Beverley BevenFlorez-CDJ STAFFCNN Money reported that more homeowners are deciding to keep their homes rather than sell, and become landlords instead. "Clients tell us all the time, 'We're never going to sell our home, even after we buy a new one,'" Glenn Kelman, CEO of the brokerage, Redfin, told CNN Money.
“The math works in most landlords' favor these days,” according to CNN Money. “Rents have risen by about 20% nationwide since mid-2006, the housing bubble peak, while home prices are still about 21% below what they were at that time.”
Read the court decisionRead the full story...Reprinted courtesy of
Application Of Two Construction Contract Provisions: No-Damages-For-Delay And Liquidated Damages
February 14, 2022 —
David Adelstein - Florida Construction Legal UpdatesA recent Florida opinion between a prime contractor and a Florida public body touches upon two important issues: (1) the application of a no-damage-for-delay provision; and (2) the application of a liquidated damages provision. Both provisions find there way into many construction contracts. Unfortunately, the opinion is sparse on facts. Nevertheless, the application of these provisions is worthy of consideration.
In this opinion, Sarasota County v. Southern Underground Industries, Inc., 2022 WL 162977 (Fla. 2d DCA 2022), a county hired a contractor to install sanitary and water piping underneath a waterway. During construction, a nearby homeowner complained that vibration from the drilling caused damage to his home. As a result, the county stopped the contractor’s work to address a potential safety issue, as it was contractually entitled to do. The contractor hired a structural engineer to inspect the house and the engineer issued a report determining that any alleged damage was cosmetic and that there was sufficient monitoring of the vibrations to prevent future damage. The contractor also had an insurance policy to cover any homeowner claim for damage. However, upon receipt of the engineer’s report, the county did not lift its stop work order. Rather, the stop work order remained in place for an additional 71 days.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Tejon Ranch Co. Announces Settlement of Litigation Related to the Tejon Ranch Conservation and Land Use Agreement
December 05, 2022 —
Tejon Ranch Co.TEJON RANCH, Calif., Nov. 30, 2022 (GLOBE NEWSWIRE) -- Tejon Ranch Co. is pleased to announce the resolution of a legal dispute involving the Tejon Ranch Conservancy and the signatories to the 2008 Tejon Ranch Conservation and Land Use Agreement (Agreement), namely, Audubon California, Endangered Habitats League, Natural Resources Defense Council, Planning and Conservation League, and the Sierra Club. The dispute stemmed from the signatories' participation in the Antelope Valley Regional Conservation Strategy (AVRCIS), which was subsequently used by the Center for Biological Diversity (CBD) and the California Native Plant Society (CNPS) to oppose Tejon Ranch Co.'s Centennial development.
The 2008 Tejon Ranch Conservation and Land Use Agreement has been widely hailed as a historic conservation achievement in preserving one of California's great natural and working landscapes. Tejon Ranch Co.'s agreement to conserve 90 percent of its landholdings pursuant to the Agreement is a monumental contribution to conservation in California. Tejon Ranch Co. continues to be a leader in balancing the stewardship of the ranch as a natural treasure for California and achieving economic opportunities for its shareholders. The Company demonstrated that leadership with the actions it took to enforce the terms of the Agreement, which led to this legal dispute.
As part of a settlement agreement, the Conservancy and the signatories dismissed with prejudice the lawsuit they filed. They also acknowledge that the AVRCIS does not contain the "best available scientific data" regarding Tejon Ranch Co.'s landholdings, and further, that they will not use, or support the use of, the AVRCIS or any other similar endeavors, to challenge Tejon Ranch Co.'s development projects and/or any Ranch uses consistent with the Agreement.
In turn, Tejon Ranch Co. released from escrow 50% of the advance payments it withheld under the terms of the Agreement. The remaining funds will be released over a three-year period as matching funds to monies raised by the Conservancy as well as others who participate in Conservancy capital raising programs, after which the remaining funds with be released to the Conservancy to further its mission. These funds are the final fulfilment of Tejon Ranch Co.'s full funding obligations under the Agreement, totaling $11,760,000 over the past 14 years, again demonstrating Tejon Ranch Co.'s commitment to fulfilling the implementation of the 2008 Tejon Ranch Conservation and Land Use Agreement.
All parties are glad to put this dispute behind them and move forward in a cooperative manner to achieve the goals envisioned in the historic 2008 Agreement.
About Tejon Ranch Co.
Tejon Ranch Co. (NYSE: TRC) is a diversified real estate development and agribusiness company, whose principal asset is its 270,000-acre land holding located approximately 60 miles north of Los Angeles and 30 miles south of Bakersfield. More information about Tejon Ranch Co. can be found on the Company's website at www.tejonranch.com.
Forward Looking Statements
This press release contains forward-looking statements, including without limitation statements regarding commitments of the parties under the settlement agreement and the achievement of certain goals related to Tejon Ranch Co.'s landholdings. These forward-looking statements are not a guarantee of future results, performance, or achievements, are subject to assumptions and involve known and unknown risks, uncertainties and other important factors that could cause the actual results, performance, or achievements to differ materially from those implied by such forward-looking statements. These risks, uncertainties and important factors include, but are not limited to, the ability and willingness of the parties to the Settlement Agreement to take the actions (or refrain from taking the actions) specified in the Settlement Agreement, and the risks described in the section entitled "Risk Factors" in our annual and quarterly reports filed with the SEC.
