Mondaq’s 2023 Construction Comparative Guide
February 27, 2023 —
Michael S. Zicherman - Peckar & AbramsonPeckar & Abramson partner
Michael S. Zicherman is the author of the United States chapter of
Mondaq‘s 2023 “Construction Comparative Guide.” The Guide provides an overview of some of the key points of construction law and practice and allows readers to compare regulatory environments and laws across multiple jurisdictions including Australia, Canada, Denmark, Ghana, India, Indonesia, Malaysia, Mexico, Qatar, Singapore, United Kingdom, United States, and United Arab Emirates.
Reprinted courtesy of
Michael S. Zicherman, Peckar & Abramson
Mr. Zicherman may be contacted at mzicherman@pecklaw.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Contractor’s Claim for Interest on Subcontractor’s Defective Work Claim Gains Mixed Results
April 27, 2020 —
John J. Gazzola, Associate, Pepper Hamilton LLP - ConsensusDocsThis case concerns calculation of a damages award to a general contractor, Skanska USA Building, Inc., on its claim for breach of contract against its masonry subcontractor, J.D. Long Masonry, Inc., arising from Long’s faulty construction of a masonry façade at a medical research facility in Baltimore. When the façade collapsed and Long failed to repair it, Skanska hired a replacement subcontractor, C.A. Lindman, to remediate Long’s defective work and filed suit against Long to recover the resulting damages. After the court granted Skanska’s motion for summary judgment as to liability, Skanska moved for summary judgment on the issue of damages, relying on the indemnification provision of the subcontract to seek compensatory damages, pre- and post-judgment interest, and litigation fees. In the subcontract, Long agreed to indemnify and hold Skanska harmless from all claims, losses, costs and expenses, including attorneys’ fees, arising before or after completion of Long’s work, caused by, arising out of, resulting from, or occurring in connection with Long’s performance of the work or breach of the subcontract.
The court first applied the terms of this provision to award Skanska compensatory damages, holding that Skanska was, as a matter of law, entitled to recover the amount of the Lindman subcontract and general conditions incurred to supervise remediation of Long’s work. The court, however, denied Skanska’s claim for pre-judgment interest on the entirety of these damages. Skanska asserted that it was entitled to pre-judgment interest on the full award, calculated from the date on which it first paid Lindman. The court disagreed, explaining that, under Maryland law, a claimant is entitled to an award of pre-judgment interest as of right only when the amount due is certain, definite and liquidated by a specific date prior to judgment. The court reasoned that, because much of the Lindman subcontract value was composed of later-executed change orders, an award of pre-judgment interest could not be uniformly calculated back to the date of Skanska’s first payment to Lindman. And moreover, because Skanska continued to withhold sums due to Lindman pending resolution of certain issues, awarding Skanska pre-judgment interest on amounts it had not yet paid would result in a “windfall” to Skanska because there was no “use of income” loss to be compensated.
Read the court decisionRead the full story...Reprinted courtesy of
John J. Gazzola, Pepper Hamilton LLPMr. Gazzola may be contacted at
gazzolaj@pepperlaw.com
Structural Failure of Precast-Concrete Span Sets Back Sydney Metro Job
February 23, 2017 —
Chris Webb - Engineering News-RecordA key component of Australia’s biggest public transport infrastructure project—Sydney’s $6.3-billion Metro North West—is the subject of a
critical and detailed technical report describing how an elevated viaduct span failed at a stitch joint between two precast segments during construction last September. Project officials say the affected span, which did not suffer a progressive collapse, has since been removed and its replacement fast-tracked to avoid further delays. Little additional detail was provided.
Read the court decisionRead the full story...Reprinted courtesy of
Chris Webb, ENRENR may be contacted at
ENR.com@bnpmedia.com
Real Estate & Construction News Roundup (7/17/24) – Housing Inflation to Remain High, Proptech Investment to Fall and Office Vacancy Rates to Reach Peak in 2025
August 26, 2024 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, construction backlog to see positives signs, regional banks to be conservative on buybacks, U.S. metro areas to permit few new housing units, and more!
- Venture capital investments in proptech and adjacent companies fell 14.3% in the first half of the year. (Leslie Shaver, Multifamily Dive)
- The expectation of interest rate cuts by the Federal Reserve later this year due to easing inflation and cooling economic growth is a positive sign for construction backlog. (Sebastian Obando, Construction Dive)
- The U.S. office real estate sector is now in three markets, each with different performance, but the overall office vacancy rate will reach a 21.6% peak in the second half of 2025. (Nish Amarnath, Construction Dive)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
The Word “Estimate” in a Contract Matters as to a Completion Date
February 12, 2024 —
David Adelstein - Florida Construction Legal UpdatesLanguage in a contract matters. The word “estimates” or “estimated” matters particularly when it comes to a date certain such as a substantial completion or completion date. Remember this.
