Late Progress Payments on Local Public Works Projects Are Not a Statutory Breach of Contract
May 10, 2022 —
Ted Senet & Christopher Trembley - Gibbs GidenCalifornia local public agencies and their contractors should take note of a recent appellate decision pertaining to late progress payments on public works projects. In Clark Bros., Inc. v. North Edwards Water Dist., 2022 Cal. App. LEXIS 331, filed on April 22, 2022, the Court of Appeal for the Fourth Appellate District held that a local agency’s late progress payments to a general contractor did not constitute breach of contract under the prompt payment penalty statute, Public Contract Code § 20104.50. Notwithstanding this holding, the contractor recovered damages, interest, fees, and costs in excess of its contract amount.
In 2013, the North Edwards Water District awarded a $6.2 million contract to Clark Bros., Inc. to construct a water treatment facility. The District’s water contained excessive levels of arsenic, and the project was sponsored by the State of California with funds earmarked to provide safe drinking water. The State agreed to disburse funds to the District during construction upon the State’s review and approval of the contractor’s progress payment applications. The contract required completion of the work within one year following the District’s issuance of a notice to proceed to the contractor.
As a result of factors arguably outside the control of the contractor, including unforeseen site conditions and the failure of the District’s equipment supplier to meet delivery deadlines, the project was significantly delayed beyond the deadline for completion. The District nonetheless terminated the contractor, which in turn filed suit against the District and the State. The contractor asserted claims for breach of contract, including breach of contract for the District’s failure to pay the contractor’s progress payment applications within the time specified under Public Contract Code § 20104.50. Subsection (b) of the statute provides:
Any local agency which fails to make any progress payment within 30 days after receipt of an undisputed and properly submitted payment request from a contractor on a construction contract shall pay interest to the contractor equivalent to the legal rate set forth in subdivision (a) of Section 685.010 of the Code of Civil Procedure.
Reprinted courtesy of
Ted Senet, Gibbs Giden and
Christopher Trembley, Gibbs Giden
Mr. Senet may be contacted at tsenet@gibbsgiden.com
Mr. Trembley may be contacted at Ctrembley@gibbsgiden.com
Read the court decisionRead the full story...Reprinted courtesy of
Job Gains a Positive for Housing
October 15, 2014 —
Beverley BevenFlorez-CDJ STAFFThe National Association of Home Builders’ Eye on Housing reported that there were 248,000 net jobs created in September, according to the Bureau of Labor Statistics (BLS): “August gains were revised from a disappointing 142,000 to a slightly better 180,000, while July’s tally was also revised from 212,000 to 243,000.”
Furthermore, “September was a promising month for residential construction employment. The BLS data reveal that home builders and remodelers added 11,800 positions last month. Over the last year, residential construction employment has expanded by 129,000 jobs.”
Read the court decisionRead the full story...Reprinted courtesy of
Court Affirms Summary Adjudication of Bad Faith Claim Where Expert Opinions Raised a Genuine Dispute
July 06, 2020 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn 501 East 51st Street etc. v. Kookmin Best Ins. Co., Ltd. (No. B293605, filed 4/2/20, ordered pub. 4/16/20), a California appeals court affirmed summary adjudication and dismissal of a bad faith claim based on the genuine dispute doctrine.
501 East 51st Street Long-Beach-10, LLC (501) was the owner of a 10-unit apartment complex, insured by Kookmin Best. In 2017, an underground water main alongside the building burst which, according to 501, caused the building to move and crack. 501 made a claim and supplied a geotechnical report finding cracks in the foundation walls, cracks in the stucco and significant floor deformation and tilting near the water leak. The engineer’s opinion concluded that that “existing building distress was substantially contributed to by the water main break. The water introduced to the soil medium appears to have triggered differential foundation movement causing the stress features to develop.”
Kookmin retained its own engineers to investigate, who returned an opinion that the leak had exacerbated long-term pre-existing settlement which would continue. Under the policy, damage to the building caused by earth movement and settlement were excluded, but water damage resulting from an “accidental discharge” of water was covered. Kookmin then obtained an opinion from coverage counsel, who opined that only damage allocable to the water leak would be covered.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
California Booms With FivePoint New Schools: Real Estate
May 13, 2014 —
John Gittelsohn – BloombergFivePoint Communities Management Inc. is already constructing a school at its Great Park Neighborhoods project in Irvine, California, for 1,000 elementary and middle school students even as it’s still building the first 700 homes.
“We build the schools ahead of time,” said Emile Haddad, chief executive officer of Aliso Viejo, California-based FivePoint, which has permits for about 10,000 homes at Great Park. “That way we always have them ready.”
Local schools, along with parks and recreation facilities, have long been draws for buyers in new communities. Now, as school districts face tight construction budgets and homebuilders compete to attract families able to qualify for mortgages, developers are taking the lead on school construction instead of waiting for local governments to do the job.
Read the court decisionRead the full story...Reprinted courtesy of
John Gittelsohn, BloombergMr. Gittelsohn may be contacted at
johngitt@bloomberg.net
Update: Supreme Court Issues Opinion in West Virginia v. EPA
August 03, 2022 —
Anne Idsal Austin, Shelby L. Dyl & Sheila McCafferty Harvey - PillsburyTakeaways
- The Supreme Court sided with a coalition of states and coal mining companies constraining EPA’s ability to regulate CO2 emissions from power plants.
- The Supreme Court’s deployment of the “major questions doctrine” could have far-reaching implications for agencies’ authority to take actions that are politically and economically significant.
