12 Newmeyer Dillion Attorneys Named to 2022 U.S. News Best Lawyers in Multiple Practice Areas
August 23, 2021 —
Newmeyer DillionProminent business and real estate law firm Newmeyer Dillion is pleased to announce that twelve of the firm's attorneys were recently selected for inclusion and will be recognized in their respective areas in The Best Lawyers in America© 2022. Additionally, Greg Dillion has been selected to Best Lawyers 2022 Lawyer of the Year list in Construction Law.
The twelve 2022 Best Lawyers are:
Jason Moberly Caruso,
Michael S. Cucchissi,
Jeffrey M. Dennis,
Greg L. Dillion,
Joseph A. Ferrentino,
Jon J. Janecek,
Michael B. McClellan,
Thomas F. Newmeyer,
John A. O'Hara,
Thomas H. Reilly,
Bonnie T. Roadarmel and
Jane M. Samson
Best Lawyers is the oldest peer-review publication for the legal profession. Attorneys are chosen through intensive peer-review surveys in which leading lawyers evaluate their professional peers. Best Lawyers listings are published in almost 70 countries worldwide and are recognized for their reliable and unbiased selections.
About Newmeyer Dillion
For over 35 years, Newmeyer Dillion has delivered creative and outstanding legal solutions and trial results that achieve client objectives in diverse industries. With over 60 attorneys working as a cohesive team to represent clients in all aspects of business, employment, real estate, environmental/land use, privacy & data security and insurance law, Newmeyer Dillion delivers holistic and integrated legal services tailored to propel each client's operations, growth, and profits. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California and Nevada, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949.854.7000 or visit www.newmeyerdillion.com.
Read the court decisionRead the full story...Reprinted courtesy of
New York Appellate Court Applies Broad Duty to Defend to Property Damage Case
January 03, 2022 —
Craig Rokuson - Traub Lieberman Insurance Law BlogIn the recent case of New York Marine and Gen. Ins. Co. v. Eastman Cooke & Associates, 153 N.Y.S.3d 840, 841 (N.Y. App. Div. 1st Dept. 2021), New York’s first department affirmed a duty to defend under New York law. In the underlying action, the plaintiff alleged property damages due to prolonged construction work in a different unit of the subject property. The underlying plaintiff sued the owner of the subject property, which in turn sued Eastman Cooke, the general contractor at the premises. New York Marine denied coverage to Eastman Cooke, asserting that the underlying suit did not seek damages occurring during the New York Marine policy period, and commenced a declaratory judgment action.
The trial court held—and the First Department affirmed—that New York Marine has a duty to defend Eastman Cooke. Initially, the court found that the underlying suit alleged property damage as required for coverage, because there were allegations regarding loss of use of the property. The court also found that the underlying suit alleged damages occurring during the New York Marine policy period. Although the underlying complaint alleged that the underlying plaintiffs were reimbursed for damages occurring during the New York Marine policy period by another insurer, the court held that the evidence was that the payments only covered a certain part of the damages sought. Accordingly, because there was a reasonable possibility that some unreimbursed damages may fall within the New York Marine policy period.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Rokuson, Traub LiebermanMr. Rokuson may be contacted at
crokuson@tlsslaw.com
Preserving Your Construction Claim
February 18, 2015 —
Craig Martin – Construction Contractor AdvisorA recent article in the Construction Executive discussed the importance of preserving your claim, both in terms of timeliness of submitting your claim and making sure that you aren’t waiving portions of your claim when executing releases. These are all excellent points and bear some follow-up.
Timing Your Claim
I often review construction contracts that contain deadlines by which claims must be submitted. It may seem counter intuitive to think that you need to submit a claim when you are discussing the basis for the claim with an upstream contractor or the owner. But, there are more cases than I care to count where a contractor’s claim has been denied because the claim was not timely submitted.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Orange County Team Obtains Unanimous Defense Verdict in Case Involving Failed Real Estate Transaction
March 25, 2024 —
Lewis Brisbois NewsroomOrange County, Calif. (March 4, 2024) - Orange County Partners Esther P. Holm and Alexandra Anast obtained a unanimous defense verdict in a real estate matter involving a failed real estate transaction. The property at issue, which was located in the West Hollywood Hills and had beautiful views, was undergoing extensive remodeling. There were several bids for its purchase. Ultimately, the plaintiff, a real estate investor, was awarded the purchase.
The plaintiff and the seller entered into a real estate purchase agreement, but the plaintiff failed to release the physical contingencies within the 17-day period prescribed by the contract. Instead, the plaintiff demanded a reduction in price, which the seller rejected. The plaintiff then filed a lis pendens on the property, clouding the title and making it impossible for the sellers to sell the property to anyone else. The buyer and seller subsequently engaged counsel. The plaintiff filed the lawsuit against the seller as well as the real estate company and its agents. Prior to trial, the plaintiff and the seller reached a settlement.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
The Risk of A Fixed Price Contract Is The Market
August 03, 2022 —
David Adelstein - Florida Construction Legal UpdatesWhen performing work on a fixed price or unit, there is risk that is being assumed on your end. One risk is the market. You are ultimately banking on the fact that the market is not going to make your fixed prices unprofitable. That’s not an unforeseeable occurrence because the market shifts and that shift can have a negative ripple effect.
