Failing to Pay Prevailing Wages May Have Just Cost You More Than You Thought
April 01, 2015 —
Garret Murai – California Construction Law BlogMechanics lien claims, payment bond claims, stop payment notice claims, delay claims, defect claims, abandonment claims . . .
With the variety of claims unique to construction projects it’s easy to forget that construction disputes are simply a category of business disputes in which broader business-related torts apply.
In Roy Allan Slurry Seal, Inc. v. American Asphalt South, Inc., Case No. B255558 (February 20, 2015), the California Court of Appeal for the Second District held for the first time that a second-place bidder on a public works contract may sue a winning bidder – who failed to pay its workers prevailing wages – under the business tort of intentional interference with prospective economic advantage.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Construction Defects Are Not An Occurrence Under New York, New Jersey Law
June 18, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe New York Supreme Court, Appellate Division, determined there was no coverage for construction defects under New York or New Jersey law. Nat'l Union Fire Ins. Co. of Pittsburgh, PA v. Turner Constr. Co., 2014 N.Y. App. Div. LEXIS 3546 (N.Y. App. Div. May 15, 2014).
The property owner retained Turner Construction to serve as the general contractor. Turner subcontracted with Permasteelisa North America Corporation to design and build the exterior wall, a "curtain wall," which consisted of granite and glass.
A segment of the pipe rail system fell to the street from the eighth floor of the building. An investigation determined that more than 20% of the pipe rail connections surveyed did not conform to the building plans. Additional problems included inconsistencies in the method of rail attachment, bent brackets on the pipe rail system, cracked glass louvers, cracked glass panels, and water infiltration.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Record Keeping—the Devil’s in the Details
July 30, 2015 —
Craig Martin – Construction Contract AdvisorAnother court has found that poor record keeping will prevent recovery on a claim. The court in Weatherproofing Tech., Inc. v. Alacran Contracting, LLC found that a contractor’s documents were a mess and that no reasonable jury could base a verdict on the contractor’s records.
The underlying project involved the construction of an army training facility. The total project cost approximated $13 million. Alacran, the general contractor, subcontracted about $3 million of the work to Weatherproofing Tech. Alacran paid Weatherproofing $700,000 for its work, even though Weatherproofing submitted invoices of more than $2 million. Alacran justified its refusal to pay Weatherproofing on the grounds that the parties had agreed to split the profit and loss on the project and the project was out of money. Not surprisingly, Weatherproofing sued Alacran for the amount owed.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Emerging Trends in Shortened Statutes of Limitations and Statutes of Repose
January 02, 2024 —
Ivette Kincaid & Thomas McCarrick - Kahana FeldIntroduction
A growing trend in construction defect legislation around the country has seen the shortening of statutes of limitation and statutes of repose for a plaintiff to bring claims related to construction defects. Over the past ten years, several states, notably Florida and Texas, have shortened their statutes of repose. This is generally positive news for developers and contractors; however, the specifics and ramifications of these legislative and judicial updates are still unknown.
Statute of Limitations
A statute of limitations sets forth the time that a plaintiff has to sue or allege a particular cause of action against a defendant. These time limitations are codified into law and vary depending on the State and the cause of action. A statute of limitations starts at the occurrence of an injury or damage or at the time the injury or damage is discovered. The statute of limitations may be subject to some exceptions such as tolling for reasons such as the injured party being a minor in which case depending on the particular statute, the statute does not begin to run until after the minor reaches the age of majority.
Reprinted courtesy of
Ivette Kincaid, Kahana Feld and
Thomas McCarrick, Kahana Feld
Ms. Kincaid may be contacted at ikincaid@kahanafeld.com
Mr. McCarrick may be contacted at tmccarrick@kahanafeld.com
Read the court decisionRead the full story...Reprinted courtesy of
California Contractors: New CSLB Procedure Requires Non-California Corporations to Associate All Officers with Their Contractor’s License
April 19, 2021 —
Amy Pierce, Mark Oertel & John Lubitz - Lewis BrisboisAs of July 1, 2020, “[e]very person who is an officer, member, responsible manager, or director of a corporation or limited liability company seeking licensure under this chapter shall be listed on the application as a member of the personnel of record,” and they must match those officers listed on California Secretary of State’s (SOS) records. (Cal. Bus. & Prof. Code § 7065 (b)(1)). This is a deviation from the Contractors State License Board’s (CSLB) past practice of requiring foreign corporations to associate as personnel of record only their president, in contrast to requiring domestic corporations to associate their president, secretary, and treasurer.
