice/Negligence Claim Against Design Professional
November 30, 2017 —
David Adelstein - Florida Construction Legal UpdatesA recent case supports a professional malpractice (negligence) claim by a general contractor against a design professional by reversing a trial court’s entry of summary judgment in favor of the design professional and finding a question of fact remained as to an architect’s role in the renovation of a public construction project. By the appellate court finding that a question of fact remained, the appellate court was finding that it was a triable issue, which is exactly what the general contractor wanted in this case. Getting this issue and the facts to the jury is the leverage the general contractor presumably wanted.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com