Roadway Contractor Owed Duty of Care to Driver Injured Outside of Construction Zone
January 04, 2021 —
Garret Murai - California Construction Law BlogFor the roadway contractor it appeared to be an open and shut case:
Plaintiff car driver was stopped at a standard one-way “reversing lane closure” traffic control in which traffic going in one direction would be stopped while traffic going in the other direction was allowed to proceed, and then the procedure would be reversed.
Plaintiff, while stopped at the traffic control, was rear-ended by another vehicle driven by George Smithson. Smithson testified that he “must have looked off to the side” at some point prior to the collision because he did not see plaintiff’s vehicle before hitting it. He also testified that the primary reason the accident happened was that he was not paying attention and that he knew of no other cause of the accident.
For the roadway contractor you couldn’t ask for a better admission. And it ended in the trial court just the way you thought it would, with a win for the roadway contractor. That is, until it was appealed.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
HOA Foreclosure Excess Sale Proceeds Go to Owner
August 15, 2022 —
Ben Reeves - Snell & Wilmer Real Estate Litigation BlogOver the last few years, the Arizona Court of Appeals wrestled with the question of who should receive the excess proceeds from a foreclosure sale. We’ve blogged about some these past unreported decisions
here and
here. Those decisions, somewhat inexplicably, required excess sale proceeds to be paid to senior creditors. As we noted at the time, these unreported (and non-precedential) decisions did not seem to make much sense in the context of debtor/creditor rights. Thankfully, a reported opinion finally sets the record straight. Excess sale proceeds should be paid downstream.
In
Tortosa Homeowners Assoc. v. Garcia, et al., No. 2 CA-CV 2021-0114 (Ct. App. Aug. 1, 2022), the Court of Appeals held that after the foreclosing lienholder is paid in full, then the excess sale proceeds should be paid to claimants in the order of their priority after the foreclosing lienholder. In other words, if a junior lienholder forecloses, then any creditors behind (i.e., junior to) the foreclosing creditor should be paid, and if all such creditors are paid, then the rest should be given to the owner. Creditors senior to the foreclosing creditor should not be paid anything from the foreclosure sale. This makes sense from a policy perspective, because the senior creditor retains its lien against the property and the bidder presumably took the presence of the senior lien into account when it made its bid for the foreclosed property.
Read the court decisionRead the full story...Reprinted courtesy of
Ben Reeves, Snell & WilmerMr. Reeves may be contacted at
breeves@swlaw.com
Winter COVID-19 Relief Bill: Overview of Key Provisions
January 04, 2021 —
White and Williams LLPIn a much needed holiday gift for businesses and individuals who continue to be affected by COVID-19, Congress finally approved a $900 billion aid package follow-up to the CARES Act (the Winter Covid-19 Relief Bill), the several trillion dollar stimulus that was enacted early in the pandemic. The bill, part of the larger annual spending bill, will hopefully be signed into law by President Trump in the coming days although the President has indicated his disappointment about the small amount of direct relief to individuals included in the bill. The bill was passed by both houses of Congress by a veto proof majority and is expected to become law whether or not the President chooses to exercise his veto power.
White and Williams has and will continue to provide more detailed updates on important components of the legislation, some of which address matters beyond COVID-19-related relief and support, including a new Paycheck Protection Program and tax deductibility of expenses paid for with PPP funds, extension and expansion of the employee retention tax credit, direct payments to individuals, additional unemployment assistance, restrictions on surprise medical billing, rental assistance and extension of the eviction moratorium, education funding, vaccine distribution, testing and tracing, and other healthcare funding. In the meantime, here is a brief overview of several pieces of the legislation:
Paycheck Protection Program
The Winter COVID-19 Relief Bill provides for $284 billion of funding for a new round of the popular Paycheck Protection Program (PPP), which was established by the CARES Act and allowed borrowers to receive forgivable loans to be used to retain employees and cover certain other basic operating expenses. New and existing businesses may participate in the program. However, eligibility for PPP Part II is more restrictive and targeted then the original PPP.
Read the court decisionRead the full story...Reprinted courtesy of
White and Williams LLP
Surety Trends to Keep an Eye on in the Construction Industry
March 25, 2024 —
Oliver Craig - Construction ExecutiveReflecting on the dynamics of the 2023 construction and surety industries, it is evident that opportunities and challenges have emerged for contractors that will shape the landscape for the year ahead. Contractors can not only capitalize on these trends but protect the successful companies they have already built.
PROJECT OPPORTUNITIES
There has been a notable increase in public works opportunities, driven by increased government spending and the aging infrastructure in the United States. This trend is expected to continue in 2024 and beyond, with a notable portion of work coming in transportation- and public-utility-related infrastructure.
