Anti-Fracking Win in N.Y. Court May Deal Blow to Industry
July 01, 2014 —
Chris Dolmetsch, Freeman Klopott and Jim Efstathiou Jr. – BloombergNew York’s cities and towns can block hydraulic fracturing within their borders, the state’s highest court ruled, dealing a blow to an industry awaiting Governor Andrew Cuomo’s decision on whether to lift a six-year-old statewide moratorium.
The case, closely watched by the energy industry, may invigorate local challenges to fracking in other states and convince the industry to stay out of New York even if Cuomo allows drilling. Pennsylvania’s highest court issued a similar ruling last year, striking down portions of a state law limiting localities’ ability to regulate drillers.
“This sends a really strong and clear message to the gas companies who have tried to buy their way into the state that these community concerns have to be addressed,” Katherine Nadeau, policy director for Environmental Advocates of New York, an anti-fracking group, said in a phone interview. “This will empower more communities nationwide.”
Mr. Dolmetsch may be contacted at cdolmetsch@bloomberg.net; Mr. Klopott may be contacted at fklopott@bloomberg.net; and Mr. Efstathiou Jr. may be contacted at jefstathiou@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Chris Dolmetsch, Freeman Klopott and Jim Efstathiou Jr., Bloomberg
Arizona Supreme Court Confirms Eight-Year Limit on Construction Defect Lawsuits
July 18, 2011 —
CDJ STAFFActing on the case of Albano v. Shea Homes Ltd. Partnership, the Arizona Supreme Court has ruled that Arizona’s eight-year statute of repose applies. The case was referred to the court by the Ninth Circuit Court of Appeals which had asked for a clarification of Arizona law. The case focused on three questions:
1. Does the filing of a motion for class certification in an Arizona court toll the statute of limitations for individuals, who are included within the class, to file individual causes of action involving the same defendants and the same subject matter?2. If so, does this class-action tolling doctrine apply to statutes of repose, and more specifically, to the statute of repose for construction defects set forth in Arizona Revised Statutes ("A.R.S.") § 12-552?3. If the doctrine applies to statutes of repose, and specifically § 12-552, may a court weigh the equities of the case in determining whether, and to what extent, an action is tolled?
The litigation at hand has a lengthy history, starting with a case referred to as “Hoffman” in 2003. The Albano plaintiffs were not able to join in Hoffman, and they filed their own lawsuit in 2006. An additional lawsuit was filed by the Albano plaintiffs in 2007. The courts decided that the Albano plaintiffs’ lawsuit was untimely.
The Arizona Supreme Court concluded that the statute of repose was the appropriate standard for this case. They noted that “the eight-year statute of repose period began to run on November 6, 1997, the date of the Town of Gilbert’s final inspection. Albano II was filed on November 5, 2007.”
The court found that the plaintiffs had waited too long for start their suit. As a result, they found it unnecessary to answer the first or third questions. Justice A. John Pelander of the Arizona Supreme Court wrote the opinion, dated June 30, 2011.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
7 Sustainability Ideas for Modular Classrooms in the Education Industry (guest post)
June 10, 2015 —
Melissa Dewey Brumback – Construction Law in North CarolinaToday, a guest post on sustainable modular classrooms from Kathy Werder, a freelance architect by profession and a researcher by nature. According to Kathy, most of her research papers focus on promoting integration that leads to sustainable and lean design and construction practices. Kathy is obsessed with the latest rage in the construction industry – modular building solutions. She is also an avid writer, and loves blogging about green buildings and portable construction units. Welcome, Kathy!
According to Wikipedia, a sustainable building refers to “ a structure and using process that is environmentally responsible and resource-efficient throughout a building’s life-cycle from sitting, to design, construction, operation, maintenance, renovation, and demolition.”
So if we accept this definition to be true, in order to make an actual sustainable building we have to consider the entire process of building right from the blueprint stage all the way to demolition, and ensure that at every step of the way there is minimal or no negative impact on the environment, especially in terms of resource efficiency.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North CarolinaMs. Brumback may be contacted at
mbrumback@rl-law.com
Determination That Title Insurer Did Not Act in Bad Faith Vacated and Remanded
March 30, 2016 —
Tred R. Eyerly – Insurance Law HawaiiIn an important decision regarding bad faith and the application of the work product doctrine to work performed by an insurer's in-house counsel, the Hawaii Supreme Court vacated the Intermediate Court of Appeals's upholding the trial court's award of summary judgment to a title insurer on the issue of bad faith. Anastasi v. Fid. Nat'l Title Ins. Co., 2016 Haw. LEXIS 30 (Feb. 4. 2016).
Llyod Anastasi loaned Alajos Nagy $2.4 million. The loan was secured by a mortgage on property. After Nagy executed the $2.4 million mortgage, a warranty deed was signed by Paul Stickney and purported to deed the property from Stickney to Nagy in exchange for $10 in consideration. Fidelity issued Anastasi a title insurance policy on the property in the amount of $2.4 million. The policy promised to provide a defense where a third party asserted a claims adverse to the interest of the insured.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Disputes Will Not Be Subject to Arbitration Provision If There Is No “Significant Relationship”
November 29, 2021 —
David Adelstein - Florida Construction Legal UpdatesAs you know from prior articles, arbitration is a creature of contract. This means if you want your disputes to be resolved by binding arbitration, as opposed to litigation, you want to make sure there is an arbitration provision in your contract. If there are certain types of disputes you do not want subject to arbitration, you want to specify those types of disputes/claims in your arbitration provision. If you are not sure, make sure to discuss the pros and cons of arbitration with your counsel when drafting and negotiating the contract. However, even with a broad arbitration provision, there are times where a dispute may still fall out of the scope of the arbitration provision, i.e., the dispute is not arbitrable. If this occurs, such dispute will be resolved by litigation. Parties that have buyer’s remove and do not want to arbitrate their dispute may try to make this argument that the dispute is not subject to the scope of the arbitration provision. There are times this argument carries weight because the dispute has no significant relationship to the agreement with the arbitration provision, as shown below.