Here is an example.
In Parque Towers Developers, LLC v. Pilac Management, Ltd., 49 Fla.L.Weekly D190a (Fla. 3d DCA 2024), a trial court held that the developer did not complete the construction of five condominium units by the date in the purchase agreements. The developer appealed because “[t]he agreements contain no date certain for the completion of the units, but rather include a clause that ‘Seller estimates it will substantially complete construction of the Unit, in the manner specified in this Agreement, by December 31, 2017, subject to extensions resulting from ‘Force Majeure (the ‘Outside Date’).’” Parque Towers, supra. Another provision in the purchase agreements stated, “[w]henver this Agreement requires Seller to complete or substantially complete any item of construction, that item will be understood to be complete or substantially complete when so completed or substantially completed in Seller’s opinion. Id.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
What Cal/OSHA’s “Permanent” COVID Standards Mean for Employers
March 06, 2023 —
Payne & Fears LLPEffective Feb. 3, 2023, California has implemented new, “permanent,” COVID-19 standards. The new regulations were adopted by Cal/OSHA on Dec. 15, 2022, but only became effective upon the review and final approval by the Office of Administrative Law. These non-emergency regulations—slated to remain in effect for two years—supplant the COVID-19 Prevention Emergency Temporary Standard (ETS) that have been in effect since early in the pandemic.
The non-emergency regulations abandon core parts of the ETS, include new definitions for key terms, and update requirements for important provisions. We discuss the primary changes below. The regulation itself is available online, as well as a copy provided by Cal/OSHA comparing the differences between the ETS and the new regulation.
An End to Exclusion Pay
The non-emergency regulations do not require employers to maintain exclusion pay (an excluded employee’s earnings, seniority, rights, and benefits). All that employers must do under the new regulations is inform confirmed COVID-19 cases and close contacts about potential COVID-19 benefits under federal or local laws (where applicable). This does not affect employees who may receive paid time off under other federal, state, and local laws, as well as through collective bargaining agreements or other employer policies.
Read the court decisionRead the full story...Reprinted courtesy of
Payne & Fears LLP
Construction Job Opening Rise in October
December 20, 2012 —
CDJ STAFFThere was a significant increase in the number of open construction jobs during October, according to a report for the National Association of Home Builders. Working from preliminary data provided by the Bureau of Labor Statistics, the NAHB said that the number of open positions reached “levels and rates last seen in 2007.” As the data is still preliminary, the NAHB noted that the conclusions should be taken with caution.
While there was a spike in job openings, the hiring of people to fill these positions hasn’t caught up with it, and there was a small decline in hires. But to return to the good news, there was also a drop in layoffs in that same period.
Through October, about 8,000 people have been hired in the construction sector. The NAHB notes that this does not correspond with the recent increases with home construction. They suggest that “it may be the case that startups in the home building and remodeling sectors are being missed by the establishment survey.” Another possibility they raise is that already-employed construction workers are simply working more hours.
Read the court decisionRead the full story...Reprinted courtesy of
When Does a Claim Against an Insurance Carrier for Failing to Defend Accrue?
November 07, 2012 —
David McLain, Colorado Construction LitigationThe following is an update on our December 20, 2010 article regarding United States Fire Insurance Company v. Pinkard Construction Company, Civil Action No. 09-CV-01854-MSK-MJW, and its underlying dispute, Legacy Apartments v. Pinkard Construction Company, Case No. 2003 CV 703, Boulder County Dist. Ct. That article can be found here.
The present action, St. Paul Fire and Marine Insurance Co., et al. v. The North River Insurance Co., et al., Civil Action No. 10-CV-02936-MSK-CBS, encompasses the coverage battle that ensued between Pinkard’s insurers, Travelers Indemnity Company of America (“Travelers”) and United States Fire Insurance Company (“USFI”), following the settlement of Legacy’s construction defect claims against Pinkard. A short history of the underlying facts is as follows:
In 1995, Pinkard constructed the Legacy Apartments housing complex in Longmont, Colorado. Following construction, Legacy notified Pinkard of water leaks associated with various elements of construction. Legacy ultimately filed suit against Pinkard in 2003, and would go on to clarify and amend its defect claims in 2004, 2006, and again in 2008. Following Pinkard’s notification of Legacy’s claims, USFI provided a defense to Pinkard, but Travelers refused to do so, on the purported basis that Legacy’s allegations did not implicate property damage under the terms of Travelers’ policy.
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain can be contacted at
mclain@hhmrlaw.com