Winning Attorney Fees in Litigation as a California Construction Contractor or Subcontractor
December 27, 2021 —
William L. Porter - Porter Law GroupThe General Rule in California: The Winner Does NOT Receive Attorney Fees and Costs:
There is a common misconception that court decisions require the loser in a lawsuit to reimburse the winner for the fees and costs incurred during the lawsuit. Reliance on this misconception in developing a legal strategy for dealing with disputes is a serious strategic error. Where the legal issue is, for example, “breach of contract,” the general rule in California is that there are only two methods by which the winning litigant will be awarded the attorney fees and costs incurred in bringing or defending the lawsuit. The first of these is if the contract in question contains an effective attorney fee clause specifically providing that the prevailing party will recover their attorney fees and costs. The second is if there is a statute on point which provides that the prevailing party will be awarded those fees and costs. The general rule in California is that each party pays their own attorney fees and costs, unless there is an independent legal basis that provides otherwise. This is known as the “American Rule,” used throughout most of the country.
The Issue is Important Because Spending More Money Than You Can Be Awarded is a Losing Strategy:
The importance of whether the prevailing party in a lawsuit will be awarded their fees and costs cannot be underestimated. The party contemplating whether to bring a lawsuit must seriously consider whether it is even worth the trouble. In many cases, unless the one bringing the lawsuit (the “plaintiff”) is entitled to be reimbursed for the considerable attorney fees and costs incurred in bringing the case, it is just not worth doing so. There is no point spending $50,000 on attorneys on a $40,000 claim unless the plaintiff can be awarded both the $40,000 and the $50,000 if the plaintiff wins. Unless fees and costs are awarded, the plaintiff will still be out $10,000 in the very best of cases. For a party sued (the “defendant”) a similar situation arises in that the defendant faces the reality that it may be less expensive to just pay on a frivolous or false claim than to fight it. Either scenario is unsatisfactory. On the whole, it is beneficial to have an attorney fee clause in a contract when either a plaintiff or a defendant must vindicate its rights. Both deserve to be fully compensated to achieve justice. It is also beneficial to have an attorney fee clause in a contract to encourage the one who is at fault to resolve the case rather than risk paying the fees and costs of the other party who is likely to win the case. In either case, the presence of an attorney fee clause facilitates the party in the right and encourages resolution outside of litigation. These are admirable societal goals.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Now Available: Seyfarth’s 50 State Lien Law Notice Requirements Guide (2023-2024 Edition)
December 23, 2023 —
Seyfarth Shaw LLPSeyfarth’s Construction team is pleased to announce the release of our 2023-2024 edition of the 50 State Lien Law Notice Requirements Guide. The Guide provides the general time requirements for filing lien notices in each state, plus Washington, DC.
Reprinted courtesy of
Seyfarth Shaw LLP
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Big League Dreams a Nightmare for Town
April 03, 2013 —
CDJ STAFFThe town of Gilbert, Arizona had their own big dreams for Big League Dreams Gilbert, which the town was convinced would bring in financial benefits. Now the amateur sports complex is plagued by defects and failing infrastructure. The town was wondering how to create sufficient recreation facilities when Big League Dreams made a proposal that would bring tax revenue from a new stadium complex.
Ten years later, Gilbert says it’s not getting enough of the revenue from the parks. The proposal, created by Big League Dreams, estimated an economic benefit of $40 million over 30 years with a construction cost of $22.7 million. Instead, construction ran to $42.7 million and over the last two years the town has received only $250,570.
Then there are the construction defects. The structure was warranteed for only one year. That warrantee long over, the complex has problems with various concrete surfaces and has generated injury claims. The town did not inspect the park after Big League Dreams started operating it. They later found out that some parts did not conform to code, with 39 problem areas referenced in a report. Some of these included safety issues like missing handrails.
Read the court decisionRead the full story...Reprinted courtesy of
COVID-19 Response: California Occupational Safety and Health Standards Board Implements Sweeping New Regulations to Prevent COVID-19 in the Workplace
December 14, 2020 —
Peter Shapiro, Drake Mirsch & Jade McKenzie - Lewis BrisboisOn November 19, 2020, the California Occupational Safety and Health Standards Board (OSHSB) proposed sweeping and significant new emergency standards to reduce employee exposure to COVID-19. These standards have been accepted by the Office of Administrative Law and are effective as of November 30, 2020. Accordingly, it is critical that employers familiarize themselves with these new requirements and begin to implement these standards as quickly as possible.
The standards include COVID-19 prevention in the workplace, multiple COVID-19 infections and outbreaks in the workplace, “major” COVID-19 outbreaks in the workplace, prevention in employer provided housing, and prevention in employer-provided transportation to and from work. They apply to all California employers and places of employment, except places with one employee who does not have contact with others, employees working from home, or employees in specified health care facilities, services or operations when covered by section 5199.
COVID-19 Prevention Program
Employers are required to establish, implement, and maintain an “effective” written COVID-19 Prevention Program. Under the Program, an employer is responsible for developing a system for communicating about COVID-19, identifying and evaluating COVID-19 hazards, investigating and responding to COVID-19 cases, correcting COVID-19 hazards, providing training and instructions to employees regarding COVID-19, ensuring all employees are physically distanced, providing face coverings, implementing policies regarding personal protective equipment and recordkeeping, ensuring COVID-19 cases are excluded from the workplace, and prohibiting symptomatic employees from returning to work unless certain requirements are met.