- The Court also announced a broad interpretation of standing, finding that the challengers could bring their suit notwithstanding EPA’s announced nonenforcement of the Clean Power Plan and intent to engage in a rulemaking to replace it.
Introduction
On June 30, 2022, the Supreme Court issued its opinion in West Virginia v. EPA, invalidating the 2015 Obama-era Clean Power Plan (CPP). Chief Justice John Roberts delivered the opinion of the court, holding that Section 111(d) of the Clean Air Act does not authorize EPA to devise emissions caps based on “generation shifting”—the approach EPA took in the CPP wherein power plants would be required to transition from higher-emitting (e.g., coal) to lower-emitting (e.g., natural-gas) to then even lower-emitting (e.g., wind and solar) electricity production.
The Court’s holding that the case was justiciable despite the Biden administration’s stated intent to repeal the Clean Power Plan and engage in a new rulemaking, as well as its deployment of the “major questions doctrine,” is likely to have far-reaching implications for legal challenges to all administrative agency actions.
Reprinted courtesy of
Anne Idsal Austin, Pillsbury,
Shelby L. Dyl, Pillsbury and
Sheila McCafferty Harvey, Pillsbury
Ms. Austin may be contacted at anne.austin@pillsburylaw.com
Ms. Dyl may be contacted at shelby.dyl@pillsburylaw.com
Ms. Harvey may be contacted at sheila.harvey@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Grad Student Sues UC Santa Cruz over Mold in Residence
November 13, 2013 —
CDJ STAFFMatthew Richert, a graduate student at UC Santa Cruz, and his wife have filed a lawsuit against UC Santa Cruz, alleging the residence they rented from the university was contaminated with mold, causing problems for them and their children.
The family noticed the signs of mold on the walls, but did not initially connect it with their daughter’s health problems, until they mentioned it to their doctor. The doctor sent a letter to the university requesting that the family be transferred to another unit if the mold problem could not be remedied. Mr. Richert made five such requests.
Eventually the university moved the family to a hotel as they investigated the unit. The Richert’s unit remains unoccupied, and a Santa Cruz spokesperson noted that 60 of the units showed mold problems.
Read the court decisionRead the full story...Reprinted courtesy of
What Are The Most Commonly Claimed Issues In Construction Defect Litigation?
April 22, 2019 —
David M. McLain - Colorado Construction Litigation BlogAs a lawyer that has spent his career defending against construction defect claims, one of the most common questions I get when counseling clients regarding risk management is: “What are the most commonly claimed issues in construction defect litigation?” Until very recently, my answer to this question has been based on my own experience and knowledge on the subject, and only vaguely reliant on empirical data.
Recently, two engineers, Elizabeth Brogan and William McConnell, along with Caroline Clevenger, an associate professor at the University of Colorado, Denver, wrote a paper entitled “Emerging Patterns in Construction Defect Litigation: A Survey of Construction Cases.” The authors analyzed 41 multifamily construction defect cases litigated in 2015, 2016 and 2017, mostly in the Denver metro area.
The authors classified the 55 most prevalent alleged defects into the following categories: structural issues; civil issues; building envelope issues; roof issues; deck, balcony and porch issues; fire protection issues; and miscellaneous issues. The authors then identified the 10 most commonly claimed construction defects, which occurred in over half of all of the cases analyzed.
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Construction Contract Clauses Only a Grinch Would Love – Part 4
November 30, 2016 —
Garret Murai – California Construction Law BlogScope, time and cost provisions may be the most important clauses in your construction contract but they’re not the only ones which can impact your bottom line. The fourth and final part in a multi-part series, here are some other important construction contract clauses that can put a damper on your holidays.
Provision: Warranty Provisions
- Typical Provision: “Subcontractor warrants to Contractor that all materials and equipment furnished shall be new unless otherwise specified and that all Work performed shall be performed in a good and workmanlike manner, of good quality and free from defects, and in conformance with industry standards, manufacturer’s recommendations and the Contract Documents. All work not conforming to these requirements, including substitutions not properly approved, shall be considered defective. Subcontractor agrees to promptly make good any and all defects due to faulty workmanship, materials and/or equipment which may appear within the Contract Documents, and if no such period is stipulated in the Contract, then for a period of one year from the date of acceptance by the Owner. Nothing herein shall shorten or limit any applicable periods of limitations including, but not limited to, those set forth in Civil Code, Part 2, Title 2, Chapter 3.”
- What it Means: Warranty periods are subject to the agreement of the parties. However, warranties are different than limitations periods, such as California’s 4 year statute of repose for patent defects and 10 year statute of repose for latent defects (note: a statute of repose is different than a statute of limitation. A statute of repose sets a deadline based on an event. So, for example, under the 10 year statute of repose for latent defects a claimant must bring a latent defect claim within 10 years following substantial completion even if the latent defect wasn’t discovered until 10 years and 1 month following substantial completion. A statute of limitation, in contrast, sets a deadline based on the occurrence of an injury or damage. So, for example, California has a 2 year statute of limitation for personal injuries, which sets a deadline of 2 years from the date of injury to bring a personal injury claim). Warranty periods are also different from limitations periods because most warranties require work to be corrected at no cost, and because many contracts include attorney’s fee provisions, breach of a warranty can give rise to claim for attorney’s fees as well.
- What You Can Do: Lower-tiered parties should examine warranty provisions to see if they are reasonable, and if not reasonable, should seek to either eliminate or limit those provisions, such as by reducing the warranty period or providing different warranty periods for different components of work, etc.
Read the court decisionRead the full story...Reprinted courtesy of