Wildfire Insurance Coverage Series, Part 7: How to Successfully Prepare, Submit and Negotiate the Claim
August 22, 2022 —
Scott P. DeVries & Yosef Itkin - Hunton Insurance Recovery BlogPrior posts in this series have discussed insurance coverage issues that pertain directly to wildfire claims, but we have not yet addressed how one proceeds following a loss. In this post in the Blog’s Wildfire Insurance Coverage Series, we discuss the preparation, submission and negotiation of the insurance claim.
Preparing a Claim
As different policies provide different timelines, where possible, it is advisable to submit the claim as soon as reasonably possible. Insurers commonly cite late submission as a basis for denial with jurisdictions varying on the import of “late” submission.
Insurers have a right to reasonable documentation of a claim before paying. Often, they will decline to consider a claim on its merits until such documentation is provided. The policy will specify whether to submit a hard copy or file online, but either way it is advisable to maintain a copy online or in a remote geographic location.
Reprinted courtesy of
Scott P. DeVries, Hunton Andrews Kurth and
Yosef Itkin, Hunton Andrews Kurth
Mr. DeVries may be contacted at sdevries@HuntonAK.com
Mr. Itkin may be contacted at yitkin@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
CC&Rs Not the Place for Arbitration Agreement, Court Rules
May 24, 2011 —
CDJ STAFFIn January, the California Court of Appeals ruled that an arbitration clause inserted in a development’s CC&Rs by the developer could not be enforced. The case, Villa Vicenza Homeowners Association v. Noble Court Development, involved a case in which, according to the opinion, “following the first sale Nobel controlled the board of directors of the Association and because the initial condominium buyers noticed defects in common areas and common facilities and did not believe Nobel had provided a reserve fund sufficient to repair the defects, the condominium owners brought a derivative action on behalf of the Association against Nobel.”
The court concluded, “The use of CC&R's as a means of providing contractual rights to parties with no interest in or responsibility for a common interest development is also problematic from the standpoint of determining what if any consideration would support such third-party agreements. By their terms the CC&R's bind all successors, even those with whom a third party such as Nobel has never had any contractual relationship and to whom Nobel has not provided any consideration.” The court determined that “the trial court did not err in denying Nobel's motion to compel arbitration.”
Read the court’s decision
Read the court decisionRead the full story...Reprinted courtesy of
Bill Introduced to give Colorado Shortest Statute of Repose in U.S.
January 21, 2015 —
Jesse Howard Witt – Acerbic WittYesterday, State Senator Ray Scott (R-Mesa County) introduced a bill to shorten Colorado’s already short statute of repose. If this bill passes, it will severely undermine the rights of Colorado homeowners.
Colorado already has one of the shortest construction defect statutes of repose in the United States. If a homeowner does not discover a defect within six years of a house’s completion, the homeowner may forfeit all legal rights to seek repairs. Senator Ray’s bill would cut this time in half and could preclude homeowners from obtaining any relief three years after a home is built. No other state in America has such a severe limit on homeowner rights.
Read the court decisionRead the full story...Reprinted courtesy of
Jesse Howard Witt, The Witt Law FirmMr. Witt welcomes comments at www.wittlawfirm.net
Cross-Office Team Secures Defense Verdict in Favor of Client in Asbestos Case
November 18, 2024 —
Lewis Brisbois NewsroomSt. Louis/Kansas City, Mo. (October 23, 2024) - St. Louis Partners Tracy J. Cowan and Karen M. Volkman, along with Kansas City Partner Vincent Gunter, secured a defense verdict in a Jackson County, Missouri matter on behalf of a Lewis Brisbois client, which was the successor-in-interest to a life, health and reinsurance firm, against claims brought by an individual who worked in the corporate headquarters and was diagnosed with mesothelioma.
Background
The plaintiff was 62 years old when she was diagnosed with mesothelioma. She worked as a clerk for several years in the 1970s in a 19-story office building that opened in 1963. The plaintiff claimed construction work being performed in the areas where she worked exposed her to asbestos from above the suspended ceiling. The beams and girders in the building were fireproofed with sprayed-on insulation. Although the plaintiff did not perform any maintenance work, she relied on evidence from several operating engineers who worked above the ceiling near the fireproofing to establish the presence of asbestos in the building. The plaintiff submitted claims for negligence and unsafe workplace. At the beginning of trial, the LBBS client had a pending motion for summary judgment on the grounds that the plaintiff’s exclusive remedy was governed by the Missouri Workers’ Compensation Law. The Court denied a motion to continue the trial and submitted the workers’ compensation issue as an affirmative defense.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
Court Orders House to be Demolished or Relocated
April 26, 2011 —
Beverley BevenFlorezCDJ STAFFDecision Affirmed in Central Arkansas Foundation Homes, LLC v. Rebecca Choate
The Arkansas Court of Appeals affirmed the decision by the trial court in Central Arkansas Foundation Homes, LLC v. Rebecca Choate. In the trial case, Central Arkansas Foundation Homes (CAFH) sought payment for a home built for Choate, while Choate alleged that the builders committed multiple construction defects including using the wrong foundation materials and positioning the house in the wrong direction.