Reprinted courtesy of
Peter Shapiro, Lewis Brisbois,
Drake Mirsch, Lewis Brisbois and
Jade McKenzie, Lewis Brisbois
Mr. Shapiro may be contacted at Peter.Shapiro@lewisbrisbois.com
Mr. Mirsch may be contacted at Drake.Mirsch@lewisbrisbois.com
Ms. McKenzie may be contacted at Jade.Mckenzie@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Challenging and Defending a California Public Works Stop Payment Notice: Affidavit vs. Counter-Affidavit Process
October 21, 2019 —
William L. Porter - Porter Law GroupOne of the most effective collection procedures available to subcontractors and suppliers to California Construction projects is the “stop payment notice” procedure found under California Civil Code sections 9350 – 9364. Under this procedure, the unpaid subcontractor or supplier may serve the stop payment notice on the public entity and the direct or “prime” contractor and cause the public entity to withhold from the direct contractor 125% of the funds identified in the stop payment notice. Thereafter, funds will not generally be released unless the parties reach a settlement agreement or the issue is decided through litigation, arbitration or mediation. There is however an alternative procedure available to direct contractors to expedite the determination of whether a stop payment notice is valid and to possibly obtain an early release of the funds withheld by the public entity. This “summary proceeding” process could result in release of funds to the direct contractor in less than 30 days. The summary proceeding can also be challenged by the unpaid subcontractor or supplier. All public works contractors, subcontractors and suppliers should be aware of the process. The process for direct contractors to release a stop payment notice and for subcontractors and suppliers to challenge the process works as follows:
After a California stop payment notice has been served and the public entity has withheld funds accordingly, the direct contractor may challenge the stop payment notice by serving an “affidavit” (basically a sworn statement showing why the stop notice is not valid) on the public entity, demanding that the public entity release all funds withheld. Upon receipt of such an affidavit, the public entity will serve the subcontractor or supplier who served the stop payment notice with a copy of the affidavit, along with a “demand for release of funds”. If the stop payment notice claimant does not respond with a “counter-affidavit” by the date stated on the notice sent by the public entity (“not less than 10 days nor more than 20 days after service on the claimant of a copy of the affidavit”), then the public entity will be within its rights to release the withheld funds to the direct contractor, and the stop payment notice claimant will relinquish its stop payment notice rights.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Harmon Towers Demolition Still Uncertain
January 23, 2013 —
CDJ STAFFIt would be a "gift" to MGM Resorts if they were able to tear down the Harmon Tower, according to an article in the New York Times, as analysts are cited that a hotel would "struggle during this economic downturn." Further, William Robinson, a professor of economics at the University of Nevada, Las Vegas, noted that "MGM has tried to cut back on the whole project," adding that "if you are a conspiracy theorist, you thin they are just looking for a way to get out of it." Professor Robinson thinks they would be unlikely to rebuild if allowed to tear down the building.
MGM Resorts has a different take on the matter. Alan M. Feldman, MGM's senior vice president for public affairs, told the New York Times that MGM "had a contract with Perini that we would pay them to give us a certain kind of building type — in this case a luxury hotel." Mr. Feldman contends that Perini had not "kept up their part of the bargain." Perini has stated that the fault was due to the designers and did not comment to the Times.
The claims of design and construction defects have left the building unfinished, with only twenty-six of the planned forty-nine floors constructed. Perini contends the building can still be repaired. MGM that its remediation plan is "to take the building down."
Read the court decisionRead the full story...Reprinted courtesy of
My Construction Law Wish List
December 31, 2014 —
Garret Murai – California Construction Law BlogI’ve been good this year.
Not great mind you, but good, and good is the standard, right?
So, here’s my construction law wish list this holiday season:
1.More Transparency. So much uncertainty and resultant litigation exists for the simple reason that contractors and subs don’t know when a higher tiered contractor or owner (on a lender financed project) has been paid for their work. So how about a requirement that owners, contractors and subcontractors of all tiers be required to disclose when payment applications are submitted, when payments are made and in what amount, and what pay applications have been paid. And because I’m pretty sure I’m at least within the 20th percentile of “good” this year how about a requirement that this information be provided through an online database accessible by all persons working on projects valued at over a certain dollar amount, say $500,000.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
The 2017 ASCDC and CDCMA Construction Defect Seminar and Holiday Reception
November 21, 2017 —
Beverley BevenFlorez-CDJ STAFFThe annual Construction Defect Seminar and Holiday Reception presented jointly by the Association of Southern California Defense Counsel (ASCDC) and the Construction Defect Claims Managers Association (CDCMA) takes place this November 30th at the Hilton Costa Mesa. This one-day seminar includes two sessions: Session 1, Recent developments in Insurance Coverage and Related Impacts on Case Resolution; Session 2, Impact of Design Claims in Construction Defect Actions. A holiday reception will immediately follow the seminar.
The keynote speaker this year is Hon. Charles Margines, Presiding Judge of the Orange Superior Court. Other speakers include David Napper, Esq., of Chapman Glucksman Dean Roeb & Barger, Adrienne Cohen, Esq., Law Offices of Adrienne D. Cohen, Blenda Eyvazzadeh, Chub North American Claims, and many others. This activity has been approved for Minimum Continuing Legal Education Credit by the State Bar of California in the amount of 3.0 hours.
November 30th, 2017
Hilton Costa Mesa
3050 Bristol Street
Costa Mesa, California 92626
United States
PDF Registration...
Online Registration...
Read the court decisionRead the full story...Reprinted courtesy of