Federal Court of Appeals Signals an End to Project Labor Agreement Requirements Linked to Development Tax Credits
October 20, 2016 —
Gregory R. Begg & Aaron C. Schlesinger – Peckar & Abramson, P.C.What Action Should Owners, Developers and Contractors Take in Anticipation of Successful Challenges to PLA Requirements?
Recently, a federal court in New Jersey issued a decision which very well may invalidate all Project Labor Agreements (“PLA’s”) entered into as a condition to receipt of tax incentives for private development. Tax incentives utilized to promote private development are different, according to the court, than typical public works projects where PLA requirements have generally been held valid. Owners, developers, contractors and governmental entities must assess the consequences of this decision upon contracts already and to be awarded in the future where tax benefits may be linked to a PLA requirement.
In 1993, in what has become known as the Boston Harbor Case, the United States Supreme Court held that state and local governmental entities may condition the award of public works contracts on the contractor’s agreement to enter into PLA’s.
That decision has been followed nationwide since then to uphold the validity of various state and local law bidding conditions requiring successful bidders to negotiate and enter into project labor agreements as a condition to the award of public works contracts. The rationale is that when the government, like any other private party, is participating in an economic market, it may exercise its discretion in setting terms and conditions it believes best suit its interests in the efficient procurement of goods and services in that market. Therefore, a PLA requirement by a governmental entity engaged in market activity is no more or less valid than a PLA requirement on a purely private project.
Reprinted courtesy of
Gregory R. Begg, Peckar & Abramson, P.C. Aaron C. Schlesinger, Peckar & Abramson, P.C.
Mr. Begg may be contacted at gbegg@pecklaw.com
Mr. Schlesinger may be contacted at aschlesinger@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
U.S. Homeowners Are Lingering Longer, and the Wait Is Paying Off
July 28, 2018 —
Jeremy Hill - BloombergHomeowners in the U.S. are holding on to their houses longer than they have in at least 18 years, and when they do sell, they’re reaping gains that haven’t been seen since before the housing crisis.
Those who sold in the second quarter did so after owning their homes for an average of 8.09 years, the longest stretch since Attom Data Solutions started tracking the statistic in 2000. The wait appears to be paying off: Second-quarter sellers recorded gains averaging $58,000 -- the most since the third quarter of 2007.
Read the court decisionRead the full story...Reprinted courtesy of
Jeremy Hill, Bloomberg
Real Estate & Construction News Roundup (5/8/24) – Hotel Labor Disputes, a Congressional Real Estate Caucus and Freddie Mac’s New Policies
June 04, 2024 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, nonresidential construction increases, Redfin settles lawsuits, overseas real estate becomes more lucrative than domestic real estate, and more!
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
LAX Construction Defect Suit May Run into Statute of Limitations
December 30, 2013 —
CDJ STAFFCurrent arguments over the claims made by LAX that Runway 25L was built in a defective manner by Tutor-Saliba/O&G Industries are hinging over whether the airport knew the runway was defective less than four years after the construction was completed. The runway was built almost five years ago, and Tutor-Saliba is claiming that Los Angeles World Airports has delayed too long in making a construction defect complaint. Tutor-Saliba is not conceding that the runway is defective, only that if it were, the airport would have known it earlier.
Los Angeles World Airports, which operates LAX, is not commenting on the matter, but Robert Span, an aviation attorney at Steinbrecher & Span, told the Daily Breeze that while “there is a four year statute of limitations for dealing with construction defects, but that’s for what they called patent defects,” and that “there’s a 10-year statute of limitations for construction projects where the defect that is alleged is called latent — something that would not be readily apparent.”
Tim Pierce, a construction attorney at K&L Gates LLP described it as “a common defense,” though he said it is “raised in most cases and only works in some.”
Read the court decisionRead the full story...Reprinted courtesy of
Used French Fry Oil Fuels London Offices as Buildings Go Green
December 10, 2015 —
Siobhan Wagner – BloombergPricewaterhouseCoopers LLP’s office above Charing Cross railway station in London is cooled, heated and fueled by an unlikely source: used cooking oil.
The system, which helped the property become the greenest building in the U.K. capital, uses oil refined less than two miles away at London Bridge. It also helps prevent an invisible problem: “fatbergs” formed when oils dumped in drains and pipes congeal with baby wipes and diapers and block the city’s sewers.
“We’re using London’s waste to fuel a London office building,” said Jon Barnes, head of building at PwC. The system contributed toward a one-third reduction in electricity costs after a two-year refurbishment of the One Embankment Place office building that finished last year.