After the house was built, CAFH contacted Choate regarding payment, however, Choate alleged that the finished product did not match the contract. “ After CAFH completed construction, it obtained permanent home financing for Choate and tried to contact her to close the transaction. Choate did not respond until October 2005, when she sent CAFH a list of alleged construction defects, including that the house was facing in the wrong direction; that it was not built on a slab; and that the fireplace, garbage disposal, driveway, and storage area were missing. CAFH replied to Choate in writing, telling her that she had until January 6, 2006, to close on the house or CAFH would sell it. The correspondence enclosed worksheets showing that the amount Choate would owe at closing exceeded $94,000, which included interest that had accrued on the as-yet unpaid construction loan.”
Initially, the court found in favor of CAFH. “On April 18, 2007, Choate’s attorney withdrew from representing her. Soon thereafter, CAFH’s attorney asked the court to set a final hearing on the case. The attorney purportedly sent Choate a letter by regular mail on May 15, 2007, advising her that the case was set for trial on July 9, 2007. Choate, however, did not appear. CAFH did appear, and its general manager, John Oldner, testified to events leading up to the case and the amount of damages claimed. According to Oldner, the interest on the construction loan had accrued to the point that CAFH now sought $104,965.88 from Choate. The court found in favor of CAFH and entered judgment for that amount, plus attorney fees, on July 18, 2007. The court ruled that CAFH could sell the house and either remit any excess to Choate or look to Choate for the deficiency if the sales price did not cover the judgment.”
However, Choate successfully argued that she did not receive notice of the trial. A new trial was ordered, and the outcome was quite different. “On June 6, 2008, the circuit court entered judgment for Choate, ruling that the house was not in substantial compliance with the parties’ contract and that the contract should be rescinded. The court found that the house suffered from numerous construction defects, that the contract contemplated a slab rather than a concrete-pier foundation, and that CAFH ignored Choate’s complaints that the house was facing the wrong way. The judgment directed CAFH to hold Choate harmless on the construction loan, to deed Choate’s two acres back to her, and to remove the house from Choate’s property.”
The Court of Appeals “found that Choate would be unjustly enriched by retaining the benefit of the septic systems and utility lines that CAFH installed on her land. The court therefore awarded $5340 to CAFH as a quantum-meruit recovery for the value of that work. CAFH contends that the award is not sufficient, but we see no clear error.” In the end, the Court of Appeals provided this reason for declining to reverse the trial court’s decision: “The court in this case apparently concluded that the house constructed by CAFH was so fundamentally at odds with Choate’s contractual expectations that she was not unjustly enriched and should simply be, as nearly as possible, returned to the status quo ante. Accordingly, the court ordered the house removed from her property and permitted CAFH to either relocate the house or salvage the house’s materials and unused appliances. We decline to reverse the court’s weighing of the equities in this manner.”
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Fed. Judge Blocks Release of Records on FIU Bridge Collapse, Citing NTSB Investigation
October 23, 2018 —
Miami Herald - Engineering News-RecordOct. 05 --A federal judge Friday blocked the release of documents that could shed light on why a busy road outside Miami was not shut down before a brand-new bridge developing severe cracks collapsed and killed six people.
Judge William Stafford said the National Transportation Safety Board , the federal agency investigating the Florida International University bridge disaster, "was exercising its valid federal regulatory authority" in keeping the documents confidential from the media.
Read the court decisionRead the full story...Reprinted courtesy of
Engineering News-RecordENR may be contacted at
ENR.com@bnpmedia.com
Code Changes Pave Way for CLT in Tall Buildings and Spark Flammability Debate
May 13, 2019 —
Sam Barnes - Construction ExecutiveAlthough nothing new, the debate over which is better as a building material—wood or concrete—intensified in December following the preliminary approval of new codes for cross-laminated timber and mass timber in tall structures.
The discussion among industry professionals has been less about CLT’s structural capabilities and more about its perceived flammability, with either side offering decidedly different perspectives. Comparatively new to the United States, CLT and mass timber products are constructed of several layers of pressed lumber board stacked in alternating directions.
In December, the International Code Council released the unofficial voting results on several code change proposals, including passage of the entire package of 14 tall mass timber codes. The proposals were presented by the ICC’s Ad Hoc Committee on Tall Wood Buildings, comprised mostly of engineers, architects, building and fire code officials, fire service, materials and testing lab representatives.
Reprinted courtesy of
Sam Barnes, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Congratulations to Haight’s 2021 Super Lawyers San Diego Rising Stars
May 03, 2021 —
Catherine M. Asuncion, Arezoo Jamshidi & Michael C. Parme - Haight Brown & Bonesteel LLPHaight congratulates partners Michael Parme and Arezoo Jamshidi and associate Catherine Asuncion who were selected to the 2021 San Diego Super Lawyers Rising Stars list.
Reprinted courtesy of
Catherine M. Asuncion, Haight Brown & Bonesteel LLP,
Arezoo Jamshidi, Haight Brown & Bonesteel LLP and
Michael C. Parme, Haight Brown & Bonesteel LLP
Ms. Asuncion may be contacted at casuncion@hbblaw.com
Ms. Jamshidi may be contacted at ajamshidi@hbblaw.com
Mr. Parme may be contacted at mparme@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of