In a recent case out of the Federal Circuit, U.S. Aeroteam, Inc. v. U.S., 2022 WL 243176 (Fed.Cir. 2022), this market risk played a role in a fixed price contract. Here, a contractor was hired by the federal government to produce ground support trailers. A key component of these trailers was a running gear. The contractor relied on a vendor for these running gears. Due to financial difficulties, the vendor had to raise its unit price for the running gears. Based on the increased price, the contractor elected to manufacture the running gears itself. The contractor asked the government if this was ok and the government approved the request. Once the contractor started manufacturing these running gears, it had an “awe” moment – the manufacturing costs were higher than anticipated. The contractor submitted a request for equitable adjustment which the government denied. The Contractor than sued the government raising three arguments to support its entitlement to additional costs: (1) constructive change; (2) cardinal change; and (3) commercial impracticability. The contractor lost on all arguments. It probably should have lost on all arguments.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Meet the Hipster Real Estate Developers Building for Millennials
October 02, 2015 —
Ben Steverman – BloombergJohn Chaffetz is showing off an apartment building that his development firm, Timberlane Partners, just bought for $7.2 million. He admits it doesn’t look so hot. “This has been treated like a prison camp,” he says of the 32-unit building in Los Angeles’s Echo Park neighborhood. Steel bars stick out of a cinder-block fence, threatening to impale someone. The front door is an ugly metal gate.
But an organic supermarket opened around the corner in November, and a Blue Bottle Coffee just arrived down the block. There’s a farmers market nearby each Friday, and five minutes up Sunset Boulevard is the Silver Lake neighborhood, a nest of hipster cafes and places to buy rare cheese and handmade clothes. Timberlane plans to tear down the building’s security fencing, put terracotta back on the roof, and repair windows that date to its pre-1930 construction. “The goal,” Chaffetz says, “is for this to look like a Moroccan boutique hotel.”
Read the court decisionRead the full story...Reprinted courtesy of
Ben Steverman, Bloomberg
New Megablimp to Deliver to Remote Alaskan Construction Sites
January 13, 2017 —
Ryan W. Sternoff - Ahlers & Cressman PLLC BlogFor nearly 20 years, Lockheed Martin has been working on developing a “Hybrid Airship” that may transform the ability to construct facilities in remote project locations.[i]
On September 13, 2016, the Daily Journal of Commerce reported that the first of these “Hybrid Airships,” which can land in snow, ice, gravel, and water, are set to deliver from a facility operated by PRL Logistics in Kenai, Alaska, beginning in 2019.[ii] PRL will be operating the blimps in partnership with UK-based Straightline Aviation who placed the first order for the airships this year. According to PRL, the hope is that the airships will provide low cost solutions for moving freight in Alaska, where runways and roads are not always available. The helium-lifted behemoth blimps have space for 47,000 pounds of cargo and 18 passengers and cost about $40 million dollars.
Read the court decisionRead the full story...Reprinted courtesy of
Ryan W. Sternoff, Ahlers & Cressman PLLCMr. Sternoff may be contacted at
rsternoff@ac-lawyers.com
Montana Supreme Court Tackles Decade-Old Coverage Dispute Concerning Asbestos Mineworker Claims
December 20, 2021 —
Patricia B. Santelle & Paul A. Briganti - White and WilliamsOn November 23, 2021, the Montana Supreme Court issued an almost unanimous decision in National Indemnity Company v. State of Montana, a ten-year-old coverage dispute arising from claims against the State of Montana alleging it had failed to warn of asbestos dust conditions at vermiculite mining and milling operations in and around Libby, Montana (the Libby Mine) run by W.R. Grace & Company and its predecessors. Affirming in part and reversing in part rulings by the trial court that culminated in a $98 million judgment against the State’s CGL insurer from 1973 to 1975, the court addressed issues including the duty to defend/estoppel, the number of occurrences, “trigger of coverage,” and, in a case of first impression, allocation under Montana law.
Whether the Insurer Breached the Duty to Defend Depended Upon the Timeframe
The court looked at whether (1) the insured provided sufficient information to bring the claims within the possibility of coverage under the subject policy and (2) the insurer gave “the necessary substance to” fulfilling its duty to defend at four points in the relevant timeframe:
- The insurer did not breach its duty at the time the State initially tendered the Libby Mine claims because the State defended the claims through its self-insurance program, hired its own counsel, managed the litigation, made its own defense decisions, and took the position with the insurer that the matter was “under control” and “nothing was left to be done[.]”
Reprinted courtesy of
Patricia B. Santelle, White and Williams and
Paul A. Briganti, White and Williams
Ms. Santelle may be contacted at santellep@whiteandwilliams.com
Mr. Briganti may be contacted at brigantip@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of