Read the court decisionRead the full story...Reprinted courtesy of
Siobhan Wagner, Bloomberg
Proposed Law Protecting Tenants Amended: AB 828 Updated
June 08, 2020 —
Rhonda Kreger – Newmeyer DillionOn May 18, 2020, AB 828 was amended and is currently on its second reading in the Senate Rules Committee. This legislation proposes a temporary moratorium on foreclosures and unlawful detainers while Governor Newsom's COVID-19 emergency order is in effect. In addition to the moratorium, AB 828 also required landlords to reduce rent by 25% under certain circumstances. AB 828 was amended to remove the provision that required landlords to reduce rent by 25% for 12 months. The new provision requires landlords to allow tenant to remain in possession, and requires tenants to start paying rent the month following the end of the emergency order. Tenants must timely pay monthly rent plus 10% of any rent due and owing when the emergency order ended.
Under AB 828, a tenant may stipulate to the entry of an order in response to a residential unlawful detainer action filed by the landlord. Upon a hearing, the court determines if the tenant's inability to pay rent is the result of increased expenses or a reduction in income due to COVID-19. The court must also make a determination that there is no material economic hardship for the landlord. Upon making such determinations, the court will issue an order that permits the tenant to remain in possession, and requires tenant to commence rental payments the month following the end of the COVID-19 emergency order. Tenant's payment would include the monthly rent plus 10% of an unpaid rent during the COVID-19 emergency order, but excludes any late charges or other fees or charges. The tenant would be required to make timely payments, and if tenant fails to do so, after a 48 hour notice from landlord, the landlord can file for an immediate writ of possession in favor of the landlord and money judgment for any unpaid balance, court costs and attorneys' fees.
Newmeyer Dillion continues to follow COVID-19 and its impact on your business and our communities. Feel free to reach out to us at NDcovid19response@ndlf.com or visit us at www.newmeyerdillion.com/covid-19-multidisciplinary-task-force/.
Rhonda Kreger is Senior Counsel on Newmeyer Dillion's transactional team at our Newport Beach office. Her practice focuses on all aspects of commercial real estate law, with a particular emphasis on the representation of residential developers, merchant builders and institutional investors. You can reach Rhonda at rhonda.kreger@ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
Wendel Rosen’s Construction Practice Group Welcomes Quinlan Tom
January 06, 2016 —
Garret Murai – California Construction Law BlogThere’s been more cheer than usual at Wendel Rosen’s Construction Practice Group this holiday season.
Earlier this month, Quinlan Tom, a construction and business attorney, joined us from McInerney & Dillon, a venerable and well-respected construction boutique firm (we know a lot of folks there) with local roots like us in Oakland, California. We’ve all known Quinlan for a while, so when he decided to join our band of merry legal practitioners, we were quite thrilled.
Being lawyers though, and better at asking than answering questions, we decided to pose a few questions to Quinlan:
Q. So, you’ve just been sworn to tell the truth, the whole truth, and nothing but the truth, under penalty of perjury. So, tell us about your practice.
A. Let me just start with it’s quite an honor to appear in your blog; I’ve been a reader for a while (in secret of course before I got to Wendel Rosen). I’m also excited to join you and the other members of Wendel Rosen’s Construction Practice Group; as you mention, I’ve known each of you professionally for quite some time and respect each of you tremendously.
I started as a construction litigator right out of law school. I completed three years of mechanical engineering at UC Davis and put that on my resume when I was looking for a job after law school. (In addition, my dad retired after 40 years in the trenches as a union electrician). McInerney & Dillon (“M&D”) and a couple of other firms found that interesting and I ended up starting with M&D. I did find that my engineering studies helped with my acclimation to construction disputes. While I never pretend to be an engineer, it has provided me with a foundation of how the construction process works and how the projects are designed. 26 years later, I continue to enjoy counseling my clients in their construction disputes/issues and still find each construction project I am involved with fascinating.
I have tried, arbitrated and litigated cases for 26 years, from the United States District Court to the California Superior Court and the California Office of Administrative Hearings. I have argued cases before the Ninth Circuit Court of Appeals and the California Court of Appeal. I counsel my clients into hopefully making the best business decisions available melding the knowledge I have gleaned from my litigation experience with their financial and personal goals.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Building in the Age of Technology: Improving Profitability and Jobsite Safety
June 10, 2019 —
Maria Laguarda-Mallo - Construction ExecutiveNew virtual design and construction (VDC) technologies are quickly shifting how the AEC industry is designing, documenting and building. From the use of new software, apps and laser scanners, to the deployment of drones and robots, many early adopters are benefitting from fully integrating these solutions into their workflows.
Virtual and Augmented Reality
In an industry where collaboration is becoming increasingly important, regardless of the firm size, VR is enabling stakeholders to “see” and “walk” through a building before ground is broken. In other words, teams can foresee issues, ask questions and provide feedback in the preconstruction phase.
The inclusion of AR and VR in the daily workflows of AEC firms signifies expedited decision-making, reduced rework and real-time collaboration, which in turn translates to a reduction of unexpected costs.
Reprinted courtesy of
Maria Laguarda-Mallo, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Ms. Laguarda-Mayllo may be contacted at
maria.laguarda-mallo@viatechnik.com