Due to increased spending, many contractors are reporting historically high backlogs—and that often includes the largest project their company has contracted in their history. While increased spending presents more opportunity, it’s critical contractors be even more diligent about new opportunities, giving additional consideration to the following:
Job Selection: New geographies, scope, project owners and/or subcontractor relationships commonly come with a learning curve. With the current state of the market, it’s not the ideal time to be learning costly lessons. Contractors should focus on having a proactive go/no-go strategy when reviewing potential projects to identify risks early and plan accordingly.
Reprinted courtesy of
Oliver Craig, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mechanics Lien Release Bond – What Happens Now? What exactly is a Mechanics Lien and Why Might it Need to be Released?
January 04, 2021 —
William L. Porter - Porter Law GroupMechanics Lien Release Bond – What Happens Now? What exactly is a Mechanics Lien and Why Might it Need to be Released?
California law entitles unpaid contractors, subcontractors, and material suppliers to record a mechanics lien on property where they performed work or supplied materials. The mechanics lien attaches to the real property as a legal interest and secures the right to payment for the work performed and materials supplied. If payment is not forthcoming the mechanics lien allows the property where the work was performed and materials supplied to be sold under court order to satisfy the debt. It is a powerful remedy against owners and their agents who do not pay for work performed and materials supplied to improve the owner’s property.
A Mechanics Lien Release Bond Frees Property from a Mechanics Lien
Owners typically do not wish to have their property sold out from under them. Fortunately for owners, there is a method by which a mechanics lien can be substituted for another interest and sale of the property thereby avoided. This method is through the use of a mechanics lien release bond. California Civil Code §8424 allows a property owner or contractor effected by a mechanics lien to record a mechanics lien release bond equal to 125 percent of the lien amount with the County Recorder where the mechanics lien has been recorded. The effect of this is to substitute the mechanics lien release bond for the mechanics lien itself, thereby relieving the property from the possibility of that property being sold to satisfy the debt. Instead, any payment made will come from the release bond.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Concrete Worker Wins Lawsuit and Settles with Other Defendant
December 04, 2013 —
CDJ STAFFHildo De Franca was injured in 2010 while pouring concrete for a residence in Perkasie, Pennsylvania. According to the lawsuit, when a concrete line plugged, the truck operator increased pump pressure, despite this not being the appropriate procedure. Mr. De Franca was injured when the hose snapped back after the clog burst free. Mr. De Franca sued both the Trans-Fleet Concrete Inc. and Albino Concrete Construction. Mr. De Franca was employed by a third party, Girafa Construction Inc., which had been hired by Albino.
Albino Construction settled with Mr. De Franca for $500,000. Trans-Fleet did not settle. The judgment against them was for $2.25 million, of which $2 million was for pain and suffering. As a result of the accident, Mr. De Franca suffered a mild brain injury and a compression fracture in his spine.
Read the court decisionRead the full story...Reprinted courtesy of
Dear Engineer: Has your insurer issued a “Reservation of Rights” letter? (law note)
April 20, 2017 —
Melissa Dewey Brumback - Construction Law in North CarolinaIn my previous post, I made reference to getting a “Reservation of Rights” letter. I noted that the carrier may decide to defend you under a Reservation of Rights (i.e., hire your lawyer) but may not, necessarily, accept the responsibility for paying the claim. Does this mean that the insurance company has denied your claim, or will never pay? No.
Reservation of Rights (ROR) letters are sent for a variety of reasons- most notably, when some portion of the construction lawsuit against you is not covered under your E&O policy. The letter must state the reason(s) that the ROR is being issued.
With the ROR, the insurance company is telling you that it reserves the right to withdraw from your defense and/or deny payment of damages at a later date, depending upon how facts in the case develop. The notice is intended to let you know that there *may* be issues later, and to put you notice that you have the right to hire your own lawyer (at your own expense) to protect yourself from that future potential risk.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale Liggett PLLCMs. Brumback may be contacted at
mbrumback@rl-law.com
Read Before You Sign: Claim Waivers in Project Documents
July 06, 2020 —
William E. Underwood - ConsensusDocsNot all claim waivers are appropriately titled “Waiver of Claims.” In fact, claim waivers can be found “hiding” without any advertisement or fanfare in a number of project documents, including change orders and applications for payment. So although getting work quickly approved and paid for is important, taking time to read the specific language in your project documents is just as important. Failure to pay close attention to this language could result in the waiver of key, unresolved project claims.
Further, and although it should go without saying, it is also just as important to read all of the terms of your contract. Important waiver language might not exist on the face of form project documents, but rather might be contained in the general and/or supplemental conditions of your contract and automatically incorporated into your form project documents. And these types of incorporated waivers can be just as enforceable.
So it is critically important to understand what you are signing and the implications it might have on future claims. This article will explore some of the common types of claim waivers that can be found in project documents so that you are better positioned to avoid inadvertently waiving claims in the future.
Read the court decisionRead the full story...Reprinted courtesy of
William E. Underwood, Jones Walker LLPMr. Underwood may be contacted at
wunderwood@joneswalker.com