Housing Woes Worse in L.A. Than New York, San Francisco
September 03, 2014 —
Nadja Brandt and John Gittelsohn – BloombergJeanette Cross took out a payday loan to cover her May rent of $1,600 in South Los Angeles. She skipped car and insurance payments to keep a roof over her head.
“I’m further and further behind,” Cross, a 34-year-old single mother of four, said in a telephone interview. “I make a payment on one thing and don’t pay others.”
She isn’t alone. Angelenos use a bigger slice of their paychecks on shelter than people in New York, San Francisco or Miami, studies show. Surging property prices in the second-largest U.S. city are driving up costs in once-impoverished areas while pushing lower-income households into converted garages or to distant suburbs, where the tradeoff is hours stuck in traffic each day.
Reprinted courtesy of
Nadja Brandt, Bloomberg and
John Gittelsohn, Bloomberg
Ms. Brandt may be contacted at nbrandt@bloomberg.net; Mr. Gittelsohn may be contacted at johngitt@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Everyone's Moving to Seattle, and It's Stressing Out Sushi Lovers
July 16, 2014 —
Peter Robison and Alison Vekshin – BloombergSooner or later, everyone moves to Seattle, went one saying in the city’s 1990s heyday. The trouble residents face now: What happens after everyone does?
Known for hiking and the open spaces of the American West, Seattle is in the midst of another boom that’s made it the fastest-growing among the top 50 U.S. cities. That’s causing angst over density, affordability, crime and other issues more familiar to an East Coast metropolis. At the same time, pay is outpacing the national average and an already rich cultural life is thriving as new restaurants and nightspots open.
“It’s a blessing,” Seattle Mayor Ed Murray, a 59-year-old Democrat, said of the growth. “But with it comes some real challenges.”
Mr. Robison may be contacted at robison@bloomberg.net; Ms. Vekshin may be contacted at avekshin@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Peter Robison and Alison Vekshin, Bloomberg
Thousands of London Residents Evacuated due to Fire Hazards
June 29, 2017 —
David Suggs – Bert L. Howe & Associates, Inc.Nearly 4,000 residents were ordered by municipal authorities to “urgently evacuate apartments in five London high-rise buildings…after fire inspectors warned that the safety of the residents could not be guaranteed,” reported the New York Times. Displaced families were urged to find shelter with family or friends, but temporary accommodations were offered. Repairs may take up to four weeks.
The five London towers that were evacuated all contain the same exterior cladding and insulation that is similar to what was used in Grenfell Tower, where 79 people died in fire only the preceding week, according to the New York Times. Camden Council stated that the cladding material would be removed. They had ordered noncombustible cladding, but later learned that combustible cladding had been installed.
“Preliminary tests on the insulation samples from Grenfell Tower show that they combusted soon after the test started,” Detective Superintendent McCormack said in a televised statement, as quoted by the New York Times. “Cladding tiles had also failed initial tests,” she continued.
Read the court decisionRead the full story...Reprinted courtesy of
A Lack of Sophistication With the Construction Contract Can Play Out In an Ugly Dispute
November 07, 2022 —
David Adelstein - Florida Construction Legal UpdatesThere are times where a lack of sophistication can come back to haunt you. This is not referring to a lack of sophistication of the parties. The parties, themselves, could be quite sophisticated. This is referring to a lack of sophistication with the construction contract forming the basis of the relationship. While parties don’t always want to buy into the contract drafting and negotiation process, it is oftentimes the first document reviewed. Because contract terms and conditions are important. They govern the relationship, the risk, scope, amount, and certain outcomes with disputes. However, a lack of sophistication can play out when that contract that should govern the relationship, the risk, the scope, the amount, and certain outcomes doesn’t actually do that, or if it does, it does it poorly. An example of how bad a dispute can play out when it comes to the lack of sophistication on the front end is Avant Design Group, Inc. v. Aquastar Holdings, LLC, 2022 WL 6852227 (Fla. 3d DCA 2022), where a cost-plus contract was treated as a lump sum contract.