Beware that the CSLB may discover that the licensee’s personnel of record are incomplete or incorrect when reviewing a license renewal application, because it will compare the SOS’s records to the license renewal application. A license renewal application requires the licensee to list its qualifier and personnel of record. If the SOS and CSLB records do not match, this could delay approval of the license renewal application until the missing personnel are added and fingerprinted.
Reprinted courtesy of
Amy Pierce, Lewis Brisbois,
Mark Oertel, Lewis Brisbois and
John Lubitz, Lewis Brisbois
Ms. Pierce may be contacted at Amy.Pierce@lewisbrisbois.com
Mr. Oertel may be contacted at Mark.Oertel@lewisbrisbois.com
Mr. Lubitz may be contacted at John.Lubitz@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
What Made the Savannah Harbor Upgrade So Complicated?
May 10, 2017 —
Jim Parsons - Engineering News-RecordOf all the East Coast port upgrade programs aimed at luring cargo traffic from the newly widened Panama Canal, the Savannah Harbor Expansion Project (SHEP) may well be the most ambitious, and complex. Elements of the joint effort by the U.S. Army Corps of Engineers’ Savannah District and the state of Georgia—originally estimated to cost $706 million, but subsequently increased to $973 million—range from 40 miles of channel dredging and new water quality mitigation facilities to the addition of an upstream fish passage and the recovery of a Civil War-era relic.
Read the court decisionRead the full story...Reprinted courtesy of
Jim Parsons, ENRENR may be contacted at
ENR.com@bnpmedia.com
Does Stricter Decertification Mean More “Leedigation?”
August 04, 2015 —
Christopher G. Hill – Construction Law MusingsRecently, my friend and fellow construction attorney/consultant, Chris Cheatham (@chrischeatham) posted the news that USGBC will be more stringent on the de-certification front. This statement relates to the continued energy performance of LEED certified buildings and increases the likelihood that energy performance (as opposed to mere reporting) could lead to de-certification.
I have discussed on several occasions the potential legal risks relating to green building. One of the big potential sources for such litigation (or “leedigation” as coined by Mr. Cheatham) is the possible de-certification of a previously certified building. With this latest statement by USGBC the specter of such de-certification seems even stronger.
Couple this potential with the fact that anyone can challenge the certification of a building at any time and contractors, subcontractors and other construction professionals face potential liability for the performance of a building in ways well beyond their control.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Protect Your Right To Payment By Following Nedd
August 03, 2022 —
Denise Motta - Gordon & Rees Construction Law BlogIn order to preserve your right to payment, you must satisfy the contractual requirements supporting a change order for the increased costs or time due to the delay. The key to the successful presentation of change order claims is educating your team on the following:
1. NOTICE
- Review the change order and notice provisions of your contracts. Make your contract searchable and insert the term “Noti” and look for the items listed below.
- Who: Check the designated representative for notice.
- It may not be the project manager.
- Confirm who can authorize the change order.
- Is owner approval required?
- Ensure that the party approving the change order has authority to do so.
- What: Check for specific information required by the contract.
- Provide ALL information available.
- If certain information is not yet available, state that the information will be provided when available.
- Reserve all rights to amend and submit additional information.
- Request both an increase to the Contract Sum and Contract Time.
- Make the request even if you do not believe the delay or time necessary will cause a significant impact.
Read the court decisionRead the full story...Reprinted courtesy of
Denise Motta, Gordon Rees Scully Mansukhani, LLPMs. Motta may be contacted at