In Deweees v. Johnson, 46 Fla. L. Weekly D2356b (Fla. 4th DCA 2021), a plaintiff purchased a home in a private residential community. The purchase contract with the developer contained a broad arbitration provision that materially provided that, “all post-closing claims, disputes, and controversies…between purchaser and seller will be resolved by binding arbitration except those arising under section G.5 and G.6 above.” Dewees, supra. Sections G.5 and G.6 provided that the purchaser will not interfere in the sales process with other purchasers and will not interfere with workmen during the construction process. There was also a workmanship and structural defect warranty for the dwelling that also contained an arbitration provision.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Federal Judge Vacates CDC Eviction Moratorium Nationwide
May 24, 2021 —
Zachary Kessler, Amanda G. Halter & Adam Weaver - Gravel2Gavel Construction & Real Estate Law BlogLate last week a federal district court judge for the District of Columbia held that the nationwide eviction moratorium issued by the Centers for Disease Control and Prevention (CDC) went beyond the agency’s statutory authority and vacated it nationwide. This decision effectively expanded a similar decision by a Texas federal court last month that found the CDC’s moratorium was an improper use of federal power but limited its decision to the litigants to that case and declined to vacate the CDC order.
The CDC eviction moratorium (the Order) was designed to halt certain cases of eviction for low-income tenants and was the most significant nationwide tenant protection for nonpayment of rent due to the COVID-19 pandemic. While the federal government has said it will appeal this week’s decision and has sought to stay its effect, it is a significant blow to the federal government’s efforts to halt evictions due to the COVID-19 pandemic. This decision may now open an avenue for landlords to begin evicting nonpaying tenants that had been halted by the eviction moratorium since mid-2020.
Reprinted courtesy of
Zachary Kessler, Pillsbury,
Amanda G. Halter, Pillsbury and
Adam Weaver, Pillsbury
Mr. Kessler may be contacted at zachary.kessler@pillsburylaw.com
Ms. Halter may be contacted at amanda.halter@pillsburylaw.com
Mr. Weaver may be contacted at adam.weaver@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Connecticut Gets Medieval All Over Construction Defects
February 10, 2012 —
CDJ STAFFThe Hartford Courant reports that Connecticut is trying a very old tactic in a construction defect suit. The law library building at the University of Connecticut suffered from leaks which have now been repaired. The state waited twelve years after was complete to file lawsuit, despite that Connecticut has a six-year statute of limitations on construction defect claims. Connecticut claims that the statute of limitations does apply to the state.
The state is arguing that a legal principle from the thirteenth century allows it to go along with its suit. As befits a medieval part of common law, the principle is called “nullum tempus occurrit regi,” or “time does not run against the king.” In 1874, the American Law Register said that nullum tempus occurrit reipublicae “has been adopted in every one of the United States” and “is now firmly established law.”
In the case of Connecticut, Connecticut Solicitor General Gregory D’Auria said that “the statute of limitations does not apply to the state.” He also noted that “the state did not ‘wait’ to file the lawsuit. The lawsuit was filed only after all other options and remedies were exhausted.”
Connecticut also argued that “nullus tempus occurrit regi” applied in another construction defect case at the York Correctional Institution. The judge in that case ruled in December 2008 to let the case proceed. But in the library case, Judge William T. Cremins ruled in February 2009 that the statute of limitations should apply to the state as well. Both cases have been appealed, with the library case moving more quickly toward the Connecticut Supreme Court.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Florida Lien Law and Substantial Compliance vs. Strict Compliance
April 20, 2017 —
David Adelstein - Florida Construction Legal UpdatesThere are literally some (or, perhaps, many!) disputes that will make you say “hmm!” The “hmm” is a euphemism for “what is a party thinking?!?” The case of Trump Endeavor 12 LLC v. Fernich, Inc., 42 Fla. L.Weekly D830a (Fla. 3d DCA 2017) is one of these cases because a party (the owner) is banking its defense on a technical “all-or-nothing” argument pertaining to whether a lienor (a supplier) substantially complied with Florida’s Lien Law because a supplier’s Notice to Owner identified the wrong general contractor. This is a challenging argument because the owner has to prove how they were adversely affected / prejudiced by the lack of substantial compliance, which is not an easy burden.
This case concerns the Trump National Doral Miami project. The project consisted of a lodge project and a separate clubhouse project, both of which had different general contractors. On the lodge project, the general contractor hired a painter which, in turn, procured paint from a supplier (the lienor). The supplier visited the project and obtained the Notice of Commencement from the owner so that it could perfect its lien rights. The owner furnished the supplier the Notice of Commencement for the clubhouse project that had a different general contractor. Relying on this Notice of Commencement, the supplier served a Notice to Owner. The Notice to Owner was timely serviced however it identified the wrong contractor – it identified the general contractor for the clubhouse project instead of the lodge project. Although the supplier later learned there was a different general contractor on the lodge project, it did not remedy the issue by serving a Notice to Owner on the correct contractor. Indeed, the contractor for the lodge project learned of the Notice to Owner furnished by the supplier and that the supplier was furnishing paint to the painting subcontractor for purposes of that project.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at