Read the court decisionRead the full story...Reprinted courtesy of
“You Can’t Make Me Pay!”
January 28, 2025 —
Daniel Lund III - LexologySeveral years ago, Louisiana enacted a law prescribing a mandamus proceeding for unpaid contract sums purportedly owed by a public entity to a contractor – Louisiana Revised Statute 38:2191. The statute tackles both progress payments and final payment, distinguishing between the two and allowing withholding of a progress payment when there is “reasonable cause” to do so.
On the other hand, at least one Louisiana appellate decision held on the topic of final payment: once a final payment amount is “due” per the statute – based upon passage expiration of the lien period following “formal final acceptance” – the act of making the final payment is purely ministerial and not subject to defenses. According to that court, a defense to payment based on assessed liquidated damages – because the damages were disputed by the contractor – could not trump the essence of the statute allowing the contractor to pursue mandamus to collect the final payment.
More recently, on a public works levee project in Lafourche Parish, a dispute arose during the work concerning the means to secure material for constructing the levees. The net effect of the dispute entailed a major change in the contract price.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Claims Litigated Under Government Claims Act Must “Fairly Reflect” Factual Claims Made in Underlying Government Claim
November 27, 2023 —
Garret Murai - California Construction Law BlogUnlike horseshoes and hand grenades, close sometimes isn’t close enough.
In the next case, Hernandez v. City of Stockton, 90 Cal.App.5th 1222 (2023), the Third District Court of appeal found that a pedestrian who sued a public entity for personal injuries caused by an “uplifted sidewalk” was barred from pursuing his claim when it was revealed that he had in fact injured himself by falling into a hole left by an “empty tree well” (i.e., a tree well that did not contain a tree”). According to the Court, the pedestrian’s claim was barred because the factual basis for recovery asserted in his complaint was not “fairly reflected” in his government claim.
The Hernandez Case
In April 2018, pedestrian Manual Sanchez Hernandez injured himself while walking on a public sidewalk in Stockton, California. He submitted a government claim with the City of Stockton claiming that his injuries, which included injuries to his knee, hands and back, was caused by a dangerous condition on public property. In his government claim, Hernandez alleged that he tripped on an “uplifted sidewalk” at or near 230 E. Charter Way in Stockton, California and that his injuries were due because the City “negligently and recklessly designed, maintained and operated the subject property so as to cause [his] injuries.”
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Europe’s Satellites Could Help Catch the Next Climate Disaster
February 15, 2021 —
Jonathan Tirone - BloombergSpain began the new year battling Storm Filomena, a once-in-a-generation weather event that blanketed Madrid in snow and paralyzed the economy. Health workers were stranded, supermarkets shut, and the army was called in. At least four people died.
“Now, consider a government or company that knew two weeks ago there was a risk that this would happen,” said Francisco Doblas-Reyes, a physicist at Barcelona’s Supercomputing Center. “Knowing the risk that a 1-in-20-year event was going to happen would have given more possibilities to prepare.”
Doblas-Reyes and his team are working on complex models that they hope can better detect the next Filomena, a job that’s become increasingly important as climate change makes weather more unpredictable — and extreme. The data collected by European satellites is at the heart of the continent’s multibillion-euro Destination Earth program seeking to develop the world’s best digital simulation of Earth.
Read the court decisionRead the full story...Reprinted courtesy of
Jonathan Tirone, Bloomberg
Occurrence-Based Insurance Policies and Claims-Made Insurance Policies – There’s a Crucial Difference
April 13, 2017 —
Garret Murai – California Construction Law BlogI’ve yet to find reading through an insurance policy on anyone’s “bucket list.”
But read them you should. Or have your attorney read through them (wink, wink).
Because when you need to tender a claim there’s probably no more important document in the world.
In Tidwell Enterprises, Inc. v. Financial Pacific Insurance Company, Inc., Case No. C078665 (November 29, 2016), a client whose attorney did read the policy, bested the insurer of a policy it issued.
Tidwell Enterprises, Inc.
In 2006 or 2007, Tidwell Enterprises, Inc. installed a fireplace at a single-family home located in Copperopolis, California. At the time, Tidwell had a general commercial liability policy issued by Financial Pacific Insurance Company, Inc. which expired in March 2010.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Failing to Pay Prevailing Wages May Have Just Cost You More Than You Thought
April 01, 2015 —
Garret Murai – California Construction Law BlogMechanics lien claims, payment bond claims, stop payment notice claims, delay claims, defect claims, abandonment claims . . .
With the variety of claims unique to construction projects it’s easy to forget that construction disputes are simply a category of business disputes in which broader business-related torts apply.
In Roy Allan Slurry Seal, Inc. v. American Asphalt South, Inc., Case No. B255558 (February 20, 2015), the California Court of Appeal for the Second District held for the first time that a second-place bidder on a public works contract may sue a winning bidder – who failed to pay its workers prevailing wages – under the business tort of intentional interference with prospective economic advantage.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at