Here, an owner planned to perform an extensive interior build-out to a residential unit. The owner had an out-of-country architect; because the architect was not licensed in Florida, the owner hired a local architect/designer to oversee construction and obtain goods and services for the residential interior build-out. The contract was nothing but a proposal of items and costs. The proposal stated the owner “would pay the cost of goods and services of the vendors, plus pay a ‘20% Interior Design & Administrative Fee’” to the local designer. Avant Design Group, 2022 WL at *1. The proposal further stated, “This preliminary budget of the Client’s construction costs include [sic] anticipated costs for construction materials, labor and sales tax. Any other cost, including but not limited to freight, cartage, shipping, receiving, storage and delivery are not included in the preliminary budget and will be invoiced separately.” Id., n.2.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Nevada Court Adopts Efficient Proximate Cause Doctrine
February 10, 2012 —
Tred R. Eyerly - Insurance Law HawaiiAlthough the Nevada Supreme Court adopted the efficient proximate cause doctrine, it determined it did not apply to salvage coverage under an all-risk policy for a rain-damaged building. Fourth Street Place, LLC v. The Travelers Indemn. Co., 2011 Nev LEXIS 114 (Nev. Dec. 29, 2011).
Fourth Street owned an office building which was insured by an all-risk policy issued by Travelers. Fourth Street hired Above It All Roofing to repair the roof of the office building. Above It All removed the waterproof membrane on the roof and prepared to replace the membrane the following week. Over the weekend, however, substantial rain hit. On Sunday, Above It All returned to cover the exposed portions of the roof with tarps, but wind later blew the tarps away. The building suffered significant interior damage as it continued to be exposed to the rain.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
Misread of Other Insurance Clause Becomes Costly for Insurer
February 22, 2018 —
Tred R. Eyerly – Insurance Law HawaiiOne insurer's refusal to defend based upon its "other insurance" provision ultimately meant the insurer had to pay all of the insured's defense costs. Steadfast Ins. Co. v. Greenwich Ins. Co., 2018 Wis. App. LEXIS 51 (Wis. Ct. App. Jan. 17, 2018).
Milwaukee Metropolitan Sewerage District (MMSD) was a government agency that provided water reclamation and flood management services to the city. From March 1, 1998 to February 20, 2008, MMSD contracted with United Water Services Milwaukee LLC to operate the sewerage system. From March 1, 2008 on, MMSD contracted with Veolia Water North America-Central, LLC to operate the system.
Through agreements, both companies were obligated to indemnify MMSD for claims arising out of the operations and maintenance of the system and to obtain insurance to cover their indemnity obligations. Both companies complied.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Ambiguity Kills in Construction Contracting
February 15, 2018 —
Christopher G. Hill – Construction Law MusingsWell, I’m back and hope to have a more consistent publishing schedule moving forward. I appreciate the continued readership through what has been a busy time for
my solo construction practice over the last couple of months. Now, back to our program. . .
Here at Construction Law Musings, I have often beaten the drum of
a solid contract that leaves as little as possible to chance or the dreaded “grey areas” where we construction lawyers like to make money. An example of the issues that can arise from ambiguity can be found in a case from 2017 in the
Western District of Virginia, W.C. English, Inc. v. Rummel, Klepper & Kahl, LLP et al
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill – The Law Officeof Christopher G. Hill, PC
Edward Beitz and William Taylor Recognized by US News – Best Lawyers as a "Lawyer of the Year"
August 31, 2020 —
Edward Beitz & William Taylor - White and WilliamsWhite and Williams is proud to announce that Edward Beitz and William Taylor have been recognized by U.S. News – Best Lawyers® as a “Lawyer of the Year” in their respective practices in Philadelphia. Ed was named in the area of Medical Malpractice and Bill was named in Construction Law. "Lawyer of the Year" recognitions are awarded to individual lawyers with extremely high overall peer-feedback for a specific practice area and geographic location.
Ed is a member of the Healthcare Group and focuses his practice on medical malpractice defense, defending doctors, nurses, physician assistants and hospitals at the trial and appellate court levels, as well as general liability matters. He has successfully defended numerous medical malpractice cases at trial involving complex issues of the human anatomy, such as cardiac surgery, neurosurgery, orthopedic surgery, nursing care, obstetrical complications, nerve injury and vascular injury. Ed has authored briefs on appellate issues in healthcare and coverage matters to the Superior Court of Pennsylvania, the New Jersey Appellate Division and the Third Circuit Court of Appeals.
Reprinted courtesy of
Edward Beitz, White and Williams and
William Taylor, White and Williams
Mr. Beitz may be contacted at beitze@whiteandwilliams.com
Mr. Taylor may be contacted at taylorw@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of